Overview
Classic Merusri Canaan Phase - II
Overview
Classic Merusri Canaan Phase - II
Overview
Classic Merusri Canaan Phase - II
Overview

Title & ownership
Approvals
| Building plan (BIAPPA) | Sanctioned 2 Sep 2025 · No. BIAAPA/TP/LAO/41/2025-26/1615 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹4.25 Cr 44.7%Development · ₹5.25 Cr 55.3%
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 2 Sep 2025 | |
| Escrow bank | HDFC · SAHAKARNAGAR |
Data room
129 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 4 cadastral survey plots named in the filing outlined. The outline is the land, not the building. 4 of 5 filed survey numbers matched, 1 found no plot, 4 plots have no filed extent to check against.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | 1 | – | Review |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
All 308 projects in Devanahalli → · Merusri Developers's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Classic Merusri Canaan Phase - II in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2030 |
| Land conversion | Converted 6 Sep 2025 · DC BENGALURU RURAL | |
|---|---|---|
| Survey numbers | 69/2 · 69/3 · 69/4 · 109 · 114 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Ekta Elements | 6.9 km | Locked |
|---|
| Classic Merusri Canaan Phase - II This project | This project is the point the others are measured from | 31 Dec 2030 | – | Not verified yet |
|---|---|---|---|---|
| Ekta Elements | 6.9 km | 31 Dec 2027 | – | Locked |
| Rent, 2BHK, 3 km | ₹24,000 /mo · 5 listings | |
|---|---|---|
| Rent per sq ft, 3 km | ₹22.6 /mo, as listed · 7 listings with a size |
| Projects within 4 km, counted | 13 (5 with an approximate location) | |
|---|---|---|
| Plots in them | 3,352 | |
| Booked | 2,152 of 3,352 (64%) | |
| Unsold | 1,200 | |
| Booked a month, pooled | 45 plots | |
| Months to sell, pooled | 22 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture | Review |
|---|---|---|
| Nearest government-flagged flood location | 18.1 km, Shankrappa Layout, MAruthi nagar | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | 1.3 km to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 90 m to the south-east, an unnamed water body |
As the promoter reported itPossession date in the agreement

| Completion | 64% | |
|---|---|---|
| Completion, accountant | 62.7% of the estimated cost spent |
| Possession, agreement | 31 Dec 2030 | |
|---|---|---|
| RERA completion date | 31 Dec 2030 | |
| Work began, as filed | 1 Sep 2025 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Mar 2026, Jun 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Chartered accountant, Form 4 | Dated 13 Oct 2026 |
| Estimated cost, at registration | ₹9.50 Cr | |
|---|---|---|
| Estimated cost, chartered accountant's certificate | ₹9.50 Cr, same as the filing | |
| Cost incurred | ₹5.96 Cr (62.7% of the estimate) |
| Escrow bank | HDFC · SAHAKARNAGAR | |
|---|---|---|
| Designated account, collected | ₹3.63 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹3.63 Cr in Q2 2026-27 (100% of that quarter's deposits) | |
| Amount withdrawable, Form 4 | ₹5,98,50,000 | |
| Net amount withdrawable, Form 4 | ₹2,35,84,275 | |
| Escrow account, Q3 2025-26 | Opened at ₹0, ₹0 deposited from sales, ₹0 withdrawn | |
| Escrow account to date, Q3 2025-26 | ₹0 deposited from sales, ₹0 withdrawn, balance ₹0 | |
| Withdrawn from the escrow account to date | ₹3,62,65,725 |
| K-RERA registrations under this promoter | 6 | |
|---|---|---|
| Marked completed | 1 | |
| Past promised date, not completed | 3 | Review |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Local authority (VILLAGE PANCHAYATH) | |
| Nearest city water main | 13.7 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 1.3 km to the south, tertiary drain | |
|---|---|---|
| Ground level | 886 m above sea level, plus or minus 4 m | |
| Metro, operational | 25.3 km, K.R. Puram | |
| Metro, under construction | 3.1 km, KIA Terminal |
| Kempegowda Airport | 12.3 | 18 | 3.2 |
| MG Road (CBD) | 40.3 | 42 | 30.5 |
| Manyata Tech Park | 35.5 | 38 | 22.6 |
| ITPL, Whitefield | 36.5 | 38 | 26.7 |
| Ecospace, Bellandur ORR | 44.3 | 50 | 33.6 |
| Electronic City Ph 1 | 59.6 | 62 | 43.2 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 2.0 km to the south-east | |
| Quarry | 2.4 km to the north-east | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 1.6 km to the south |