Title & ownership
Approvals
| Power NOC | Filed with the registration | |
|---|---|---|
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| AAI | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹3.20 Cr 68.1%Development · ₹1.50 Cr 31.9%
Loan & collateral
| Escrow bank | Canara Bank · Hosakote Branch |
|---|
Data room
87 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
All 308 projects in Devanahalli → · Nisarga Developers's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Nisarga Aero City Devanahalli Phase - 3 in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2021 |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Ekta Elements | about 9.5 km | Locked |
|---|
| Nisarga Aero City Devanahalli Phase - 3 This project | This project is the point the others are measured from | 31 Dec 2021 | – | Not verified yet |
|---|---|---|---|---|
| Ekta Elements | about 9.5 km | 31 Dec 2027 | – | Locked |
| Projects within 4 km, counted | 14 (14 with an approximate location) | |
|---|---|---|
| Plots in them | 3,820 | |
| Booked | 2,694 of 3,820 (71%) | |
| Unsold | 1,126 | |
| Booked a month, pooled | 45 plots | |
| Months to sell, pooled | 20 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 21 km, Shankrappa Layout, MAruthi nagar |
|---|
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Self development |
| RERA completion date | 31 Dec 2021 | |
|---|---|---|
| Work began, as filed | 15 Oct 2020 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Estimated cost, at registration | ₹4.70 Cr |
|---|
| Escrow bank | Canara Bank · Hosakote Branch |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | None within 3 km | |
|---|---|---|
| Metro, operational | about 29 km, K.R. Puram | |
| Metro, under construction | about 7 km, KIA Terminal |
| Kempegowda Airport | 12.5 | 7 |
| MG Road (CBD) | 38 | 34 |
| Manyata Tech Park | 33 | 26 |
| ITPL, Whitefield | 42 | 30.5 |
| Ecospace, Bellandur ORR | 52.5 | 37.5 |
| Electronic City Ph 1 | 58 | 47 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 2 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |