Overview
Blossom
Overview
Blossom
Overview
Blossom
Overview
Title & ownership
Approvals
| Building plan (Local Planning Authority) | Sanctioned 16 Mar 2021 · No. GBBSCPA/TP/CC/04/2020-2021 |
|---|
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Total - 1BHK · avg 29 m² 100%
Location & risks
Construction & progress
Developer
Land · ₹1.70 Cr 18.7%Development · ₹7.38 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 16 Mar 2021 | |
| Escrow bank | Karnataka Bank Ltd. · Jayanagar 4th Block |
Data room
172 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | 1 | – | Review |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| Aaradhya GardensRegistered · no quarterly update yet | SAI SAMRUDHI CONSTRUCTIONS | Apartment | 992 sqft carpet (as filed) | Dec 2028 |
| Aashirvad Siddhi PriyaFiled as completed · no completion certificate on record | SEENAPPA P | Plot | ~600–1,240 sqft (estimate: filed carpet plus 25%) | Nov 2024 |
| Aashirvad's Panchamukhi ShreyodhamaCompleted (regulator flag) | RAJESHWARI AASHIRVAD INFRA PROJECTS PRIVATE LIMITED | Plot | ~1,650 sqft (estimate: filed carpet plus 25%) | Completed |
| Aditya OrchardLapsed · completion date passed | Mangala Raghavan | Plot | ~1,200–1,800 sqft (estimate: filed carpet plus 25%) | May 2024 |
| Aprameya Brindavanam EliteCompleted (regulator flag) | Aprameya Properties Pvt Ltd | Plot | – | Completed |
| Ashwasurya Atharva RitewayCompleted (regulator flag) | RITEWAY & KUBERA PROMOTERS | Plot | ~1,200–2,400 sqft (estimate: filed carpet plus 25%) | Completed |
| Axis Banyan CountyCompleted (regulator flag) | R.Harish babu | Plot | – | Completed |
| Birla Apple SpireLapsed · completion date passed | Apple spire India LLP | Apartment | 1,667 sqft carpet (as filed) | Sep 2019 |
8 of 121 other projects in Mysore Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Blossom in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Power NOC | Filed with the registration |
|---|
| Fire department | Filed with the registration |
|---|
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | Granted · Approved 2 Feb 2024 | |
|---|---|---|
| RERA completion date | 12 Nov 2024 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 8/13 | Converted 23 May 2006 · D.C -Bangalore Rural | |
| Sy 8/P3 | Converted 7 Aug 2006 · D.C - Bangalore Rural | |
| Sy 8/P5 | Converted 31 Dec 2010 · D.C - Bangalore Rural | |
| Survey numbers | 8/13 · 8/P3 · 8/P5 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| Total - 1BHK | 44 | 13,573 |
| Good Earth Cadence | about 5 km | Locked | |
|---|---|---|---|
| Good Earth Ochre | about 5.5 km | Locked | |
| Samaya Sunshine | about 9.5 km | Locked | |
| Harivishram | about 11 km | Locked | |
| Axis Amarissa | about 11 km | Locked | |
| Sattva Springs | about 11.5 km | Locked | |
| Sumadhura Pramoda | about 11.5 km | Locked |
| Blossom This project | This project is the point the others are measured from | 12 Nov 2024 | – | Not verified yet |
|---|---|---|---|---|
| Good Earth Cadence | about 5 km | 31 Dec 2028 | 72% (104 of 145) | Locked |
| Good Earth Ochre | about 5.5 km | 31 Oct 2027 | 92% (35 of 38) | Locked |
| Samaya Sunshine | about 9.5 km |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 7.5 km, Kengeri Yellamma temple |
|---|
| Nearest storm drain | about 2.5 km to the south-east, Vrishabhavati, primary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Amenities declared | Electricity · CCTV Surveillance · Power Backup · Water and Sanitation | |
|---|---|---|
| Covered parking per unit | 0.50 (22 covered spaces for 44 units) | |
| Power backup | Declared by the promoter |
| Water supply, as filed | Borewell |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 2.5 km to the south-east, Vrishabhavati, primary drain | |
|---|---|---|
| Metro, operational | about 6 km, Challaghatta | |
| Metro, under construction | about 19 km, Kalena Agrahara |
| Completion | Completed, occupancy certificate 11 Jul 2024 |
|---|
| Schedule end | 12 Nov 2024 | |
|---|---|---|
| RERA completion date | 12 Nov 2024 | |
| Work began, as filed | 12 Nov 2021 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Provided, 12 sq m |
|---|
| Engineer's certificate, registration | Dated 11 Apr 2022 |
|---|
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹9.08 Cr |
|---|
Sold (6) 18.8%Unsold (26) 81.3%
| Flats sold, at completion | 6 | |
|---|---|---|
| Flats unsold, at completion | 26 | |
| Flats in the phase | 32 |
| Escrow bank | Karnataka Bank Ltd. · Jayanagar 4th Block |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 31 Dec 2026 |
| 33% (8 of 24) |
| Locked |
| Harivishram | about 11 km | 31 Mar 2027 | 100% (152 of 152) | Locked |
|---|
| Axis Amarissa | about 11 km | 31 Dec 2029 | 30% (24 of 81) | Locked |
|---|
| Sattva Springs | about 11.5 km | 18 Sep 2027 | 38% (25 of 66) | Locked |
|---|
| Projects within 4 km, counted | 3 (3 with an approximate location) | |
|---|---|---|
| Flats in them | 1,410 | |
| Booked | 781 of 1,410 (55%) | |
| Unsold | 629 | |
| Booked a month, pooled | 19 flats | |
| Months to sell, pooled | 34 months |
| Kempegowda Airport | 60.5 | 48.5 |
| MG Road (CBD) | 27.5 | 23 |
| Manyata Tech Park | 38 | 29.5 |
| ITPL, Whitefield | 44.5 | 37 |
| Ecospace, Bellandur ORR | 41.5 | 29 |
| Electronic City Ph 1 | 38 | 28 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 3 km to the west | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 2.5 km to the east, named Kumbalagodu on OpenStreetMap |