Overview
7hills Courtyard
Overview
7hills Courtyard
Overview
7hills Courtyard
Overview
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BIAPPA) | Sanctioned 10 Mar 2023 · No. 108/2022-23 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department |
Disputes & cases
Contract & costs
Valuation
We haven't verified this for this project yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹14.68 Cr 60.5%Development · ₹9.58 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 10 Mar 2023 | |
| Escrow bank | ICICI Bank · KUMARA PARK |
Data room
141 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | 1 | – | Review |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 1 Lakh Multi Storied Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation | Apartment | 323 sqft carpet (as filed) | Jul 2023 |
| 96 Brick Wood AvenueActive · 9% built | Cinoti ventures LLP | Apartment | 851–1,084 sqft carpet (as filed) | May 2031 |
| Amogh Anagha NivasayatiLapsed · completion date passed | Individual promoter (named in the filing) | Plot | – | Sep 2022 |
| Apranje Elite GrandeurApplied for completion 13/11/2018 | APRANJE ELITE HABITAT | Plot | – | Mar 2018 |
| Apranje Elite GrandeurApplied for completion 13/11/2018 | APRANJE ELITE HABITAT | Plot | – | Mar 2018 |
| Aratt-Escapes Phase 2Active · 67% built | ARATT CITY TOWERS LLP | Plot | ~1,670–2,120 sqft (estimate: filed carpet plus 25%) | Apr 2028 |
| Bellevue NestApplied for completion 03/03/2026 | AFFAIRAL GLOBAL FASHION PRIVATE LIMITED | Plot | – | Mar 2026 |
| Canterbury LakesideLapsed · completion date passed | Vyasti Project | Plot | – | Nov 2025 |
8 of 54 other projects in North Bengaluru, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open 7hills Courtyard in the interactive atlas
Transfer of the land
Title deed executed
No. DNH-1-04147-2018-19 · Book 1 · Consideration ₹85.0 L
Title deed filed with K-RERA, pp. 1, 5, 12 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹23.0 L
Title deed filed with K-RERA, pp. 1, 7 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹23.0 L
Title deed filed with K-RERA, pp. 1, 4 · See it in Documents
Transfer of the land
Sale deed
Survey 96
K-RERA filing, land schedule
Covers 103/1 only
Transfer of the land
Title deed registered
No. DNH-1-09129-2021-22 · Book 1 · executed 6 Jan 2022 · Consideration ₹35.6 L · Sy 103/1, Devanahalli taluk
Title deed filed with K-RERA, pp. 1, 8, 10, 14 · See it in Documents
Covers 103/1 only
Transfer of the land
Title deed executed
Consideration ₹35.6 L · Sy 103/1, Devanahalli taluk
Title deed filed with K-RERA, pp. 1, 10, 14 · See it in Documents
Covers 103/1 only
Transfer of the land
Sale deed
Survey 103/1
K-RERA filing, land schedule
Approval or registration
Land use converted
DC, Bangalore Rural · Survey 96, 103/4, 103/1
K-RERA filing, land schedule
Approval or registration
Land use converted
DC, Bangalore Rural · Survey 96, 103/4, 103/1
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BIAPPA · plan 108/2022-23
K-RERA filing, approvals
Covers 103/4 only
Approval or registration
Khata issued
E Khatha · Panchayath · Survey 103/4
K-RERA filing, land schedule
Covers 103/1 only
Approval or registration
Khata issued
E Khatha · Panchayath · Survey 103/1
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · Panchayath · Survey 96
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1250/303/PR/050723/006043
K-RERA registration
Transfer of the landApproval or registrationThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Developer's project loan | None declared |
|---|
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 96, 103/4, 103/1 | |
|---|---|---|
| Land extent, Sy 96 | 3 Acre 12 Gunta | |
| Land extent, Sy 103/4 | .28.4 Gunta | |
| Land extent, Sy 103/1 | 28.8 Gunta | |
| Khata | A Khatha · Panchayath · 6 May 2023; E Khatha · Panchayath · 4 Apr 2023; E Khatha · Panchayath · 3 May 2023 | |
| Sale deed | Dated 21 Aug 2021, 6 Jan 2022 |
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Dec 2024 |
| Land conversion | Converted 19 Jan 2023 · DC, Bangalore Rural | |
|---|---|---|
| Survey numbers | 96 · 103/4 · 103/1 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 26 km, Shankrappa Layout, MAruthi nagar |
|---|
| Nearest storm drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, Channarayapatna Ammanikere |
| Possession, agreement | 31 Dec 2024 | |
|---|---|---|
| RERA completion date | 30 Dec 2024 | Review |
| Work began, as filed | 25 Mar 2023 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Engineer's certificate, registration | Dated 2 May 2023 |
|---|
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹24.26 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹7.50 Cr | |
| Estimated cost, chartered accountant's certificate | ₹24.26 Cr, same as the filing |
| Escrow bank | ICICI Bank · KUMARA PARK | |
|---|---|---|
| Share of collections the promoter declared for escrow | 70% |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Nalluru Grama Panchayath) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 28 km, Whitefield | |
| Metro, under construction | about 10.5 km, KIA Terminal |
| Kempegowda Airport | 20.5 | 11 |
| MG Road (CBD) | 49.5 | 37 |
| Manyata Tech Park | 38.5 | 29.5 |
| ITPL, Whitefield | 37.5 | 29.5 |
| Ecospace, Bellandur ORR | 48 | 38 |
| Electronic City Ph 1 | 64.5 | 47 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |