Overview
Kanisha White Palace
Overview
Kanisha White Palace
Overview
Kanisha White Palace
Overview

Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BBMP) | Sanctioned 10 May 2022 · No. E-4199/2021-22 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 19 Jul 2022 | Review |
| Building plan (BBMP) | Sanctioned 10 May 2022 | |
| Escrow bank | STATE BANK OF INDIA · SME Branch Kumara Park |
Data room
138 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | 1 | 1 | Review |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | 1 | – | Review |
| 4square Park SierraActive · 29% built | 4SQUARE ESTATES | Apartment | 1,083 sqft carpet (as filed) | Dec 2029 |
| Adithya TranquilLapsed · completion date passed | ADITHYA DEVELOPERS | Apartment | – | Jan 2023 |
| Aditi North StarActive · 0% built | ADI DEVELOPERS | Apartment | – | Dec 2030 |
| Aditrri LotusExtended to 20-12-2026 | ADITRRI BUILDERS AND DEVELOPERS | Apartment | 839 sqft carpet (as filed) | Dec 2026 |
| Affinity GardeniaActive · 95% built | AFFINITY PROPERTIES LLP | Apartment | 682–853 sqft carpet (as filed) | Dec 2026 |
| After the RainCompleted · OC 30-04-2022 | Total Environment | Villa | 3,184–5,182 sqft | Completed |
| After the Rain - Phase II ACompleted · OC 10-01-2024 | Total Environment Building Systems Private Limited | Mixed development | 290–2,669 sqft carpet (as filed) | Completed |
| After the Rain Phase IIIActive · 3% built | TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD | Apartment | 2,643–6,964 sqft carpet (as filed) | Apr 2032 |
8 of 135 other projects in Yelahanka, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Kanisha White Palace in the interactive atlas
Approval or registration
Land use converted
DC, Bangalore Urban · Survey 7/5
K-RERA filing, land schedule
Transfer of the land
Title deed registered
No. HBB-1-01434-2021-22 · Book 1 · executed 12 Aug 2021 · ಚಿಕ್ಕಬೆಟ್ಟಹಳ್ಳಿ village, ಯಲಹಂಕ hobli
Title deed filed with K-RERA, pp. 1, 3, 8 · See it in Documents
Transfer of the land
Sale deed
Survey 7/5
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BBMP · plan E-4199/2021-22
K-RERA filing, approvals
Approval or registration
Khata issued
A Khatha · Local Authority · Survey 7/5
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1251/472/PR/160123/005624
K-RERA registration ·
Approval or registrationTransfer of the landTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 19 Jul 2022 |
|---|
| Developer's project loan | None declared | |
|---|---|---|
| Mortgage on the project land | None declared |
Page 1
Page 1 of 2 of the encumbrance certificate. Filed with K-RERA: EC 01-05-2004 till date, 2 pages, English.
Page 1
Page 1 of 5 of the survey sketch. Filed with K-RERA: Akaband and survey sketch, 5 pages.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 7/5 | |
|---|---|---|
| Land extent, Sy 7/5 | 11 Gunta | |
| Land area of this registration | 1,112 sq m | |
| Khata | A Khatha · Local Authority · 3 Aug 2022 | |
| Sale deed | Dated 12 Aug 2021 |
| SEIAA | Filed with the registration |
|---|
| Airport height NOC | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Dec 2026 |
| Land conversion | Converted 19 Aug 2020 · DC, Bangalore Urban | |
|---|---|---|
| Survey numbers | 7/5 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Residential 3BHK flats 37.5%Residential 2BHK flats 37.5%Residential 1BHK flats 25%
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| Residential 1BHK flats | 10 | 4,241 |
| Residential 2BHK flats | 15 | 4,532 |
| Residential 3BHK flats | 15 | 4,392 |
| Sold, Q4 2025-26 | 8 / 40 | |
|---|---|---|
| Unsold, Q4 2025-26 | 32 | |
| Months to sell, derived from filed bookings | Too few bookings to project (3 flats booked in 3 months) |
| Legacy Salvador | about 1.5 km | Locked | |
|---|---|---|---|
| 4square Park Sierra | about 1.5 km | Locked | |
| Godrej Aveline | about 2 km | Locked | |
| Century Kindle Phase 1 | about 3 km | Locked | |
| Tnm Lakeview | about 3.5 km | Locked | |
| Shriram Solitaire | about 4 km | Locked | |
| Assetz Soho & Sky | about 4.5 km | Locked | |
| Cumins Sanctum | about 4.5 km | Locked | |
| Assetz Soho & Sky Phase 1b | about 5 km | Locked | |
| Assetz Zen & Sato | about 5 km | Locked | |
| Sri Rama Enclave | about 5.5 km | Locked | |
| Sobha Dream Gardens Phase 5 - Wing 10 | about 5.5 km | Locked |
| Kanisha White Palace This project | This project is the point the others are measured from | 30 Dec 2026 | 20% (8 of 40) | Not verified yet |
|---|---|---|---|---|
| Legacy Salvador | about 1.5 km | 31 Dec 2026 | 71% (119 of 167) | Locked |
| 4square Park Sierra | about 1.5 km | 31 Dec 2029 | 8% (14 of 170) | Locked |
| Godrej Aveline | about 2 km |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 0.5 km, Kondappa layout |
|---|
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, Yelahanka Lake |
| Amenities declared | Electricity | |
|---|---|---|
| Electricity, built | 100% | |
| Covered parking per unit | 1.00 (40 covered spaces for 40 units) |
As the promoter reported it

| Main structure | 100% · planned by 30 Dec 2023 | |
|---|---|---|
| Electrical and plumbing finishing | 100% · planned by 30 Dec 2025 | |
| Completion | 100% |
| Schedule end | 30 Dec 2026 | |
|---|---|---|
| RERA completion date | 30 Dec 2026 | Review |
| Work began, as filed | 2 Sep 2022 |
| Building heights, fire NOC | 15 m filed |
|---|
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026 (2 filed) | Clear |
|---|---|---|
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026 (2 filed) |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹2.26 Cr 17.3%Development · ₹10.84 Cr 82.7%
| Estimated cost, at registration | ₹13.10 Cr |
|---|
Sold (8) 20%Unsold (32) 80%
| Sold, Q3 2025-26 | 5 / 40 · 35 available | |
|---|---|---|
| Sold, Q4 2025-26 | 8 / 40 · 32 available | |
| Unsold, Q4 2025-26 | 32 | |
| Sold in Q4 2025-26 | 3 |
| Escrow bank | STATE BANK OF INDIA · SME Branch Kumara Park | |
|---|---|---|
| Designated account, collected | ₹1.04 Cr in Q4 2025-26 | |
| Designated account, withdrawn | ₹77.0 L in Q4 2025-26 (74% of that quarter's deposits) |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 31 Mar 2031 |
| 91% (769 of 849) |
| Locked |
| Century Kindle Phase 1 | about 3 km | 14 Mar 2031 | 73% (336 of 458) | Locked |
|---|
| Tnm Lakeview | about 3.5 km | 31 Oct 2026 | 100% (36 of 36) | Locked |
|---|
| Shriram Solitaire | about 4 km | 15 May 2026 | 100% (269 of 269) | Locked |
|---|
| Projects within 4 km, counted | 46 (46 with an approximate location) | |
|---|---|---|
| Flats in them | 13,054 | |
| Booked | 8,318 of 13,054 (64%) | |
| Unsold | 4,736 | |
| Booked a month, pooled | 222 flats | |
| Months to sell, pooled | 21 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Borewell, BWSSB |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 10.5 km, Goraguntepalya | |
| Metro, under construction | about 1 km, Yelahanka |
| Kempegowda Airport | 20.5 | 16 |
| MG Road (CBD) | 17 | 14.5 |
| Manyata Tech Park | 12 | 7.5 |
| ITPL, Whitefield | 29 | 20.5 |
| Ecospace, Bellandur ORR | 32.5 | 22.5 |
| Electronic City Ph 1 | 36.5 | 31 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 0.5 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 1 km, named Wheel & Axle on OpenStreetMap |