Title & ownership
Approvals
| Building plan (BBMP) | Sanctioned 20 Oct 2020 · No. BBMP./AD.COM./MDP/030420-21 | |
|---|---|---|
| Power NOC | Filed with the registration | |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹12.00 Cr 30.2%Development · ₹27.70 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BBMP) | Sanctioned 20 Oct 2020 | |
| Escrow bank | Union Bank of India · BHUWANESHWARI NAGAR |
Data room
131 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 2 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 2 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | 2 | Clear |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 10xLapsed · completion date passed | M/S. MAZ-RD BUILDERS AND DEVELOPERS PRIVATE LIMITED | Apartment | – | Sep 2024 |
| 10x ELapsed · completion date passed | MAZ RD Builders and Developers Private Limited | Apartment | 478 sqft carpet (as filed) | Dec 2024 |
| A.S.R.S ParadiseLapsed · completion date passed | A.S. Builders | Apartment | – | Jan 2021 |
| Aadya HeightsLapsed · completion date passed | WHITEWINDS CONSTRUCTIONS PRIVATE LIMITED | Apartment | 917–1,080 sqft carpet (as filed) | Dec 2025 |
| Aakriti EmeraldActive · 51% built | AAKRITI PROJECTS | Apartment | 694–1,137 sqft carpet (as filed) | Aug 2028 |
| Aakruthi NestActive · 35% built | KRITI BUILDERS AND DEVELOPERS | Apartment | 608–837 sqft carpet (as filed) | Dec 2028 |
| Aban DesireRegistered · no quarterly update yet | ABAN DEVELOPERS PRIVATE LIMITED | Apartment | 801–1,054 sqft carpet (as filed) | Dec 2028 |
| Adarsh ParadiseActive · 93% built | A1 BUILDERS | Apartment | 668–924 sqft carpet (as filed) | Dec 2026 |
8 of 328 other projects in Old Madras Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Galaxy One Phase-2 in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Fire department |
|---|
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| Pollution board (CFE) | consent order AW-337152 · issued 30 Mar 2023 |
|---|
| Water and sewerage NOC (BWSSB) | issued 8 Sep 2021 |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2025 |
| Land conversion | Converted 20 Mar 2012 · Deputy Commissioner | |
|---|---|---|
| Survey numbers | SY No.43/6&45/1A, |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
2 BHK Flats · avg 69 m² 79.2%3 BHK Flats · avg 89 m² 16.7%1 BHK Flats 4.2%
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| 1 BHK Flats | 4 | 1,679 |
| 2 BHK Flats | 76 | 56,737 |
| 3 BHK Flats | 16 | 15,306 |
Map of 4 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Garuda Grand, price locked; 2g Tula, price locked; Assetz Bloom & Dell - Phase 2, price locked; Godrej Splendour, price locked.
| Assetz Sun & Sanctum - Phase 2 | about 2 km | Locked | |
|---|---|---|---|
| Garuda Grand | 2.3 km | Locked | |
| 2g Tula | 2.3 km | Locked | |
| Assetz Bloom & Dell - Phase 2 | 2.8 km | Locked |
| Galaxy One Phase-2 This project | This project is the point the others are measured from | 31 Dec 2025 | – | Not verified yet |
|---|---|---|---|---|
| Assetz Sun & Sanctum - Phase 2 | about 2 km | 31 Jul 2026 | 100% (70 of 70) | Locked |
| Garuda Grand | 2.3 km | 31 Mar 2028 | 41% (56 of 136) | Locked |
| 2g Tula | 2.3 km |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main) | Clear |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 66 kV, 400 m from the filed location | Clear |
| Nearest government-flagged flood location | 370 m, TRIVENI NAGAR NEAR KR PURAM | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | 100 m to the north-east, secondary drain | |
|---|---|---|
| Nearest lake, tank or pond | 120 m to the north, an unnamed water body |
| Amenities declared | Electricity · CCTV Surveillance · Power Backup · Water and Sanitation | |
|---|---|---|
| Sewage plant | Sewage treatment plant | |
| Power backup | Declared by the promoter |
| Completion | Completed, occupancy certificate 3 Mar 2023 |
|---|
| Schedule end | 15 Oct 2023 | |
|---|---|---|
| RERA completion date | 31 Dec 2025 | |
| Completion date, agreement | Dec 2023 | |
| Work began, as filed | 25 Oct 2021 |
| Structure | RCC framed structure | |
|---|---|---|
| Wall thickness | All walls: 6" & 4" | |
| Building heights, fire NOC | 14 m filed |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | UPVC windows | |
|---|---|---|
| Flooring | Vitrified tiles | |
| Toilet tiles | Ceramic tiles (floor) | |
| Power backup | Power backup for common areas | |
| Sewage plant | Sewage treatment plant |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹39.70 Cr |
|---|
Sold (59) 61.5%Unsold (37) 38.5%
| Flats sold, at completion | 59 | |
|---|---|---|
| Flats unsold, at completion | 37 | |
| Flats in the phase | 96 |
| Escrow bank | Union Bank of India · BHUWANESHWARI NAGAR |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Godrej Splendour Phase II | about 3 km | Locked |
|---|
| Godrej Splendour | 3.2 km | Locked |
|---|
| Sattva Songbird | 4.5 km | Locked |
|---|
| Nirmaanika Aria | about 4.5 km | Locked |
|---|
| Godrej Woodscapes | about 4.5 km | Locked |
|---|
| Vaswani Starlight | about 5 km | Locked |
|---|
| Coevolve Misty Shores | about 5 km | Locked |
|---|
| Axis Ekatva | about 5 km | Locked |
|---|
| 27 Dec 2027 |
| 68% (173 of 256) |
| Locked |
| Assetz Bloom & Dell - Phase 2 | 2.8 km | 31 Oct 2027 | 100% (238 of 238) | Locked |
|---|
| Godrej Splendour Phase II | about 3 km | 14 Jan 2028 | 88% (782 of 891) | Locked |
|---|
| Godrej Splendour | 3.2 km | 20 Mar 2027 | 98% (1,135 of 1,161) | Locked |
|---|
| Rent, 3BHK, 3 km | ₹49,270 /mo · 46 listings | |
|---|---|---|
| Rent, 2BHK, 3 km | ₹28,000 /mo · 70 listings | |
| Rent, 1BHK, 3 km | ₹13,000 /mo · 29 listings | |
| Rent per sq ft, 3 km | ₹26.3 /mo, as listed · 89 listings with a size |
| Projects within 4 km, counted | 54 (26 with an approximate location) | |
|---|---|---|
| Flats in them | 15,796 | |
| Booked | 9,158 of 15,796 (58%) | |
| Unsold | 6,638 | |
| Booked a month, pooled | 99 flats | |
| Months to sell, pooled | 59 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 30.5 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru East taluk average, July 2023: 27.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell, BWSSB | |
| Nearest city water main | 80 m |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 100 m to the north-east, secondary drain | |
|---|---|---|
| Ground level | 868 m above sea level, plus or minus 4 m | |
| Metro, operational | 3.4 km, Garudacharpalya | |
| Metro, under construction | 4.7 km, Saraswathi Nagar |
| Kempegowda Airport | 31.2 | 31 | 19.9 |
| MG Road (CBD) | 16.7 | 17 | 13.7 |
| Manyata Tech Park | 16.2 | 20 | 11.1 |
| ITPL, Whitefield | 8.2 | 11 | 4.2 |
| Ecospace, Bellandur ORR | 14.5 | 22 | 11.3 |
| Electronic City Ph 1 | 31.5 | 36 | 20.6 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 130 m to the north, named Yelemallappa Chetti 15MLD Sewage Treatment Planet on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.6 km to the south, named Hoodi Substation on OpenStreetMap |