Overview
Sipani City Phase-1
Overview
Sipani City Phase-1
Overview
Sipani City Phase-1
Overview
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | Aditya Birla Capital ltd · ₹17.00 Cr disbursed | |
|---|---|---|
| Records searched to | 2 May 2024 | Review |
| Building plan (BMRDA) | Sanctioned 29 Aug 2025 | |
| Escrow bank | HDFC · kasturba road |
Data room
193 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | – | – | 5 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | 1 | 1 | Review |
| Loan & collateral | – | 1 | – | Review |
| "new Dawn"Lapsed · completion date passed | M/s.Bricks & Milestones | Apartment | 1,932 sqft carpet (as filed) | Apr 2023 |
| 36 Park AvenueCompleted (regulator flag) | R K Developers | Plot | ~800–2,000 sqft (estimate: filed carpet plus 25%) | Completed |
| 36 Park Avenue Phase IIICompleted (regulator flag) | R K DEVELOPERS | Plot | ~1,200–2,000 sqft (estimate: filed carpet plus 25%) | Completed |
| 36 Park Avenue Phase-IICompleted (regulator flag) | R K DEVELOPERS | Plot | ~1,200–2,000 sqft (estimate: filed carpet plus 25%) | Completed |
| 42 Mark ThreeCompleted · OC 19-02-2024 | LIVING STRUCTURES | Apartment | 2,041 sqft carpet (as filed) | Completed |
| 42 MarquisCompleted (regulator flag) | LIVING STRUCTURES | Plot | – | Completed |
| 63 Degree East - Tower ACompleted · OC 03-06-2025 | APG Intelli Homes Private Limited | Apartment | 918 sqft carpet (as filed) | Completed |
| 63 Degree East - Tower BLapsed · completion date passed | APG Intelli Homes Private Limited | Apartment | 833 sqft carpet (as filed) | Jun 2023 |
8 of 513 other projects in Sarjapur Road, A to Z. Status is taken from each project's own filing.
All 534 projects in Sarjapur Road → · sipani properties pvt ltd's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sipani City Phase-1 in the interactive atlas
Transfer of the land
Title deed executed
Sy 22/2, Sarjapura hobli, Anekal taluk
Title deed filed with K-RERA, pp. 1, 51 · See it in Documents
Transfer of the land
Sale deed
in favour of SIPANI PROPERTIES PVT LTD, REP BY M N MADHAVA MURTHY · Survey 150200102200820061
K-RERA filing, land schedule
Transfer of the land
Title deed executed
Consideration ₹2.70 Cr · Sy 2, Madappanahalli village, Sarjapura hobli, Anekal taluk
Title deed filed with K-RERA, pp. 1, 11, 17 · See it in Documents
Transfer of the land
Sale deed
in favour of sipani properties pvt ltd reprented by Madhava Murthy M N · Survey 150200102200820062
K-RERA filing, land schedule
Approval or registration
Land use converted
Dy commissioner · Survey 150200102200820062
K-RERA filing, land schedule
Approval or registration
Land use converted
DY COMMISSIONER · Survey 150200102200820061
K-RERA filing, land schedule
Approval or registration
Land use converted
Dy commissioner · Survey 150200102200820064
K-RERA filing, land schedule
Transfer of the land
Sale deed
in favour of sipani properties pvt ltd represented by Madhava murthy M N · Survey 150200102200820064
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · PDO MADAPPAN HALLI · Survey 150200102200820062
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · PDO MADAPPANAHALI · Survey 150200102200820061
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · PDO MADAPPAN HALLI · Survey 150200102200820064
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BMRDA · plan APA/cc/210/2025-26
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/308/PR/171025/008179
K-RERA registration ·
Transfer of the landApproval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 2 May 2024 |
|---|
| Developer's project loan | Aditya Birla Capital ltd · ₹17.00 Cr disbursed |
|---|
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 150200102200820064, 150200102200820062, 150200102200820061 | |
|---|---|---|
| Land extent, Sy 150200102200820064 | 1 acre | |
| Land extent, Sy 150200102200820062 | 3 acre 31 gunts | |
| Land extent, Sy 150200102200820061 | 6 ACRES | |
| Land area of this registration | 41,425 sq m | |
| Khata | E Khatha · PDO MADAPPAN HALLI · 4 Jan 2025; E Khatha · PDO MADAPPAN HALLI · 2 Jan 2025; E Khatha · PDO MADAPPANAHALI · 2 Jan 2025 | |
| Sale deed | Dated 13 Jul 2022, 14 Feb 2023, 15 Jun 2024 | |
| Sale deed in favour of | sipani properties pvt ltd represented by Madhava murthy M N, sipani properties pvt ltd reprented by Madhava Murthy M N, SIPANI PROPERTIES PVT LTD, REP BY M N MADHAVA MURTHY | |
| Title deed | Sy 24/6, Sarjapura hobli, Anekal taluk |
Valid as of this reportValidity ended
| Building plan (BMRDA) | Sanctioned 29 Aug 2025 · No. APA/cc/210/2025-26 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | KSFES/NOC/212/2025 · issued 4 Aug 2025 | Clear |
| Environmental clearance (1 of 3) | SEIAA 156 CON 2025 | Clear |
| Environmental clearance (2 of 3) | SEIAA 156 CON 2025 · EC identification no. EC25C3801KA5145920N · issued 25 Sep 2025 | Clear |
| Environmental clearance (3 of 3) | SEIAA 156 CON 2025 · issued 25 Sep 2025 | Clear |
| Airport height NOC | NOC ID HOSU/SOUTH/B/011025/1479305 · issued 14 Feb 2025 · valid until 13 Feb 2033 | Clear |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2030 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 150200102200820064 | Converted 14 Jun 2024 · Dy commissioner | |
| Sy 150200102200820062 | Converted 19 Jul 2023 · Dy commissioner | |
| Sy 150200102200820061 | Converted 8 Nov 2023 · DY COMMISSIONER | |
| Survey numbers | 150200102200820064 · 150200102200820062 · 150200102200820061 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
1 ,2,3BHK · avg 80 m² 54.3%2BHK 25.1%3BHK 19.7%1BHK 0.8%
| 1 ,2,3BHK | 771 | 6,61,916 |
| 1BHK | 12 | – |
| 2BHK | 356 | – |
| 3BHK | 280 | – |
| Sold, Q2 2026-27 | 612 / 771 | |
|---|---|---|
| Unsold, Q2 2026-27 | 159 | |
| Months to sell, derived from filed bookings | 4 months |
| Leafy Delight | about 1 km | Locked | |
|---|---|---|---|
| Leafy Avenue | about 3 km | Locked | |
| Coevolve Florenza | about 3.5 km | Locked | |
| Vasudharini Nest | about 3.5 km | Locked | |
| Jeevan's Allure | about 5 km | Locked | |
| Royal Nest | about 5.5 km | Locked | |
| Inspira Infinity | about 7 km | Locked | |
| Sobha Windsor Phase 4 Wing 9, 10 And 11 | about 7 km | Locked | |
| Sobha Windsor Phase 2 Wing 3, 4 And 5 | about 7 km | Locked | |
| Bilva Phase-II By Bhavisha Homes | about 7 km | Locked | |
| Sowparnika Ashiyana Phase II | about 7 km | Locked | |
| Sobha Windsor Phase 3 Wing 6, 7 And 8 | about 7 km | Locked |
| Sipani City Phase-1 This project | This project is the point the others are measured from | 31 Dec 2030 | 79% (612 of 771) | Not verified yet |
|---|---|---|---|---|
| Leafy Delight | about 1 km | 31 Mar 2028 | 24% (16 of 67) | Locked |
| Leafy Avenue | about 3 km | 31 Dec 2028 | 11% (8 of 71) | Locked |
| Coevolve Florenza | about 3.5 km | 31 Dec 2027 |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 7 km, Varthur police station |
|---|
| Nearest storm drain | about 1 km, Dakshina Pinakini, primary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed pond |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Outdoor Sports facility, built | 0% | |
| Swimming Pool, built | 0% | |
| Parks, built | 5% | |
| Water and Sanitation, built | 10% | |
| Covered parking per unit | 0.88 (679 covered spaces for 771 units) | |
| Power backup | Declared by the promoter |
As the promoter reported it
| Main structure | 21% · planned by 31 Dec 2029 | |
|---|---|---|
| Electrical and plumbing finishing | 5% · planned by 30 Jun 2030 | |
| Club house | Not started | |
| Completion | 35% | |
| Completion, accountant | 34.6% of the estimated cost spent |
| Schedule end | 28 Dec 2030 | |
|---|---|---|
| RERA completion date | 31 Dec 2030 | |
| Work began, as filed | 15 Oct 2025 |
| Building heights, fire NOC | filed: A 58.25 m, B 58.25 m, C 43.5 m, D 43.25 m, E 58.25 m, F 58.25 m, G 58.25 m, H 58.25 m |
|---|
| Power backup | Provided, 92.29 sq m |
|---|
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | KSFES/NOC/212/2025 · issued 4 Aug 2025 | |
| Environmental clearance (1 of 3) | SEIAA 156 CON 2025 | |
| Environmental clearance (2 of 3) | SEIAA 156 CON 2025 · EC identification no. EC25C3801KA5145920N · issued 25 Sep 2025 | |
| Environmental clearance (3 of 3) | SEIAA 156 CON 2025 · issued 25 Sep 2025 | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 8 Sep 2025 | |
| Engineer's certificate, registration | Dated 8 Sep 2025 | |
| Chartered accountant's certificate, registration | Dated 11 Sep 2025 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹28.07 Cr 6.4%Development · ₹407.31 Cr 93.6%
| Estimated cost, at registration | ₹435.38 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹435.00 Cr | |
| Estimated cost, engineer's certificate | ₹435.38 Cr | |
| Estimated cost, Form 4 Q2 2026-27 | ₹435.38 Cr | |
| Cost incurred | ₹150.75 Cr (34.6% of the Form 4 Q2 2026-27 estimate) | |
| Cost left | ₹284.63 Cr | |
| Receivable, sold flats | ₹301.75 Cr |
Sold (612) 79.4%Unsold (159) 20.6%
| Sold, Q3 2025-26 | 253 / 771 · 518 available | |
|---|---|---|
| Sold, Q4 2025-26 | 155 / 771 · 616 available | |
| Sold, Q1 2026-27 | 108 / 771 · 663 available | |
| Sold, Q2 2026-27 | 612 / 771 · 159 available | |
| Unsold, Q2 2026-27 | 159 | |
| Sold in Q4 2025-26 | 98 bookings cancelled or corrected (253 → 155 sold) | |
| Sold in Q1 2026-27 | 47 bookings cancelled or corrected (155 → 108 sold) | |
| Sold in Q2 2026-27 | 504 |
| Escrow bank | HDFC · kasturba road | |
|---|---|---|
| Designated account, collected | ₹106.68 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹106.68 Cr in Q2 2026-27 (100% of that quarter's deposits) |
| K-RERA registrations under this promoter | 8 | |
|---|---|---|
| Marked completed | 2 | |
| Past promised date, not completed | 4 | Review |
| Other phases under this promoter name | 5 | |
| With a filed extension or completion | 5 (1 completed, 4 extended) | |
| Average schedule slip | 26 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 48% (149 of 309) |
| Locked |
| Vasudharini Nest | about 3.5 km | 31 Mar 2028 | 31% (26 of 84) | Locked |
|---|
| Jeevan's Allure | about 5 km | 31 Jul 2027 | 32% (49 of 152) | Locked |
|---|
| Royal Nest | about 5.5 km | 30 Jun 2028 | 9% (9 of 104) | Locked |
|---|
| Projects within 4 km, counted | 14 (14 with an approximate location) | |
|---|---|---|
| Flats in them | 1,271 | |
| Booked | 451 of 1,271 (35%) | |
| Unsold | 820 | |
| Booked a month, pooled | 32 flats | |
| Months to sell, pooled | 26 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 28.7 m
Taluk average; not a reading at the site.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class | |
| Through the year | January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several) | |
| Water supply, as filed | Borewell, Local authority (Madappanahalli panchayat) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1 km, Dakshina Pinakini, primary drain | |
|---|---|---|
| Metro, operational | about 9.5 km, Channasandra | |
| Metro, under construction | about 12 km, Kodibeesanahalli |
| Kempegowda Airport | 48 | 32.5 |
| MG Road (CBD) | 26.5 | 23 |
| Manyata Tech Park | 30.5 | 24.5 |
| ITPL, Whitefield | 15 | 10.5 |
| Ecospace, Bellandur ORR | 17.5 | 14 |
| Electronic City Ph 1 | 31 | 17 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |