Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Payments
Agreement for sale
Late-payment interest
SBI MCLR + 2%
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Due on signing; Due within 15 days; Each construction stage; Floors in payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
The area
Comparable projects
Nearest 12 with filed prices
Location & risks
What is the location like?
Groundwater, taluk average22.7 m below groundBengaluru North taluk, July 2023
Water supply, as filedLocal authorityDeclared by the promoter
The site
Flooding
Site vs nearest drain
Construction & progress
How is it being built, and when will it be ready?
CompletionCompletedOccupancy certificate, 7 Nov 2025
Progress
Completion, architect
Completed: no quarterly return is on this phase's K-RERA filing
Work left
By component
Completed: no quarterly return is on this phase's K-RERA filing
Quarterly return
Developer
Can the developer deliver?
Sold370 / 400At the completion filing, 31 Dec 2025
Sold in the latest quarterNo return filed
Funding
Estimated cost
Land · ₹123.56 Cr 31.4%Development · ₹270.29 Cr
Loan & collateral
Can it be financed?
Conditions
Collateral checks
Escrow bank
INDUSIND BANK · M G ROAD
Stage
Certified progress
Completed: no quarterly return is on this phase's K-RERA filing
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Records searched to; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Locked
110 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Title & ownership, Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around the locality centre named in the filing, on satellite imagery. The outlines are the land of each survey number, not buildings. The filing names only the locality, so the marker is the locality centre, not the site. The survey plots around it are shown for orientation only; this project's survey numbers are not matched to them yet.
Premium property located near manyata tech park. Location is excellent and well connected to main road. Part of very big Township project. View from top is superb and full city view. View of lake is too peaceful. Many amenities are…
SSatish Kumar Reddy30 Apr 2026★★★★★
High quality construction,,,Excellent location.. thoughtfully planned with superb amenities.. highlight is the Sky lounge on 34 th floor which offers stunning views of Bangalore .. a futuristic living concept..
NNiraj Jayswal29 Jan 2026★★★★★
False commitment and deadline. Commited for Aug 2023 still not handed over. Took payment upfront and without getting key we are paying interest of 50k to bank for each and every month due to delay. Careful before you land your hard earn…
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Vario Homes is not plotted on the interactive atlas: its filing gives no coordinate precise enough to place a single building, only the surrounding locality.
•• ••• ••••
•••••
₹ •.•• Cr
Charges
Not verified yet
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
Approval letters
Power NOC
Filed with the registration
Fire NOC
KSFES/NOC/426/2018
✓Clear
Environmental clearance
SEIAA 87 CON 2018 · issued 31 Oct 2018
✓Clear
Airport height NOC
issued 8 Feb 2016 · permissible top elevation 1014 m above mean sea level · validity ended 7 Feb 2021
Pollution board (CFE)
consent order AW-349088 · issued 19 Jun 2025 · valid until 30 Jun 2027
✓Clear
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
Granted · Approved 30 Dec 2024
RERA completion date
30 Dec 2025
Registration certificates
PRM/KA/RERA/1251/309/PR/190427/002539
EX/PRM/KA/RERA/1251/309/PR/241230/002539
Not verified yet: Building plan, Land conversion, Conversion order.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Unit mix filed; Unit types; Transactions in this project; North Bengaluru, past year; Bengaluru, past year; North Bengaluru since 2022; This project vs North Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields; Months to sell unsold stock; K-RERA inventory.
Nearest storm drain
about 0.5 km from the locality centre, primary drain
Nearest lake, tank or pond
about 0.5 km from the locality centre, an unnamed water body
Around it
Water
Groundwater, Bengaluru North taluk average
Ten-year July mean for this taluk: 26.8 m
Taluk average; not a reading at the site.
Water at a glance
Groundwater
Bengaluru North taluk average, July 2023: 22.7 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 7 CGWB wells in Bengaluru North taluk read in this class
Through the year
January 2025: 2.6 m (5 wells), Pre-monsoon 2025: 2.9 m (7 wells), August 2025: 3.2 m (7 wells), depth below ground of CGWB's monitoring wells in Bengaluru North taluk (the median where there are several)
Water supply, as filed
Local authority
Distances
Approximate: locality level
Nuisances
Distance from the site
Locality only filed: no distance from the site to show
DOSL nuisance layer
Landfill or waste transfer station
None within 3 km of the locality centre
Sewage treatment plant
about 1 km from the locality centre, named Hebbal 60MLD Sewage Treatment Plant on OpenStreetMap
Quarry
None within 3 km of the locality centre
Crematorium
None within 3 km of the locality centre
Prison
None within 3 km of the locality centre
Electrical substation
about 0.5 km from the locality centre, named Manyata on OpenStreetMap
Not verified yet: Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Drains and lakes; Specification and Form 5; Nearest city water main; Ground level; Metro, under construction; Road distance from the site; Six city anchors · OSRM, no traffic.
Completion
Completed, occupancy certificate 7 Nov 2025
Dates
Dates
Filed dates
Schedule end
20 Jun 2023
RERA completion date
30 Dec 2025
Completion date, agreement
31 Mar 2024
Work began, as filed
1 Apr 2019
Specified structure
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Main structure; Electrical and plumbing finishing; Internal roads; Club house; Completion, accountant; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Structural engineer, quarterly; Design consultants (Form 6).
68.6%
Form 4
Estimated cost, at registration
₹393.85 Cr
Sales
Sold vs unsold, at completion
Sold (370) 92.5%Unsold (30) 7.5%
Sold per quarter
Completed: no quarterly return is on this phase's K-RERA filing
K-RERA inventory
Flats sold, at completion
370
Flats unsold, at completion
30
Flats in the phase
400
Compliance
Escrow
Completed: no quarterly return is on this phase's K-RERA filing
Escrow and filings
Escrow bank
INDUSIND BANK · M G ROAD
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Basemap: Esri, OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.