Photo: Shankar Shankar| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | 1 | Clear |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | 2 | |
| 10xLapsed · completion date passed | M/S. MAZ-RD BUILDERS AND DEVELOPERS PRIVATE LIMITED | Apartment | – | Sep 2024 |
| 10x ELapsed · completion date passed | MAZ RD Builders and Developers Private Limited | Apartment | 478 sqft carpet (as filed) | Dec 2024 |
| A.S.R.S ParadiseLapsed · completion date passed | A.S. Builders | Apartment | – | Jan 2021 |
| Aadya HeightsLapsed · completion date passed | WHITEWINDS CONSTRUCTIONS PRIVATE LIMITED | Apartment | 917–1,080 sqft carpet (as filed) | Dec 2025 |
| Aakriti EmeraldActive · 51% built | AAKRITI PROJECTS | Apartment | 694–1,137 sqft carpet (as filed) | Aug 2028 |
| Aakruthi NestActive · 35% built | KRITI BUILDERS AND DEVELOPERS | Apartment | 608–837 sqft carpet (as filed) | Dec 2028 |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Page 1
Page 1 of 17 of the encumbrance certificate. Filed with K-RERA: Encumbrance Certificate, 17 pages.
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 20 May 2021 |
Disputes & cases
Builder: M/s Atharva Ventures
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None found. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹13.48 Cr 88.8%Development · ₹1.70 Cr 11.2%
Loan & collateral
| Escrow bank | Allahabad Bank · Rajajinagar |
|---|
Data room
Source: K-RERA project page and the documents filed there, as read by us. 2 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Review |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Aban DesireRegistered · no quarterly update yet | ABAN DEVELOPERS PRIVATE LIMITED | Apartment | 801–1,054 sqft carpet (as filed) | Dec 2028 |
| Adarsh ParadiseActive · 93% built | A1 BUILDERS | Apartment | 668–924 sqft carpet (as filed) | Dec 2026 |
8 of 328 other projects in Old Madras Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Srinivasa Enclave in the interactive atlas
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Land area of this registration | 33,133 sq m |
|---|
| Projects within 4 km, counted | 23 (16 with an approximate location) | |
|---|---|---|
| Plots in them | 5,000 | |
| Booked | 3,099 of 5,000 (62%) | |
| Unsold | 1,901 | |
| Booked a month, pooled | 110 plots | |
| Months to sell, pooled | 16 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main), at the filed pin | Clear |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 66 kV, 400 m from the filed location | Clear |
| Nearest government-flagged flood location | 9.7 km, SIDDHARTHA LAYOUT KADUGODI |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 440 m to the east, an unnamed water body |
| RERA completion date | 20 May 2021 | |
|---|---|---|
| Work began, as filed | 21 Aug 2018 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Estimated cost, at registration | ₹15.18 Cr |
|---|
| Escrow bank | Allahabad Bank · Rajajinagar |
|---|
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 62 m
Taluk average; not a reading at the site.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Self development | |
| Nearest city water main | 6.9 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | None within 3 km | |
|---|---|---|
| Ground level | 890 m above sea level, plus or minus 4 m | |
| Metro, operational | 10.3 km, Whitefield | |
| Metro, under construction | 16.0 km, Saraswathi Nagar |
| Kempegowda Airport | 34.6 | 35 | 17.9 |
| MG Road (CBD) | 27.9 | 27 | 25.0 |
| Manyata Tech Park | 27.4 | 29 | 20.8 |
| ITPL, Whitefield | 18.4 | 18 | 12.5 |
| Ecospace, Bellandur ORR | 29.0 | 31 | 21.5 |
| Electronic City Ph 1 | 42.8 | 45 | 29.7 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.1 km to the west, named Hoskote on OpenStreetMap |