Title & ownership
Approvals
| Building plan (Satellite Town Ring Road Planning Authority) | Sanctioned 8 Jan 2026 · No. STRRPA/TP/CC/324/2025-26 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
2BHK · avg 79 m² 58.3%3BHK · avg 101 m²
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 8 Jan 2026 | |
| Escrow bank | HDFC · Domlur Layout |
Data room
143 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | – | – | – |
| 1 Lakh Multi Storied Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation | Apartment | 323 sqft carpet (as filed) | Jul 2023 |
| 7hills CourtyardApplied for completion 22/05/2024 | 7HILLS PROPERTIES | Plot | ~1,200 sqft (estimate: filed carpet plus 25%) | Dec 2024 |
| Amogh Anagha NivasayatiLapsed · completion date passed | Individual promoter (named in the filing) | Plot | – | Sep 2022 |
| Apranje Elite GrandeurApplied for completion 13/11/2018 | APRANJE ELITE HABITAT | Plot | – | Mar 2018 |
| Apranje Elite GrandeurApplied for completion 13/11/2018 | APRANJE ELITE HABITAT | Plot | – | Mar 2018 |
| Aratt-Escapes Phase 2Active · 67% built | ARATT CITY TOWERS LLP | Plot | ~1,670–2,120 sqft (estimate: filed carpet plus 25%) | Apr 2028 |
| Bellevue NestApplied for completion 03/03/2026 | AFFAIRAL GLOBAL FASHION PRIVATE LIMITED | Plot | – | Mar 2026 |
| Canterbury LakesideLapsed · completion date passed | Vyasti Project | Plot | – | Nov 2025 |
8 of 54 other projects in North Bengaluru, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open 96 Brick Wood Avenue in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 16 May 2031 |
| Land conversion | 8 of 8 parcels converted | |
|---|---|---|
| Sy 179/9, 179/24, 179/47(old 179/10)… | Converted 29 Mar 2022 · DC Office-Bengaluru Rural | |
| Sy 179/21, 179/47(old 179/9), 179/56 | Converted 30 Jul 2024 · DC Office-Bengaluru Rural | |
| Survey numbers | 179/9 · 179/21 · 179/24 · 179/47(old 179/9) · 179/47(old 179/10) · 179/48 · 179/49 · 179/56 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Flats | Carpet per flat, average (sq ft) |
|---|---|---|
| 2BHK | 28 | 851 |
| 3BHK | 20 | 1,084 |
| Sold, Q2 2026-27 | 0 / 48 | |
|---|---|---|
| Unsold, Q2 2026-27 | 48 |
| Sowparnika Indradhanush Phase I | about 4.5 km | Locked | |
|---|---|---|---|
| Sowparnika Shivadhanush | 4.4 km | Locked | |
| Neighbourhood Tree Park | about 4.5 km | Locked | |
| Definer Upper Deck | about 4.5 km | Locked | |
| Triaxis Splendour + | about 5 km | Locked | |
| One Residences At Sobha One World Ph4 W7 And 8 | about 6 km | Locked | |
| One Residences At Sobha One World Ph5 W9,10,11 | about 6 km | Locked | |
| One Residences At Sobha One World Ph6 W12,13,14 | about 6 km | Locked | |
| Riqueza Siri | about 6 km | Locked | |
| Chaithanya Sankhya | about 6 km | Locked | |
| Godrej Woodscapes | about 7.5 km | Locked | |
| Sattva Songbird | 7.3 km | Locked |
| 96 Brick Wood Avenue This project | This project is the point the others are measured from | 16 May 2031 | 0% (0 of 48) | Not verified yet |
|---|---|---|---|---|
| Sowparnika Indradhanush Phase I | about 4.5 km | 31 May 2027 | 99% (567 of 570) | Locked |
| Sowparnika Shivadhanush | 4.4 km | 30 Nov 2027 | 99% (357 of 360) | Locked |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Nearest government-flagged flood location | 11.3 km, TRIVENI NAGAR NEAR KR PURAM |
|---|
| Nearest storm drain | 750 m to the south-west, Dakshina Pinakini, primary drain | |
|---|---|---|
| Nearest lake, tank or pond | 130 m to the north, an unnamed water body |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Gym · Power Backup · Water and Sanitation · Kids play area | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Outdoor Sports facility, built | 0% | |
| Gym, built | 0% | |
| Water and Sanitation, built | 0% | |
| Kids play area, built | 0% | |
| Covered parking per unit | 1.04 (50 covered spaces for 48 units) | |
| Power backup | Declared by the promoter |
As the promoter reported it
| Main structure | Not started · planned by 25 May 2029 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 23 Apr 2031 | |
| Club house | Not started | |
| Completion | 9% |
| Schedule end | 16 May 2031 | |
|---|---|---|
| RERA completion date | 16 May 2031 | |
| Work began, as filed | 25 Jun 2026 |
| Wall thickness | External walls: 6"; Internal walls: 6" & 4" | |
|---|---|---|
| Building heights, fire NOC | 14.95 m filed, 2 towers |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Flooring | Vitrified tiles | |
|---|---|---|
| Toilet tiles | Anti-skid ceramic tiles (floor); Ceramic tiles (walls, up to 7feet) | |
| Power backup | Provided, 15 sq m |
| Structural engineer, quarterly | Form 6 · Jul 2026, Oct 2026 (2 filed) | Clear |
|---|---|---|
| Fire safety | Filed with the registration | |
| Architect, quarterly | Form 5 · Jul 2026, Oct 2026 (2 filed) | |
| Architect's certificate, registration | Dated 31 Mar 2026 | |
| Engineer's certificate, registration | Dated 31 Mar 2026 | |
| Chartered accountant's certificate, registration | Dated 12 May 2026 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹2.84 Cr 8.5%Development · ₹30.56 Cr 91.5%
| Estimated cost, at registration | ₹33.40 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹30.06 Cr | |
| Estimated cost, chartered accountant's certificate | ₹33.40 Cr, same as the filing |
Unsold (48) 100%
| Sold, Q1 2026-27 | 0 / 48 · 48 available | |
|---|---|---|
| Sold, Q2 2026-27 | 0 / 48 · 48 available | |
| Unsold, Q2 2026-27 | 48 | |
| Sold in Q2 2026-27 | 0 |
| Escrow bank | HDFC · Domlur Layout | |
|---|---|---|
| Designated account, collected | ₹0 in Q2 2026-27 | |
| Designated account, withdrawn | ₹0 in Q2 2026-27 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Neighbourhood Tree Park |
|---|
| about 4.5 km |
| 31 Dec 2028 |
| 27% (25 of 93) |
| Locked |
| Definer Upper Deck | about 4.5 km | 31 Dec 2025 | 71% (78 of 110) | Locked |
|---|
| Triaxis Splendour + | about 5 km | 31 Dec 2026 | 57% (59 of 104) | Locked |
|---|
| One Residences At Sobha One World Ph4 W7 And 8 | about 6 km | 30 Sep 2033 | 22% (98 of 440) | Locked |
|---|
| Projects within 4 km, counted | 1 | |
|---|---|---|
| Flats in them | 49 | |
| Booked | 48 of 49 (98%) | |
| Unsold | 1 | |
| Booked a month, pooled | 2 flats | |
| Months to sell, pooled | 1 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 62 m
Taluk average; not a reading at the site.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell | |
| Nearest city water main | 9.9 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 750 m to the south-west, Dakshina Pinakini, primary drain | |
|---|---|---|
| Ground level | 875 m above sea level, plus or minus 4 m | |
| Metro, operational | 13.0 km, Whitefield | |
| Metro, under construction | 11.7 km, KIA Terminal |
| Kempegowda Airport | 21.4 | 27 | 12.1 |
| MG Road (CBD) | 29.9 | 28 | 23.9 |
| Manyata Tech Park | 29.4 | 31 | 18.1 |
| ITPL, Whitefield | 20.4 | 19 | 14.5 |
| Ecospace, Bellandur ORR | 31.0 | 32 | 22.9 |
| Electronic City Ph 1 | 44.7 | 46 | 32.0 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |