RERA extensionsNone on the filingFiling read 20 Oct 2026
Permits
Approval letters
Power NOC
Filed with the registration
Fire NOC
GBC(1)766/2012 · building height 29.85 m
✓Clear
SEIAA
Filed with the registration
Airport height NOC
Filed with the registration
KSPCB
Filed with the registration
Disputes & cases
Are there court cases or buyer complaints on this project?
Clear1 clear
Builder: EDGAR BRITTO
Court cases on the project's land
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Buyer complaints filed with K-RERA on this project
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
Buyer complaints on other projects by this builder
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
Search pending.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
The area
Comparable projects
Nearest 12 with filed prices
Location & risks
What is the location like?
Water supply, as filedLocal authorityDeclared by the promoter
The site
Flooding
Site vs nearest drain
Nearest storm drain
about 1 km from the locality centre, primary drain
Nearest lake, tank or pond
about 1 km from the locality centre, an unnamed water body
Around it
Construction & progress
How is it being built, and when will it be ready?
CompletionCompletedOccupancy certificate filed with K-RERA
Progress
Completion, architect
Completed: no quarterly return is on this phase's K-RERA filing
Work left
By component
Completed: no quarterly return is on this phase's K-RERA filing
Quarterly return
Completion
Developer
Can the developer deliver?
SoldNo return filed
Sold in the latest quarterNo return filed
Funding
Estimated cost
Land · ₹4.62 Cr 27%Development · ₹12.47 Cr
Loan & collateral
Can it be financed?
Review1 to review
Conditions
Collateral checks
Records searched to
17 May 2016
!Review
Escrow bank
Industrial Development Bank of India · Mission Road
Stage
Certified progress
Completed: no quarterly return is on this phase's K-RERA filing
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Documents filed58On K-RERA
Available58100% of filed
K-RERA only0
Approvals with a validity dateNone read
Approvals & NOCs
What we read
Fire NOCGBC(1)766/2012Filed as Fire Force Department, pp. 1, 2
Fire NOCbuilding height 29.85 mFiled as Fire Force Department, pp. 1, 2
2 pagesAvailable
8 pagesAvailable
Available
3 pages2 factsAvailable
1 pageAvailable
2 pagesAvailable
Available
Available
Available
Available
Available
Available
Available
3 pagesAvailable
1 pageAvailable
Source: K-RERA project page and the documents filed there, as read by us. 2 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. 32 Richmond is not plotted on the interactive atlas: its filing gives no coordinate precise enough to place a single building, only the surrounding locality.
Page 1
Page 1 of 1 of the encumbrance certificate. Filed with K-RERA: Encumbrance Certificate, 1 page, not in English.
No survey sketch is listed on this phase's K-RERA filing
Land record
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around the locality centre named in the filing, on satellite imagery. The outlines are the land of each survey number, not buildings. The filing names only the locality, so the marker is the locality centre, not the site. The survey plots around it are shown for orientation only; this project's survey numbers are not matched to them yet.
Not verified yet: Title opinion; Charges on the land; Landowner share of sales; How the land reached this project; Court-case search; High Court order; Charges; Schedule in the EC vs KGIS neighbours; Sketch, sanction and mutation vs KGIS map; Area on the KGIS map; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
31 Mar 2018
Registration certificates
PRM/KA/RERA/1251/446/PR/171214/001550
Not verified yet: Building plan, Land conversion, Validity, Conversion order.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Unit mix filed; Unit types; Transactions in this project; Central Bengaluru, past year; Bengaluru, past year; Central Bengaluru since 2022; This project vs Central Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields; Months to sell unsold stock; K-RERA inventory.
Water
Water at a glance
Water supply, as filed
Local authority
Distances
Approximate: locality level
Basemap: Esri, OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
about 1 km from the locality centre, primary drain
Nuisances
Distance from the site
Locality only filed: no distance from the site to show
DOSL nuisance layer
Landfill or waste transfer station
about 1.5 km from the locality centre
Sewage treatment plant
about 1 km from the locality centre, named Cubbon Park 4MLD Sewage Treatment Planet on OpenStreetMap
Quarry
None within 3 km of the locality centre
Crematorium
None within 3 km of the locality centre
Prison
None within 3 km of the locality centre
Electrical substation
about 1 km from the locality centre, named Kanteerava Stadium on OpenStreetMap
Not verified yet: Groundwater; Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Drains and lakes; Specification and Form 5; What it means; Through the year; Nearest city water main; Ground level; Metro, under construction; Road distance from the site; Six city anchors · OSRM, no traffic.
Completed, occupancy certificate filed with K-RERA
Dates
Dates
Filed dates
Schedule end
29 Jun 2018
RERA completion date
31 Mar 2018
Work began, as filed
31 Aug 2014
Specified structure
What the promoter specified · not an inspection
Building heights, fire NOC
29.85 m on the fire NOC
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Completed: no quarterly return is on this phase's K-RERA filing
Sold per quarter
Completed: no quarterly return is on this phase's K-RERA filing
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
Compliance
Escrow
Completed: no quarterly return is on this phase's K-RERA filing
Escrow and filings
Escrow bank
Industrial Development Bank of India · Mission Road
Track record
Average schedule slip
DOSL builder track
Other phases under this promoter name
263
With a filed extension or completion
119 (85 completed, 34 extended)
Average schedule slip
10 months
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid.