Overview
Cinnamon Citadel
Overview
Cinnamon Citadel
Overview
Cinnamon Citadel
Overview

Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BMICAPA) | Sanctioned 27 Feb 2025 · No. 1/50/2022-23 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹27.18 Cr 82.6%Development · ₹5.71 Cr 17.4%
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 14 Mar 2025 | |
| Building plan (BMICAPA) | Sanctioned 27 Feb 2025 | |
| Escrow bank | HDFC · Malleshwaram, Bangalore |
Data room
117 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 1410 The ResidencesCompleted (regulator flag) | Hitin Property Developments | Apartment | 1,550 sqft carpet (as filed) | Completed |
| A.N. ComfortsCompleted · OC 30-12-2019 | D. Anand Naidu | Apartment | – | Completed |
| Aarohana AlterraActive · 2% built | AAROHANA PROJECTS | Apartment | 1,133–1,936 sqft carpet (as filed) | Aug 2033 |
| AayodhyaLapsed · completion date passed | UTOCORP | Apartment | 285 sqft carpet (as filed) | Jun 2024 |
| AiekyaCompleted · OC 18-08-2025 | Avaneesh Ventures | Apartment | 1,129 sqft carpet (as filed) | Completed |
| Aikyam Emerald GroveCompleted (regulator flag) | AIKYAM VENTURES | Plot | – | Completed |
| Amberstone ElanzaActive · 63% built | SRIVARI VENTURES | Apartment | 804–1,161 sqft carpet (as filed) | Dec 2028 |
| Amberstone IlluminaActive · 54% built | SRIVARI DWELLINGS | Apartment | 793–1,071 sqft carpet (as filed) | Dec 2028 |
8 of 170 other projects in Kanakapura Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Cinnamon Citadel in the interactive atlas
Approval or registration
Land use converted
Deputy Commissioner, Bangalore · Survey 288/3
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · Jayanagar · Survey 288/3
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BMICAPA · plan 1/50/2022-23
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/310/PR/070525/007716
K-RERA registration ·
Transfer of the landApproval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 14 Mar 2025 |
|---|
| Developer's project loan | None declared |
|---|
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: Survey Sketch, 1 page, not in English.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 288/3 | |
|---|---|---|
| Land extent, Sy 288/3 | 15,960 sq m | |
| Khata | E Khatha · Jayanagar · 28 Nov 2024 |
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 2 May 2027 |
| Land conversion | Converted 17 Feb 2023 · Deputy Commissioner, Bangalore | |
|---|---|---|
| Survey numbers | 288/3 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| Projects within 4 km, counted | 19 (19 with an approximate location) | |
|---|---|---|
| Plots in them | 5,278 | |
| Booked | 2,399 of 5,278 (45%) | |
| Unsold | 2,879 | |
| Booked a month, pooled | 39 plots | |
| Months to sell, pooled | 58 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 4 km, Mantri Lake view Appartment Next to Talagattapura Lake |
|---|
| Nearest storm drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed pond |
As the promoter reported itPossession date in the agreement

| Completion | 100% |
|---|
| Possession, agreement | 2 May 2027 | |
|---|---|---|
| RERA completion date | 2 May 2027 | |
| Work began, as filed | 2 May 2025 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Engineer's certificate, registration | Dated 7 Mar 2025 |
| Estimated cost, at registration | ₹32.89 Cr | |
|---|---|---|
| Estimated cost, Form 4 Q2 2026-27 | ₹29.68 Cr |
| Escrow bank | HDFC · Malleshwaram, Bangalore | |
|---|---|---|
| Designated account, collected | ₹10.43 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹7.30 Cr in Q2 2026-27 (70% of that quarter's deposits) | |
| Amount withdrawable, Form 4 | ₹14,04,98,107 | |
| Net amount withdrawable, Form 4 | ₹99,92,371 | |
| Withdrawn from the escrow account to date | ₹15,61,63,011 |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 23.2 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 10 CGWB wells in Bengaluru South taluk read in this class | |
| Through the year | January 2025: 2.2 m (5 wells), Pre-monsoon 2025: 1.9 m (10 wells), August 2025: 1.5 m (11 wells), depth below ground of CGWB's monitoring wells in Bengaluru South taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Grama Panchayath, Agara) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 3.5 km, Silk Institute | |
| Metro, under construction | about 9.5 km, Kalena Agrahara |
| Kempegowda Airport | 54.5 | 45.5 |
| MG Road (CBD) | 21.5 | 18.5 |
| Manyata Tech Park | 30 | 26 |
| ITPL, Whitefield | 39 | 29.5 |
| Ecospace, Bellandur ORR | 26.5 | 20.5 |
| Electronic City Ph 1 | 23.5 | 17.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |