Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 19 Dec 2025 | |
| Escrow bank | ICICI Bank · CUNNINGHAM ROAD |
Data room
139 documents filed with K-RERA for this project
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 7 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 7 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Locked |
| Location & risks | – | 1 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
Part of the full report. Unlock all 5 sections
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Vaishnavi At-One Life IV in the interactive atlas
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (BIAPPA) | Sanctioned 19 Dec 2025 · No. BIAAPA/TP/LAO/2024-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | None filed | |
| Environmental clearance | Filed with the registration | |
| Airport height NOC | None filed | |
| Pollution board (CFE) | consent order CTE-353226 · issued 17 Mar 2026 · valid until 16 Mar 2031 | Clear |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 18 Dec 2027 |
| Land conversion | 7 of 7 parcels converted | |
|---|---|---|
| Sy 65 | Converted 8 Apr 2005 · DEPUTY COMMISSIONER - BANGALORE RURAL DISTRICT | |
| Sy 66/1 | Converted 23 Jul 2025 · DEPUTY COMMISSIONER - BANAGLORE RURAL DISTRICT | |
| Sy 66/2 | Converted 23 Jul 2025 · DEPUTY COMISSIONER - BANAGLORE RURAL DIST | |
| Sy 67/2, 68/4 | Converted 16 May 2025 · DEPUTY COMMISSIONER - BANGALORE RURAL DIST | |
| Sy 67/3 | Converted 16 May 2025 · DEPUTY COMISSIONER - BANGALORE RURAL DIST | |
| Sy 68/3 | Converted 16 May 2025 · DEPUTY COMMISSIONER - BANGALORE RURAL DISTRICT | |
| Survey numbers | 65 · 66/1 · 66/2 · 67/2 · 67/3 · 68/3 · 68/4 |
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Agriculture, over the filed survey numbers | Review |
|---|---|---|
| Nearest government-flagged flood location | about 11.5 km, Kondappa layout | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 1 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
| Layout works specified | Entrance portal with security room; 12 m and 9 m wide internal roads, asphalted; concrete pavers on pedestrian pathways; landscaped avenue on both sides of the road; paved access to each plot; LED street lighting; underground power lines from transformer yards to feeder pillars, with provision up to the plot; irrigation network for the common landscape; underground water supply in UPVC pipes; water and sewerage lines ending within the plots; underground sanitary lines to a sewage plant; underground sump | |
|---|---|---|
| Sewage plant | 140 KLD plant under the consent for establishment of 17 Mar 2026, valid to 16 Mar 2031 |
As the promoter reported itPossession date in the agreement
| Internal roads | 95% | |
|---|---|---|
| Completion | 90% | |
| Completion, accountant | 73.2% of the estimated cost spent |
| Possession, agreement | 18 Dec 2027 | |
|---|---|---|
| RERA completion date | 18 Dec 2027 | |
| Work began, as filed | 1 May 2026 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Layout works | Entrance portal with security room; 12 m and 9 m wide internal roads, asphalted; concrete pavers on pedestrian pathways; landscaped avenue on both sides of the road; paved access to each plot; LED street lighting; underground power lines from transformer yards to feeder pillars, with provision up to the plot; irrigation network for the common landscape; underground water supply in UPVC pipes; water and sewerage lines ending within the plots; underground sanitary lines to a sewage plant; underground sump | |
|---|---|---|
| Sewage plant | 140 KLD plant under the consent for establishment of 17 Mar 2026, valid to 16 Mar 2031 |
| Structural engineer, quarterly | Form 6 · Jul 2026, Oct 2026 (2 filed) | Clear |
|---|---|---|
| Fire safety | None filed | |
| Environmental clearance | Filed with the registration |
Land · ₹56.47 Cr 51.5%Development · ₹53.08 Cr 48.5%
| Estimated cost, at registration | ₹109.55 Cr | |
|---|---|---|
| Cost incurred | ₹80.21 Cr (73.2% of the estimate) | |
| Cost left | ₹29.34 Cr | |
| Receivable, sold plots | ₹45.82 Cr |
| Escrow bank | ICICI Bank · CUNNINGHAM ROAD | |
|---|---|---|
| Designated account, collected | ₹15.36 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹5.68 Cr in Q2 2026-27 (37% of that quarter's deposits) | |
| Escrow account to date, Q2 2026-27 | ₹12.16 Cr deposited from sales | |
| Escrow account to date, Q1 2026-27 | ₹0 withdrawn |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 21 km, Dasarahalli | |
| Metro, under construction | about 6 km, Doddajala |
| Kempegowda Airport | 16.5 | 12 |
| MG Road (CBD) | 32 | 26.5 |
| Manyata Tech Park | 27.5 | 19 |
| ITPL, Whitefield | 43 | 29.5 |
| Ecospace, Bellandur ORR | 47.5 | 33.5 |
| Electronic City Ph 1 | 52 | 42.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 1.5 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |