Building plan (BMRDA)Sanctioned 10 Nov 2023No. APA/CC/344/2023-24
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted 15 Oct 2008Special Deputy Commissioner Bangalore District
Permits
Approval letters
Building plan (BMRDA)
Sanctioned 10 Nov 2023 · No. APA/CC/344/2023-24
Power NOC
Filed with the registration
Fire NOC
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Valuation
What is it worth?
Locked
Recent price, super built-upNot verified yet
Recent price, carpet₹ ••,•••
Phase 1 → Phase 2Not verified yet
Gross yield, per sq ftNot verified yet
This project
Price
Price per sq ft, super built-up
Not verified yet
Location & risks
What is the location like?
Review3 to review
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedBorewell, Local authority (Bommasandra)Declared by the promoter
Metro, operational
Construction & progress
How is it being built, and when will it be ready?
Clear1 clear
Completion61%As of Q2 2026-27, promoter's return
Progress
Completion, as the promoter reported it
Developer
Can the developer deliver?
Clear2 clear
Sold414 / 414✓ClearClear
Sold in Q2 2026-270✓ClearClear
Funding
Estimated cost
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan (BMRDA)
Sanctioned 10 Nov 2023
Escrow bank
HDFC · BENGALURU - RICHMOND ROAD
Stage
Progress as reported, by quarter
Data room
Documents filed for this project
Locked
162 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Valuation, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Valuation, Title & ownership, Disputes & cases and DocumentsUnlock
DOSL Score
59/100
Red flag
38th percentile in Electronic CityHigher than 17 of 46 scored projects
Shriram Sapphire is a nice project with good planning and a pleasant environment. I liked the layout, amenities, and overall quality of the project. The team was helpful and explained everything clearly. It feels like a good place to live…
NNarasimha jayson10 Sep 2026★★★★★
Lake sides view was amazing place to live comfortably while many amazing place. Still construction going on
KKirti Anand11 Aug 2026★★★★★
Very poor RM service. The support has been extremely disappointing and the team has been of little help. Ranjith Kumar S was very rude and was not able to provide any proper assistance. They are also raising the demand by almost 85% even…
Electricity · CCTV Surveillance · Gym · Power Backup · Water and Sanitation
Club House, built
0%
!Review
Electricity, built
30%
Swimming Pool, built
0%
Parks, built
0%
Water and Sanitation, built
0%
Covered parking per unit
1.17 (486 covered spaces for 414 units)
Power backup
Declared by the promoter
Around it
Water
Groundwater, Anekal taluk average
Not verified yet: Nearest high-tension line, Kitchen handover, Sewage plant.
As the promoter reported it
Site photos filed with K-RERA, Q1 2026-27
Work left
By component, Q2 2026-27
Quarterly return, Q2 2026-27
Main structure
80% · planned by 17 Sep 2026
Electrical and plumbing finishing
10% · planned by 20 Jan 2028
Club house
Not started
Completion
61%
Dates
Dates
Filed dates
Schedule end
5 Nov 2028
RERA completion date
5 Nov 2028
Work began, as filed
1 Dec 2023
Specified structure
What the promoter specified · not an inspection
Building heights, fire NOC
23.95 m (Tower A), 26.95 m (Tower B, Tower C, Tower D, Tower E, Tower F) on the fire NOC · filed: A 23.95 m, B 23.95 m, C 23.95 m, D 26.95 m, E 23.95 m, F 23.95 m
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Land · ₹21.21 Cr 12.5%Development · ₹148.83 Cr 87.5%
Form 4
Estimated cost, at registration
₹170.04 Cr
Estimated cost, architect's and engineer's certificates
₹170.04 Cr, same as the filing
Cost incurred
₹145.43 Cr
Sales
Sold vs unsold, Q2 2026-27
Sold (414) 100%
Sold per quarter
K-RERA inventory
Sold, Q3 2025-26
414 / 414 · 0 available
Sold, Q4 2025-26
414 / 414 · 0 available
Sold, Q1 2026-27
414 / 414 · 0 available
Sold, Q2 2026-27
414 / 414 · 0 available
Unsold, Q2 2026-27
0
Sold in Q4 2025-26
0
Sold in Q1 2026-27
0
Sold in Q2 2026-27
0
Compliance
Escrow, Q2 2026-27
Escrow and filings
Escrow bank
HDFC · BENGALURU - RICHMOND ROAD
Designated account, collected
₹27.21 Cr in Q2 2026-27
Designated account, withdrawn
₹18.77 Cr in Q2 2026-27 (69% of that quarter's deposits)
Track record
DOSL builder track
K-RERA registrations under this promoter
16
Marked completed
5
Past promised date, not completed
6
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid; Average schedule slip.
Site photos, Q1 2026-27
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Anekal taluk average, July 2023: 21.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class
Through the year
January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several)
Water supply, as filed
Borewell, Local authority (Bommasandra)
Nearest city water main
2.7 km
!Review
Distances
Within 3 km
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.