Building plan (BBMP)Sanctioned 21 May 2020No. BBMP/ADDL.DIR/JDNORTH/0075/19-20
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted 9 Jun 2005Special DC (Revenue) Bangalore District
Permits
Approval letters
Building plan (BBMP)
Sanctioned 21 May 2020 · No. BBMP/ADDL.DIR/JDNORTH/0075/19-20
Power NOC
Filed with the registration
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Unit mix filed
3BHK 4BHK · avg 91 m² 100%
Unit types
Location & risks
What is the location like?
Clear1 clear
Groundwater, taluk average27.3 m below groundBengaluru East taluk, July 2023
Water supply, as filedBorewell, BWSSBDeclared by the promoter
Metro, operational4.0 kmHosa Road
Construction & progress
How is it being built, and when will it be ready?
CompletionCompletedOccupancy certificate, 4 Nov 2023
Progress
Completion, architect
Completed: no quarterly return is on this phase's K-RERA filing
Work left
By component
Completed: no quarterly return is on this phase's K-RERA filing
Quarterly return
Developer
Can the developer deliver?
Sold148 / 162At the completion filing, 14 Jan 2024
Sold in the latest quarterNo return filed
Funding
Estimated cost
Land · ₹10.00 Cr 7.6%
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan (BBMP)
Sanctioned 21 May 2020
Escrow bank
Union Bank of India · HSR LAYOUT
Stage
Certified progress
Completed: no quarterly return is on this phase's K-RERA filing
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Locked
147 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Disputes & cases and DocumentsUnlock
Imagery: Esri, Vantor, Earthstar Geographics
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Klassik Landmark Phase III in the interactive atlas
Approval or registration
Land use converted
Special DC (Revenue) Bangalore District · Survey 34/9, 34/10, 34/11, 34/12, 34
K-RERA filing, land schedule
2013
Survey 34/9, 34/10, 34/11, 34/12, 34
Transfer of the land
Sale deed
in favour of Klassik Enterprises Private Limited · Survey 34/9, 34/10, 34/11, 34/12, 34
K-RERA filing, land schedule
Survey 34/9, 34/10, 34/11, 34/12, 34
Approval or registration
Khata issued
A Khatha · ARO · Survey 34/9, 34/10, 34/11, 34/12, 34
K-RERA filing, land schedule
2020
Project
Approval or registration
Building plan sanctioned
BBMP · plan BBMP/ADDL.DIR/JDNORTH/0075/19-20
K-RERA filing, approvals
2022
Project
Approval or registration
RERA registration
PRM/KA/RERA/1251/446/PR/210222/004720
K-RERA registration ·
Approval or registrationTransfer of the landThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
Title
Charges
Developer's project loan
None declared
Mortgage on the project land
None declared
Boundaries
Schedule in the EC vs KGIS neighbours
Side
Schedule in the EC
KGIS neighbours
North
EC schedule not read yet
Survey 33, 35 (Junnasandra); Survey 23 (Kasavanahalli); tank
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
Share as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
30
Owner as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
████████
Owner kind, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
Individual
Share as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
30
Owner as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
████████
Owner kind, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
Individual
Share as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
30
Owner as printed, Sy 34/9, 34/10, 34/11, 34/12 & 34/13
The RTC of each filed survey
Sy. No. 34/9
████████
1
2 acres 19 guntas
Not read yet
Sy. No. 34/10
████████
5
4 acres 21 guntas
Not read yet
Sy. No. 34/11
████████
2
2 acres
Ownership
Joint development agreement
Joint development agreement number
276 of Book 1, 2013-14
Not verified yet: Title opinion, Records searched to, Charges on the land, Landowner share of sales, Title report, Sketch dimensions, Sanctioned plan area, Mutation entry, Share of sales revenue, Landowner share, Developer share, Sale deed signed by.
Fire NOC
GBC(1)520/2012
✓Clear
SEIAA
Filed with the registration
Airport height NOC
Filed with the registration
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
31 Dec 2023
Registration certificates
PRM/KA/RERA/1251/446/PR/210222/004720
Land use
Conversion order
Land conversion
Converted 9 Jun 2005 · Special DC (Revenue) Bangalore District
Survey numbers
34/9, 34/10, 34/11, 34/12 & 34
Not verified yet: Validity.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
Type
Flats
Carpet per flat, average (sq ft)
3BHK 4BHK
236
983
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
The area
Comparable projects
Filed prices nearby
Basemap: Esri, OpenStreetMap contributors
Map of 10 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Satori Residence By Genurise, price locked; Assetz Mizumi Reserve Tower A1 A2 A4, price locked; Sobha Royal Pavilion Phase 8 - Wing 15, price locked; Sobha Royal Pavilion Phase 6 - Wing 10 And 11, price locked; Sobha Royal Pavilion Phase 7 - Wing 12, 13 And 14, price locked; Adarsh Rosewood, price locked; 63 Degree East - Tower E, price locked; Birla Evara, price locked; Mana Jardin Neo, price locked; Assetz Ren & Rei, price locked.
This project
Padlock: that project's price is part of its own report
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; East Bengaluru, past year; Bengaluru, past year; East Bengaluru since 2022; This project vs East Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Bengaluru median yield.
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Main structure; Electrical and plumbing finishing; Internal roads; Club house; Completion, accountant; Foundation; Wall material; Wall thickness; Concrete / steel grade; Windows; Flooring; Toilet tiles, spec vs brochure; Wiring; Sanctioned load per flat; Sewage plant; Structural engineer, quarterly; Design consultants (Form 6); Environmental clearance.
Development · ₹121.45 Cr 92.4%
Form 4
Estimated cost, at registration
₹131.45 Cr
Estimated cost, architect's certificate
₹121.45 Cr
Estimated cost, engineer's certificate
₹120.00 Cr
Sales
Sold vs unsold, at completion
Sold (148) 91.4%Unsold (14) 8.6%
Sold per quarter
Completed: no quarterly return is on this phase's K-RERA filing
K-RERA inventory
Flats sold, at completion
148
Flats unsold, at completion
14
Flats in the phase
162
Compliance
Escrow
Completed: no quarterly return is on this phase's K-RERA filing
Escrow and filings
Escrow bank
Union Bank of India · HSR LAYOUT
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.