Overview
Nava Skanda Bellavita
Overview
Nava Skanda Bellavita
Overview
Nava Skanda Bellavita
Overview
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Transfer of the land
Title deed executed
Consideration ₹1.36 Cr · Sy 93/6 · 00 Acres 24 guntas
Title deed filed with K-RERA, pp. 1, 10, 16
Approvals
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 21 Jun 2025 | |
| Building plan (BBMP) | Sanctioned 18 Jun 2025 | |
| Escrow bank | HDFC · HEGDE NAGAR |
Data room
132 documents filed with K-RERA for this project
₹99 for this report opens Valuation, Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | 1 | 3 | Review |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Locked |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | 1 | – | Review |
| Loan & collateral | – | – | – | – |
Part of the full report. Unlock all 4 sections
| Aaptha LandmarkLapsed · completion date passed | AAPTHA VENTURES | Apartment | – | Nov 2021 |
| Adarsh PinecourtLapsed · completion date passed | Varin Infra Projects Private Limited | Apartment | 382–1,141 sqft carpet (as filed) | Mar 2026 |
| Adarsh PinecourtWithdrawn | Nusrath Unisa | Apartment | – | Nov 2023 |
| Adarsh TranqvilleLapsed · completion date passed | Varin Infra Projects Private Limited | Apartment | – | Mar 2026 |
| Adarsh Wisteria Phase 1Lapsed · completion date passed | VARIN INFRA PROJECTS PRIVATE LIMITED | Apartment | – | Aug 2023 |
| AlanovilleCompleted (regulator flag) | Goyal Hariyana Realty | Apartment | 2,251 sqft carpet (as filed) | Completed |
| Amigo PalacioActive · 40% built | AMIGO SHELTERS PVT LTD | Apartment | 1,044–1,480 sqft carpet (as filed) | Mar 2028 |
| Amigo RegencyCompleted · OC 24-08-2021 | AMIGO SHELTERS PVT LTD | Apartment | – | Completed |
8 of 185 other projects in Hennur Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Nava Skanda Bellavita in the interactive atlas
Transfer of the land
Title deed executed
Consideration ₹1.36 Cr
Title deed filed with K-RERA, pp. 1, 13 · See it in Documents
Covers 93/5 only
Approval or registration
Land use converted
Deputy Commissioner, Bangalore District · Survey 93/5
K-RERA filing, land schedule
Covers 93/1, 93/2, 93/3, 93/4, 93/6 only
Approval or registration
Land use converted
Deputy Commissioner, Bangalore District · Survey 93/1, 93/2, 93/3, 93/4 and 1 more
K-RERA filing, land schedule
Covers 93/7 only
Approval or registration
Land use converted
Deputy Commissioner, Bangalore District · Survey 93/7
K-RERA filing, land schedule
Covers 93/1, 93/2, 93/3, 93/4, 93/6, 93/7 only
Approval or registration
Khata issued
A Khatha · ARO HORAMAVU BBMP · Survey 93/1, 93/2, 93/3, 93/4 and 2 more
K-RERA filing, land schedule
Transfer of the land
Title deed executed
Sy 93/5
Title deed filed with K-RERA, pp. 1, 26 · See it in Documents
Covers 93/5 only
Approval or registration
Khata issued
A Khatha · ARO HORAMAVU BBMP · Survey 93/5
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BBMP · plan BBMP/Addl.Dir/JDNORTH/0080/24-25
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/446/PR/280725/007956
K-RERA registration ·
Transfer of the landApproval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 21 Jun 2025 |
|---|
| Developer's project loan | None declared |
|---|
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 93/1, 93/2, 93/3, 93/4, 93/5, 93/6 and 1 more | |
|---|---|---|
| Land area of this registration | 18,127 sq m | |
| Khata | A Khatha · ARO HORAMAVU BBMP · 8 Dec 2023; A Khatha · ARO HORAMAVU BBMP · 26 Aug 2024 |
Valid as of this reportValidity ended
| Building plan (BBMP) | Sanctioned 18 Jun 2025 · No. BBMP/Addl.Dir/JDNORTH/0080/24-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | KSFES/NOC/516/2024 · issued 12 Jun 2025 | Clear |
| Environmental clearance | SEIAA 146 CON 2024 · EC identification no. EC24C3801KA5757403N · issued 4 Jan 2025 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | consent order CTE-349919 · issued 31 Jul 2025 · valid until 3 Jan 2035 | Clear |
| Water and sewerage NOC (BWSSB) | issued 11 Apr 2025 | |
| Clearances pending | 1, in the latest update | Review |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2029 |
| Land conversion | 7 of 7 parcels converted | |
|---|---|---|
| Sy 93/1, 93/2, 93/3, 93/4, 93/6 | Converted 17 Nov 2023 · Deputy Commissioner, Bangalore District | |
| Sy 93/5 | Converted 1 Sep 2023 · Deputy Commissioner, Bangalore District | |
| Sy 93/7 | Converted 18 Nov 2023 · Deputy Commissioner, Bangalore District | |
| Survey numbers | 93/1 · 93/2 · 93/3 · 93/4 · 93/5 · 93/6 · 93/7 |
₹99 for this report opens Valuation, Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 3 km, Telecom layout, Ashwathnagar | |
|---|---|---|
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body |
| Amenities declared | Electricity · CCTV Surveillance · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Indoor Sports facility, built | 0% | |
| Gym, built | 0% | |
| Power Backup, built | 0% | |
| Covered parking per unit | 1.45 (522 covered spaces for 360 units) | |
| Power backup | Declared by the promoter |
As the promoter reported itPossession date in the agreement
| Main structure | 70% · planned by 31 Dec 2026 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 30 Jul 2029 | |
| Club house | Not started | |
| Completion | 14% |
| Possession, agreement | 31 Dec 2029 | |
|---|---|---|
| Schedule end | 31 Dec 2029 | |
| RERA completion date | 31 Dec 2029 | |
| Work began, as filed | 4 Jul 2025 |
| Structure | RCC framed structure | |
|---|---|---|
| Wall thickness | External walls: 6"; Internal walls: 4" | |
| Building heights, fire NOC | 30.45 m filed, 2 towers |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | UPVC windows | |
|---|---|---|
| Flooring | Vitrified tiles | |
| Wiring | Concealed copper wiring | |
| Power backup | Provided, 55 sq m |
| Structural engineer, quarterly | Form 6 · Jan 2026, Jun 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | KSFES/NOC/516/2024 · issued 12 Jun 2025 | |
| Environmental clearance | SEIAA 146 CON 2024 · EC identification no. EC24C3801KA5757403N · issued 4 Jan 2025 | |
| Architect, quarterly | Form 5 · Jan 2026, Jun 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 3 Jul 2025 · site inspected 31 Mar 2025 | |
| Engineer's certificate, registration | Dated 3 Jul 2025 | |
| Chartered accountant, Form 4 | Dated 15 Oct 2026 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹292.15 Cr |
|---|
| Estimated cost, architect's and engineer's certificates | ₹217.94 Cr |
|---|
| Cost left | ₹252.13 Cr |
|---|
Sold (63) 17.5%Unsold (297) 82.5%
| Sold, Q3 2025-26 | 20 / 360 · 340 available | |
|---|---|---|
| Sold, Q4 2025-26 | 26 / 360 · 334 available | |
| Sold, Q1 2026-27 | 49 / 360 · 311 available | |
| Sold, Q2 2026-27 | 63 / 360 · 297 available | |
| Unsold, Q2 2026-27 | 297 | |
| Sold in Q4 2025-26 | 6 | |
| Sold in Q1 2026-27 | 23 | |
| Sold in Q2 2026-27 | 14 | |
| Flats booked, Form 4 Q2 2026-27 | 63 |
| Escrow bank | HDFC · HEGDE NAGAR | |
|---|---|---|
| Designated account, collected | ₹9.87 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹6.91 Cr in Q2 2026-27 (70% of that quarter's deposits) | |
| Escrow account, Q1 2026-27 | Opened at ₹1.7 L | |
| Escrow account to date, Q1 2026-27 | ₹2.16 Cr other withdrawals | |
| Share of collections deposited in escrow | 70% | |
| Sale proceeds realised, Q2 2026-27 | ₹9,87,17,950 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 30.5 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru East taluk average, July 2023: 27.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell, BWSSB |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 7.5 km, K.R. Puram | |
| Metro, under construction | about 4.5 km, Nagawara |
| Kempegowda Airport | 23 | 16 |
| MG Road (CBD) | 14 | 11.5 |
| Manyata Tech Park | 8 | 4.5 |
| ITPL, Whitefield | 18 | 12 |
| Ecospace, Bellandur ORR | 24 | 15.5 |
| Electronic City Ph 1 | 34 | 25 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 2 km to the south, named Horamavu Agara 20MLD Sewage Treatment Plant on OpenStreetMap | |
| Quarry | about 1 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |