Overview
Evo Aeris
Overview
Evo Aeris
Overview
Evo Aeris
Overview
Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
villa · avg 227 m² 100%
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 16 Sep 2022 | |
| Escrow bank | HDFC · 17th Cross ,4th Sector, HSR Layout |
Data room
248 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 3 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | – | – | – |
| 1 Lakhmulti Storey Housing Chikanahalli KamnahaliLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| Aashrayaa Eco CityApplied for completion 06/08/2020 | AASHRAYAA PROJECTS | Plot | – | Sep 2019 |
| Adithya Homes Grand Phase 2Completed (regulator flag) | M/s.ADITHYA HOMES | Plot | ~1,520 sqft (estimate: filed carpet plus 25%) | Completed |
| Adithya Homes Grand Phase 3Completed (regulator flag) | M/S.ADITHYA HOMES | Plot | ~1,400–1,990 sqft (estimate: filed carpet plus 25%) | Completed |
| Adithya Homes ParadiseCompleted (regulator flag) | ADITHYA HOMES | Plot | ~1,200–1,770 sqft (estimate: filed carpet plus 25%) | Completed |
| Adithya Homes Paradise Phase 2Applied for completion 09/01/2024 | ADITHYAHOMES | Plot | – | May 2024 |
| Adithya Homes Paradise Phase-3Completed (regulator flag) | M/s.ADITHYA HOMES | Plot | – | Completed |
| Adithya Homes Paradise Phase-4Lapsed · completion date passed | ADITHYA HOMES | Plot | ~1,200–1,600 sqft (estimate: filed carpet plus 25%) | Jun 2026 |
8 of 47 other projects in East Bengaluru, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Evo Aeris in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (Local Planning Authority) | Sanctioned 16 Sep 2022 · No. LAO/18/2022-23 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department | Filed with the registration | |
| Environmental clearance (1 of 2) | SEIAA 41 CON 2021 · issued 13 Oct 2021 | Clear |
| Environmental clearance (2 of 2) | SEIAA 68 CON 2022 · EC identification no. EC22B038KA110543 · issued 2 Aug 2022 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | consent order CTE-334144 · issued 31 Oct 2022 · valid until 30 Oct 2027 | Clear |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2031 |
| Land conversion | 4 of 4 parcels converted | |
|---|---|---|
| Sy 13 | Converted 17 May 2011 · Deputy Commissioner | |
| Sy 14/1, 14/2, 16 | Converted 12 May 2011 · DEPUTY COMMISSIONER | |
| Survey numbers | 13 · 14/1 · 14/2 · 16 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Villas | Carpet per villa, average (sq ft) |
|---|---|---|
| villa | 144 | 2,448 |
| Sold, Q2 2026-27 | 89 / 166 | |
|---|---|---|
| Unsold, Q2 2026-27 | 77 | |
| Months to sell, derived from filed bookings | Too few bookings to project (4 villas booked in 3 months) |
| Sowparnika Ashiyana Phase II | about 6.5 km | Locked | |
|---|---|---|---|
| Leafy Delight | about 7 km | Locked | |
| Sowparnika Rhythm of Rain | about 7 km | Locked | |
| Kumari Nautilus | about 7.5 km | Locked | |
| Sobha Windsor Phase 4 Wing 9, 10 And 11 | about 9 km | Locked | |
| Sobha Windsor Phase 2 Wing 3, 4 And 5 | about 9 km | Locked | |
| Vasudharini Nest | about 9 km | Locked | |
| Leafy Avenue | about 9 km | Locked | |
| Vintage Valley | about 9 km | Locked | |
| Sobha Windsor Phase 3 Wing 6, 7 And 8 | about 9 km | Locked | |
| Coevolve Florenza | about 9.5 km | Locked | |
| Jeevan's Allure | about 10 km | Locked |
| Evo Aeris This project | This project is the point the others are measured from | 31 Dec 2031 | 54% (89 of 166) | Not verified yet |
|---|---|---|---|---|
| Sowparnika Ashiyana Phase II | about 6.5 km | 31 Dec 2025 | 99% (419 of 422) | Locked |
| Leafy Delight | about 7 km | 31 Mar 2028 | 24% (16 of 67) | Locked |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 10.5 km, GANDHIPURAM NEAR WHITE FIELD |
|---|
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body |
| Amenities declared | Electricity · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Electricity, built | 35% | |
| Outdoor Sports facility, built | 35% | |
| Swimming Pool, built | 30% | |
| Parks, built | 20% | |
| Water and Sanitation, built | 0% | |
| Covered parking per unit | 0.10 (15 covered spaces for 144 units) | |
| Power backup | Declared by the promoter |
As the promoter reported itPossession date in the agreement
| Main structure | 98% · planned by 30 Jun 2028 | |
|---|---|---|
| Electrical and plumbing finishing | 70% · planned by 30 Nov 2028 | |
| Completion | 61% | |
| Completion, accountant | 53.5% of the estimated cost spent |
| Possession, agreement | Dec 2028 | |
|---|---|---|
| Schedule end | 31 Dec 2031 | |
| RERA completion date | 31 Dec 2031 | |
| Work began, as filed | 31 Jan 2023 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Provided, 12 sq m |
|---|
| Structural engineer, quarterly | Form 6 · Jul 2026, Oct 2026 (2 filed) | Clear |
|---|---|---|
| Environmental clearance (1 of 2) | SEIAA 41 CON 2021 · issued 13 Oct 2021 | |
| Environmental clearance (2 of 2) | SEIAA 68 CON 2022 · EC identification no. EC22B038KA110543 · issued 2 Aug 2022 | |
| Architect, quarterly | Form 5 · Jul 2026, Oct 2026 (2 filed) | |
| Architect's certificate, registration | Dated 15 Jul 2026 | |
| Engineer's certificate, registration | Dated 15 Jul 2026 | |
| Chartered accountant's certificate, registration | Dated 5 Apr 2023 | |
| Chartered accountant, Form 4 | Dated 13 Oct 2026 | |
| Architect's quarterly progress certificate | 57.08% complete per the architect, as of 13 Jul 2026 | |
| Architect's quarterly progress certificate dated | 13 Jul 2026 | |
| Architect's site inspection for the quarterly progress certificate | 13 Jul 2026 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹9.54 Cr 6.8%Development · ₹131.59 Cr 93.2%
| Estimated cost, at registration | ₹141.13 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹265.47 Cr | |
| Estimated cost, Form 4 Q2 2026-27 | ₹280.06 Cr | |
| Cost incurred | ₹149.93 Cr (53.5% of the Form 4 Q2 2026-27 estimate) |
Sold (89) 53.6%Unsold (77) 46.4%
| Sold, Q1 2026-27 | 85 / 166 · 81 available | |
|---|---|---|
| Sold, Q2 2026-27 | 89 / 166 · 77 available | |
| Unsold, Q2 2026-27 | 77 | |
| Sold in Q2 2026-27 | 4 | |
| 4BHK, sold | 89 / 166 | |
| Villas booked, Form 4 Q1 2026-27 | 85 |
| Escrow bank | HDFC · 17th Cross ,4th Sector, HSR Layout | |
|---|---|---|
| Designated account, collected | ₹8.75 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹5.85 Cr in Q2 2026-27 (67% of that quarter's deposits) | |
| Share of collections the promoter declared for escrow | 70% |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| about 7 km |
| 15 Jan 2032 |
| 97% (703 of 725) |
| Locked |
| Kumari Nautilus | about 7.5 km | 12 Jan 2028 | 69% (114 of 165) | Locked |
|---|
| Sobha Windsor Phase 4 Wing 9, 10 And 11 | about 9 km | 31 Mar 2028 | 100% (210 of 210) | Locked |
|---|
| Sobha Windsor Phase 2 Wing 3, 4 And 5 | about 9 km | 30 Apr 2026 | 100% (197 of 197) | Locked |
|---|
| Projects within 4 km, counted | 2 (2 with an approximate location) | |
|---|---|---|
| Villas in them | 507 | |
| Booked | 207 of 507 (41%) | |
| Unsold | 300 | |
| Booked a month, pooled | 12 villas | |
| Months to sell, pooled | 25 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 62 m
Taluk average; not a reading at the site.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | None within 3 km | |
|---|---|---|
| Metro, operational | about 11 km, Whitefield | |
| Metro, under construction | about 16 km, Marathahalli |
| Kempegowda Airport | 50.5 | 31 |
| MG Road (CBD) | 32.5 | 27 |
| Manyata Tech Park | 32 | 26.5 |
| ITPL, Whitefield | 14.5 | 12.5 |
| Ecospace, Bellandur ORR | 25 | 19 |
| Electronic City Ph 1 | 44.5 | 23 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 1 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |