Overview
V.R Mega Township
Overview
V.R Mega Township
Overview
V.R Mega Township
Overview
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Survey | Land converted | Sale deed | Khata | Extent |
|---|---|---|---|---|
| Survey 84 | ||||
| 84/7 | ||||
Approvals
| Building plan (Hoskote Planning Authority) | Sanctioned 6 Mar 2025 · No. HPA/LAO/09/2024-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹7.13 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 31 Jul 2024 | Review |
| Building plan | Sanctioned 6 Mar 2025 | |
| Escrow bank | Canara Bank · HOSKOTE |
Data room
281 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | 1 | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | 1 | – | Review |
| 10xLapsed · completion date passed | M/S. MAZ-RD BUILDERS AND DEVELOPERS PRIVATE LIMITED | Apartment | – | Sep 2024 |
| 10x ELapsed · completion date passed | MAZ RD Builders and Developers Private Limited | Apartment | 478 sqft carpet (as filed) | Dec 2024 |
| A.S.R.S ParadiseLapsed · completion date passed | A.S. Builders | Apartment | – | Jan 2021 |
| Aadya HeightsLapsed · completion date passed | WHITEWINDS CONSTRUCTIONS PRIVATE LIMITED | Apartment | 917–1,080 sqft carpet (as filed) | Dec 2025 |
| Aakriti EmeraldActive · 51% built | AAKRITI PROJECTS | Apartment | 694–1,137 sqft carpet (as filed) | Aug 2028 |
| Aakruthi NestActive · 35% built | KRITI BUILDERS AND DEVELOPERS | Apartment | 608–837 sqft carpet (as filed) | Dec 2028 |
| Aban DesireRegistered · no quarterly update yet | ABAN DEVELOPERS PRIVATE LIMITED | Apartment | 801–1,054 sqft carpet (as filed) | Dec 2028 |
| Adarsh ParadiseActive · 93% built | A1 BUILDERS | Apartment | 668–924 sqft carpet (as filed) | Dec 2026 |
8 of 328 other projects in Old Madras Road, A to Z. Status is taken from each project's own filing.
All 345 projects in Old Madras Road → · Vr Ventures's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open V.R Mega Township in the interactive atlas
| 3 Feb 2023 |
| 14 Mar 202517 Guntas · Revenue department,Hoskote |
| 17 Guntas |
| 84/8 | 7 Mar 2024District Commissioner, Bangalore Rural | 5 Feb 2022 | 18 Mar 20228.50 guntas · Revenue department,Hoskote | 8.50 guntas |
|---|
| 84/9 | 7 Mar 2023District Commissioner, Bangalore Rural | 5 Feb 2022 | 7 Jun 20258.50 Guntas · Revenue department,Hoskote | 8.50 Guntas |
|---|
| Survey 85 | ||||
|---|---|---|---|---|
| 85/6 | 7 Mar 2024District Commissioner, Bangalore Rural | 3 Nov 2023 | 16 Nov 20236 Guntas · Revenue department,Hoskote | 6 Guntas |
| 85/9 | 7 Mar 2024District Commissioner, Bangalore Rural | 3 Jun 2025 | 22 Jun 20237 Guntas · Revenue department,Hoskote | 7 Guntas |
| 85/11 | 8 May 2024District Commissioner, Bangalore Rural | 29 Sep 1977 | 6 Nov 201935.75 Guntas · Revenue department,Hoskote | 35.75 Guntas |
| 85/12 | 7 Mar 2024District Commissioner, Bangalore Rural | 3 Nov 2023in favour of Ramesh Naidu & Surendra | 16 Nov 202335.50 Guntas · Revenue department,Hoskote | 35.50 Guntas |
| Survey 86 | ||||
|---|---|---|---|---|
| 86/1 | 7 Mar 2024District Commissioner, Bangalore Rural | 6 Dec 2013 | 29 Mar 201413 guntas · Revenue department,Hoskote | 13 Guntas |
| 86/2, 86/3 | 7 Mar 2024District Commissioner, Bangalore Rural | 9 Dec 2020 | 28 Jan 20216 guntas · Revenue department,Hoskote | 6 Guntas + 6 Guntas |
| 86/4, 86/5 | 7 Mar 2024District Commissioner, Bangalore Rural | 9 Dec 2020 | 28 Jan 20216 Guntas · Revenue department,Hoskote | 6 Guntas + 6 GUNTAS |
| Survey 89 | ||||
|---|---|---|---|---|
| 89/1 | 8 Feb 2024District Commissioner, Bangalore Rural | 18 Apr 1991 | 24 Sep 201929 guntas · Revenue department,Hoskote | 29 guntas |
| 89/2 | 8 Feb 2024District Commissioner, Bangalore Rural | 23 Dec 2020in favour of RAMESH NAIDU & Others | 5 Feb 20211 Acres 4 Guntas · Revenue department,Hoskote | 1 Acres 4 Guntas |
| 89/3 | 8 Feb 2024District Commissioner, Bangalore Rural | 6 Jun 1989 | 24 Sep 201834 Guntas · Revenue department,Hoskote | 34 Guntas |
| 89/4 | 8 Feb 2024District Commissioner, Bangalore Rural | 17 May 2018in favour of N Harish & N Suresh | 4 Nov 20211 Acres 04 Guntas · Revenue department,Hoskote | 1 Acres 04 Guntas |
| 89/5 | 8 Feb 2024District Commissioner, Bangalore Rural | 11 Nov 2021 | 2 Mar 202419 Guntas · Revenue department,Hoskote | 19 Guntas |
| 89/6 | 8 Feb 2024District Commissioner, Bangalore Rural | 11 Nov 2021 | 2 Mar 20246 Guntas · Revenue department,Hoskote | 6 Guntas |
| Survey 121 | ||||
|---|---|---|---|---|
| 121/1B2 | 10 Jul 2024District Commissioner, Bangalore Rural | 1 Jun 1971 | 12 Feb 20197.50 Guntas · Revenue department,Hoskote | 7.50 Guntas |
| 121/1B3 | 8 Feb 2024District Commissioner, Bangalore Rural | 25 Jan 2023 | 27 Feb 20237.75 Guntas · Revenue department,Hoskote | 7.75 Guntas |
| 121/2E | 6 Jul 2024District Commissioner, Bangalore Rural | 22 Dec 1967 | 3 Jun 20092 Guntas · Revenue department,Hoskote | 2 Guntas |
| 121/5B | 7 Mar 2024District Commissioner, Bangalore Rural | 22 Dec 1967 | 11 Jun 200923 Guntas · Revenue department,Hoskote | 23 Guntas |
| 121/6 | 8 Feb 2024District Commissioner, Bangalore Rural | 29 Jun 2001 | 24 Sep 201820 Guntas · Revenue department,Hoskote | 20 Guntas |
| 122/3B | 8 Jan 2024District Commissioner, Bangalore Rural | 22 Dec 1967 | 7 Jun 20251 Acres 2 Guntas · Revenue department,Hoskote | 1 Acres 2 Guntas |
|---|
| Survey 123 | ||||
|---|---|---|---|---|
| 123/4 | 17 Nov 2023District Commissioner, Bangalore Rural | 26 Jun 2020 | 23 May 202420 Guntas · Revenue department,Hoskote | 20 Guntas |
| 123/6 | 29 Jun 2024District Commissioner, Bangalore Rural | 26 Jun 2020 | 23 May 20246 guntas · Revenue department,Hoskote | 6 guntas |
K-RERA filing, land schedule
Deeds read, and the whole project
Transfer of the land
Title deed registered
No. HSK-1-07959-2020-21 · Book 1 · executed 27 Nov 2020
Title deed filed with K-RERA, pp. 1, 10 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹45.0 L · Sy 89/2, Kannurahalli village, Kasaba hobli, Hoskote taluk · 1 Acre 04 Guntas
Title deed filed with K-RERA, pp. 1, 7, 10 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹8.3 L · Sy 89/3; 89/1, Kannurahalli village, Kasaba hobli, Hoskote taluk
Title deed filed with K-RERA, pp. 1, 7, 10 · See it in Documents
Transfer of the land
Title deed executed
Sy 89/3; 89/1, Kannurahalli village, Kasaba hobli, Hoskote taluk
Title deed filed with K-RERA, pp. 1, 11 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹45.0 L
Title deed filed with K-RERA, pp. 1, 9 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹9.6 L · Sy 85/9; 85/4, Kannurahalli village, Kasaba hobli, Hoskote taluk · 7 Guntas
Title deed filed with K-RERA, pp. 1, 5, 9 · See it in Documents
Transfer of the land
Title deed registered
No. HSK-1-10935-2023-24 · Book 1 · Consideration ₹93.4 L · Kannurahalli village, Kasaba hobli, Hoskote taluk
Title deed filed with K-RERA, pp. 4, 7, 11 · See it in Documents
Approval or registration
Building plan sanctioned
Hoskote Planning Authority · plan HPA/LAO/09/2024-25
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1250/304/PR/160725/007934
K-RERA registration
Approval or registrationTransfer of the landTitle check
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 31 Jul 2024 |
|---|
| Developer's project loan | None declared |
|---|
Page 1
Page 1 of 2 of the survey sketch. Filed with K-RERA: KANNURAHALLI CLU SKETCH & VILLAGE MAP, 2 pages, not in English.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Survey numbers | SY No 84/7, SY No 84/8, SY NO 84/9, SY NO 85/6, SY no 85/9, SY no 85/11 and 20 more | |
|---|---|---|
| Khata | 17 Guntas · Revenue department,Hoskote · 14 Mar 2025; 8.50 guntas · Revenue department,Hoskote · 18 Mar 2022; 8.50 Guntas · Revenue department,Hoskote · 7 Jun 2025; and 21 more | |
| Sale deed | Dated 22 Dec 1967, 1 Jun 1971, 29 Sep 1977 and 14 more | |
| Sale deed in favour of | Ramesh Naidu & Surendra, RAMESH NAIDU & Others, N Harish & N Suresh | |
| Title deed | Consideration ₹93.4 L · Kannurahalli village, Kasaba hobli, Hoskote taluk | |
| Title deed | Consideration ₹23.4 L · Sy 84/7; 84, Kasaba hobli, Hoskote taluk · 17 Guntas |
| Sy. No. 84/7 | 5 | 17 guntas | 0 | ||||
| Sy. No. 84/8 | 1 | 9 guntas | 0 | ||||
| Sy. No. 84/9 | 1 | 9 guntas |
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2027 |
| Land conversion | 26 of 26 parcels converted | |
|---|---|---|
| Sy SY No 84/7, SY No 84/8, SY NO 85/… | Converted 7 Mar 2024 · District Commissioner, Bangalore Rural | |
| Sy SY NO 84/9 | Converted 7 Mar 2023 · District Commissioner, Bangalore Rural | |
| Sy SY no 85/11 | Converted 8 May 2024 · District Commissioner, Bangalore Rural | |
| Sy SY NO 89/1, SY no 89/2, SY NO 89/… | Converted 8 Feb 2024 · District Commissioner, Bangalore Rural | |
| Sy SY NO 121/1B2 | Converted 10 Jul 2024 · District Commissioner, Bangalore Rural | |
| Sy SY No 121/2E | Converted 6 Jul 2024 · District Commissioner, Bangalore Rural | |
| Other parcels | 3 more groups on the filing | |
| Survey numbers | SY No 84/7 · SY No 84/8 · SY NO 84/9 · SY NO 85/6 · SY no 85/9 · SY no 85/11 · SY NO 85/12 · SY No 86/1 · SY No 86/2 · SY NO 86/3 · SY NO 86/4 · SY NO 86/5 and 14 more parcels |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| Projects within 4 km, counted | 20 (15 with an approximate location) | |
|---|---|---|
| Plots in them | 3,308 | |
| Booked | 1,446 of 3,308 (44%) | |
| Unsold | 1,862 | |
| Booked a month, pooled | 45 plots | |
| Months to sell, pooled | 39 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture, at the filed pin | Review |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 400 kV, 470 m from the filed location | Clear |
| Nearest government-flagged flood location | 8.9 km, SIDDHARTHA LAYOUT KADUGODI |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 60 m to the south-east, an unnamed water body |
As the promoter reported itPossession date in the agreement
| Internal roads | 80% | |
|---|---|---|
| Completion | 25% | |
| Completion, accountant | 45.5% of the estimated cost spent |
| Possession, agreement | 31 Dec 2027 | |
|---|---|---|
| RERA completion date | 31 Dec 2027 | |
| Work began, as filed | 1 May 2025 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Feb 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Engineer's certificate, registration | Dated 14 Jul 2025 | |
| Chartered accountant's certificate, registration | Dated 10 Jun 2025 | |
| Chartered accountant, Form 4 | Dated 14 Oct 2026 |
| Estimated cost, at registration | ₹26.11 Cr | |
|---|---|---|
| Estimated cost, Form 4 Q2 2026-27 | ₹26.11 Cr | |
| Cost incurred | ₹11.87 Cr (45.5% of the Form 4 Q2 2026-27 estimate) | |
| Cost left | ₹14.24 Cr | |
| Receivable, sold plots | ₹9.45 Cr |
| Escrow bank | Canara Bank · HOSKOTE | |
|---|---|---|
| Designated account, collected | ₹15.17 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹5.72 Cr in Q2 2026-27 (38% of that quarter's deposits) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| 0 |
| Sy. No. 85/6 | 2 | 6 guntas | 0 |
| Sy. No. 85/9 | 1 | 7 guntas | 0 |
| Sy. No. 85/11 | 1 | 36 guntas | 0 |
| Sy. No. 85/12 | 2 | 36 guntas | 0 |
| Sy. No. 86/1 | 1 | 13 guntas | 0 |
| Sy. No. 86/2 | 1 | 6 guntas | 0 |
| Sy. No. 86/3 | 1 | 6 guntas | 0 |
| Sy. No. 86/4 | 1 | 6 guntas | 0 |
| Sy. No. 86/5 | 1 | 6 guntas | 0 |
| Sy. No. 89/1 | 1 | 29 guntas | 0 |
| Sy. No. 89/2 | 4 | 1 acre 4 guntas | 0 |
| Sy. No. 89/3 | 1 | 34 guntas | 0 |
| Sy. No. 89/4 | 2 | 1 acre 4 guntas | 0 |
| Sy. No. 89/5 | 1 | 19 guntas | 0 |
| Sy. No. 89/6 | 1 | 6 guntas | 0 |
| Sy. No. 121/2E | 1 | 2 guntas | 0 |
| Sy. No. 121/5B | 1 | 23 guntas | 0 |
| Sy. No. 121/6 | 1 | 20 guntas | 0 |
| Sy. No. 122/3B | 1 | 1 acre 2 guntas | 0 |
| Sy. No. 123/4 | 1 | 20 guntas | 0 |
| Sy. No. 123/6 | 1 | 8 guntas | 0 |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 62 m
Taluk average; not a reading at the site.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell, Local authority (CMC HOSKOTE) | |
| Nearest city water main | 6.2 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | None within 3 km | |
|---|---|---|
| Ground level | 883 m above sea level, plus or minus 4 m | |
| Metro, operational | 9.5 km, Whitefield | |
| Metro, under construction | 15.6 km, DRDO Sports complex |
| Kempegowda Airport | 35.9 | 36 | 19.1 |
| MG Road (CBD) | 29.2 | 28 | 24.8 |
| Manyata Tech Park | 28.7 | 31 | 20.9 |
| ITPL, Whitefield | 18.4 | 20 | 11.8 |
| Ecospace, Bellandur ORR | 29.0 | 33 | 20.9 |
| Electronic City Ph 1 | 44.0 | 47 | 28.8 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.7 km to the north-west, named Hoskote on OpenStreetMap |