~1,200–3,190 sqft (estimate: filed carpet plus 25%)
Jun 2029
Title & ownership
Who owns it, and is the title clean?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Land and deed chain
How the land reached this project
Survey
Land converted
Sale deed
Khata
Extent
Survey 13
13/2
30 Aug 2014Office of Deputy Commissioner - Bangalore Rural District
10 Jul 2025
10 Jul 20250-35
0-35
Approvals
Is it approved for its use?
Review1 to review
Building plan (BIAPPA)Sanctioned 13 Mar 2026No. BIAPA/ALO/29/14-15/25-26
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted, 13 of 13 parcelsDates and authorities below
Permits
Approval letters
Building plan (BIAPPA)
Sanctioned 13 Mar 2026 · No. BIAPA/ALO/29/14-15/25-26
Power NOC
Filed with the registration
Disputes & cases
Are there court cases or buyer complaints on this project?
Clear1 clear
Builder: SAMANVI ESTATES LLP
Court cases on the project's land
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Buyer complaints filed with K-RERA on this project
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
Buyer complaints on other projects by this builder
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Groundwater, taluk average19.3 m below groundDevanahalli taluk, July 2023
Water supply, as filedBorewellDeclared by the promoter
Metro, operationalabout 31 kmK.R. Puram
Construction & progress
How is it being built, and when will it be ready?
Clear1 clear
Completion80%As of Q2 2026-27, promoter's return
Progress
Site photos filed with K-RERA, Q2 2026-27
Developer
Can the developer deliver?
Funding
Estimated cost
Land · ₹20.18 Cr 69.8%Development · ₹8.71 Cr 30.2%
Form 4
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan (BIAPPA)
Sanctioned 13 Mar 2026
Escrow bank
RATNAKAR BANK · Yelahanka New Town
Stage
Progress as reported, by quarter
Data room
Documents filed for this project
Documents filed172On K-RERA
Available3118% of filed
K-RERA only141
Approvals with a validity dateNone read
Approvals & NOCs
K-RERA only
Available
Available
Available
Filed 31 Jul 2026K-RERA only
Filed 31 Jul 2026K-RERA only
Filed 31 Jul 2026K-RERA only
Filed 31 Jul 2026K-RERA only
Filed 17 Aug 2026Available
Filed 17 Aug 2026K-RERA only
Filed 17 Aug 2026K-RERA only
Filed 17 Aug 2026K-RERA only
Source: K-RERA project page and the documents filed there, as read by us. 25 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Highgrove in the interactive atlas
13/3
11 Nov 2014Office of Deputy Commissioner - Bangalore Rural District
10 Jul 2025
10 Jul 20250-30
0-30
13/5
11 Nov 2014Office of Deputy Commissioner - Bangalore Rural District Dev
10 Jul 2025
10 Jul 20250-19
0-19
13/6
11 Nov 2014Office of Deputy Commissioner - Bangalore Rural District Dev
10 Jul 2025
10 Jul 20250-35
0-35
13/7
11 Nov 2014Office of Deputy Commissioner - Bangalore Rural District Dev
10 Jul 2025
10 Jul 20250-20
0-20
Survey 14
14/1
3 Aug 2023Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20250-23
0-23
14/2
3 Aug 2023Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20251-17
1-17
14/3
3 Aug 2023Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20230-24
0-24
14/4
3 Aug 2023Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20250-10
0-10
Survey 15
15/2
9 Oct 2023Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20250-28
0-28
15/6
9 Oct 2023Office of Deputy Commissioner - Bangalore Rural District Dev
9 Oct 2023
9 Oct 20230-19.5
0-19.5
15/3
23 Mar 2020Office of Deputy Commissioner - Bangalore Rural District Dev
23 Mar 2020
23 Mar 20200-21
0-21
16
23 Mar 2020Office of Deputy Commissioner - Bangalore Rural District Dev
23 Jan 2025
23 Jan 20252-05
2-05
K-RERA filing, land schedule
The whole project
Approval or registration
Building plan sanctioned
BIAPPA · plan BIAPA/ALO/29/14-15/25-26
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1250/303/PR/010926/008897
K-RERA registration
Approval or registrationTransfer of the land
Described in the filing or another document; the original is not read here
Title
Charges
Developer's project loan
None declared
Boundaries
Encumbrance certificate filed with K-RERA
Page 1
Page 1 of the encumbrance certificate. Filed with K-RERA: EC FOR ALL 13 SY NOS TILL DATE.
No survey sketch is listed on this phase's K-RERA filing
Land record
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
0-35 · 10 Jul 2025; 0-30 · 10 Jul 2025; 0-19 · 10 Jul 2025; and 9 more
Sale deed
Dated 23 Mar 2020, 9 Oct 2023, 23 Jan 2025 and 1 more
Not verified yet: Title opinion; Records searched to; Charges on the land; Landowner share of sales; Title report; Schedule in the EC vs KGIS neighbours; Sketch, sanction and mutation vs KGIS map; Area on the KGIS map; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
Environmental clearance
Filed with the registration
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
Clearances pending
1, in the latest update
!Review
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
31 Mar 2028
Registration certificates
PRM/KA/RERA/1250/303/PR/010926/008897
Land use
Conversion order
Land conversion
13 of 13 parcels converted
Sy 13/2
Converted 30 Aug 2014 · Office of Deputy Commissioner - Bangalore Rural District
Sy 13/3
Converted 11 Nov 2014 · Office of Deputy Commissioner - Bangalore Rural District
Sy 13/5, 13/6, 13/7
Converted 11 Nov 2014 · Office of Deputy Commissioner - Bangalore Rural District Dev
Sy 14/1, 14/2, 14/3, 14/4
Converted 3 Aug 2023 · Office of Deputy Commissioner - Bangalore Rural District Dev
Sy 15/2, 15/6
Converted 9 Oct 2023 · Office of Deputy Commissioner - Bangalore Rural District Dev
Sy 15/3, 16
Converted 23 Mar 2020 · Office of Deputy Commissioner - Bangalore Rural District Dev
Not verified yet: Recent price, plot area; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, plot area; Form 4 certified totals; Agreements in the Form 4 sold list; Plot area vs rest, by type; Unit mix filed; Unit types; K-RERA inventory; Transactions in this project; North Bengaluru, past year; Bengaluru, past year; North Bengaluru since 2022; This project vs North Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Plot price, plotted layouts within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
The site
Zoning & hazards
Power lines and drains around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400 and 66 kV
Its corridor, to scale
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Devanahalli taluk average, July 2023: 19.3 m below ground
What it means
10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class
Through the year
January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several)
Water supply, as filed
Borewell
Distances
Within 3 km of the filed pin
Connectivity
Road distance from the site
Nuisances
Distance from the filed pin
Not verified yet: Zoning, RMP 2015; Nearest high-tension line; Specification and Form 5; Nearest city water main; Ground level.
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Completion, architect; Club house; Completion, accountant; Schedule end; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Design consultants (Form 6); Fire safety.
Estimated cost, at registration
₹28.89 Cr
Compliance
Escrow, Q2 2026-27
Escrow and filings
Escrow bank
RATNAKAR BANK · Yelahanka New Town
Designated account, collected
₹1.45 Cr in Q2 2026-27
Designated account, withdrawn
₹1.25 Cr in Q2 2026-27 (86% of that quarter's deposits)
Not verified yet: Receivable, sold plots; Cost left; Sold; Sold in the latest quarter; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Sold vs unsold; Sold per quarter; K-RERA inventory; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Site photos, Q2 2026-27
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot