Title & ownership
Approvals
| Building plan (BIAPPA) | Sanctioned 22 Aug 2019 · No. BIAAPA/TP03/LAO/52/2017/18 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Projects within 4 km, counted | 1 (1 with an approximate location) |
|---|
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹10.79 Cr |
|---|
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 22 Aug 2019 | |
| Escrow bank | ICICI Bank · Margosa Road |
Data room
219 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Clay Groove in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| SEIAA | Filed with the registration |
|---|
| Airport height NOC | Filed with the registration |
|---|
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 5 Feb 2023 |
| Land conversion | 12 of 12 parcels converted | |
|---|---|---|
| Sy 293/1 | Converted 17 Dec 1997 · Deputy Commissioner, Bangalore | |
| Sy 293/2 | Converted 31 Jul 1999 · Deputy Commissioner, Bangalore | |
| Sy 293/3 | Converted 15 Sep 1997 · Deputy Commissioner, Bangalore | |
| Sy 293/4, 293/5, 295/3, 295/4 | Converted 17 Dec 1997 · Deputy Commissioner, Banglore | |
| Sy 294/1, 294/3 | Converted 16 Sep 1997 · Deputy Commissioner, Banglore | |
| Sy 294/2 | Converted 29 Oct 2001 · Deputy Commissioner, Banglore | |
| Other parcels | 2 more groups on the filing | |
| Survey numbers | 293/1 · 293/2 · 293/3 · 293/4 · 293/5 · 294/1 · 294/2 · 294/3 · 295/1 · 295/2 · 295/3 · 295/4 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Plots in them | 85 |
|---|
| Booked | 85 of 85 (100%) |
|---|
| Unsold | 0 |
|---|
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 27 km, Kondappa layout |
|---|
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | The filed pin is inside the mapped outline of Thatamachanahalli Ammanikere |
| Sewage plant | Sewage treatment plant, 75 KLD |
|---|
| RERA completion date | 5 Feb 2023 | |
|---|---|---|
| Work began, as filed | 5 Feb 2022 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Sewage plant | Sewage treatment plant, 75 KLD |
|---|
| Fire safety | Filed with the registration |
|---|
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Escrow bank | ICICI Bank · Margosa Road |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | None within 3 km | |
|---|---|---|
| Metro, operational | about 36 km, K.R. Puram | |
| Metro, under construction | about 13.5 km, KIA Terminal |
| Kempegowda Airport | 20.5 | 13.5 |
| MG Road (CBD) | 46 | 40.5 |
| Manyata Tech Park | 41 | 32.5 |
| ITPL, Whitefield | 50 | 37 |
| Ecospace, Bellandur ORR | 60.5 | 44 |
| Electronic City Ph 1 | 66 | 54 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 1 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |