I recently visited Billore and was genuinely impressed by its long-term potential. The biggest strength of this location is its position within a rapidly developing growth corridor. With expanding infrastructure, improving road…
Overview
Kns Billore
Overview
Kns Billore
Overview
Kns Billore
Overview
Photo: Veeresh HakkiTitle & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BMRDA) | Sanctioned 27 Mar 2024 · No. DPA/TP/LAO/05/2023-24 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹17.24 Cr 55.3%Development · ₹13.93 Cr
Loan & collateral
| Developer's project loan | Texterity Private Limited · ₹30.00 Cr disbursed | |
|---|---|---|
| Records searched to | 30 Apr 2024 | Review |
| Building plan (BMRDA) | Sanctioned 27 Mar 2024 | |
| Escrow bank | RATNAKAR BANK · Prestige Towers ,Bangalore |
Data room
117 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
I recently visited Billore and was genuinely impressed by its long-term potential. The biggest strength of this location is its position within a rapidly developing growth corridor. With expanding infrastructure, improving road…
Not worth the investment. Price is too much as per the location and quality of infrastructure. Nearby properties are available at 60-70% of the price quoted. In addition to that the sales team is inflexible about negotiation. They are…
Located in a rapidly developing corridor along with projects from top-grade builders, this property offers excellent value for money. With strong infrastructure growth and increasing demand, it presents a promising investment opportunity…
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | – | Review |
| Construction & progress | – | 1 | – | Review |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | 1 | – | Review |
| 1 Lakh Multi - Storey Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Apr 2023 |
| 99d By SanthustaApplied for completion 15/11/2026 | M/s. SANTHUSTA INFRACON PRIVATE LIMITED | Plot | ~1,080–2,430 sqft (estimate: filed carpet plus 25%) | Jul 2028 |
| Adhya EnclaveLapsed · completion date passed | ADHYA DEVELOPERS | Plot | – | Dec 2023 |
| Affinity FidelityLapsed · completion date passed | SUDHAKARA REDDY ANNEM | Apartment | – | Jul 2022 |
| Affinity HarmonyCompleted · OC 01-09-2018 | AFFINITY PROJECTS | Apartment | 1,414 sqft carpet (as filed) | Completed |
| Affinity SarovarActive · 96% built | AFFINITY PROJECTS LLP | Apartment | 982–1,237 sqft carpet (as filed) | Sep 2027 |
| Affinity SerenityLapsed · completion date passed | Sudhakara Reddy Annem | Apartment | – | Feb 2022 |
| Alpine Pyramid EfghCompleted (regulator flag) | ALPINE HOUSING DEVELOPMENT CORPORATION LIMITED | Apartment | 1,066 sqft carpet (as filed) | Completed |
8 of 99 other projects in Doddaballapur Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Kns Billore in the interactive atlas
Transfer of the land
Title deed executed
No. GNR-1-05678-2022-23 · Book 1 · Consideration ₹12.25 Cr · Sy 37/1
Title deed filed with K-RERA, pp. 1, 9, 11, 14 · See it in Documents
Transfer of the land
Sale deed
in favour of Billore Royal Ventures Rep by its Partner Jagadish kumar Patel and Sanjay Suresh · Survey 37/1
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · Revenue Inspector Hesaragatta Hobli · Survey 37/1
K-RERA filing, land schedule
Transfer of the land
Title deed executed
Consideration ₹30.30 Cr
Title deed filed with K-RERA, pp. 1, 12 · See it in Documents
Transfer of the land
Sale deed
in favour of Billore Royal Ventures Rep by its Partner Jagadish kumar Patel and Sanjay Suresh · Survey 37/3
K-RERA filing, land schedule
Transfer of the land
Title deed registered
No. GNR-1-02868-2023-24 · Book 1 · executed 28 Jul 2023 · Consideration ₹30.30 Cr
Title deed filed with K-RERA, pp. 1, 5, 13 · See it in Documents
Approval or registration
Khata issued
A Khatha · Revenue Inspector Hesaragatta Hobli · Survey 37/3
K-RERA filing, land schedule
Approval or registration
Land use converted
Deputy Comissioner, Bengaluru Urban District · Survey 37/1
K-RERA filing, land schedule
Approval or registration
Land use converted
Deputy Comissioner, Bengaluru Urban District. · Survey 37/3
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BMRDA · plan DPA/TP/LAO/05/2023-24
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/472/PR/020724/006937
K-RERA registration ·
Transfer of the landApproval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 30 Apr 2024 |
|---|
| Developer's project loan | Texterity Private Limited · ₹30.00 Cr disbursed |
|---|
| Side | Schedule in the EC | KGIS neighbours |
|---|---|---|
| North | EC schedule not read yet | Survey 44, 46 (Hosahudya) |
| East | EC schedule not read yet | Survey 43 (Hosahudya); Survey 38 (Kadathanamale) |
| South | EC schedule not read yet | Survey 33, 34 (Kadathanamale) |
| West | EC schedule not read yet | tank |
| Filed survey numbers matched to the KGIS map | 1 of 1 | |
|---|---|---|
| Matched plots on the KGIS map | 55,842 sq m | |
| Extent the filed land schedule names for these survey numbers | 40,469 sq m | |
| Plot area against the filed extent | 1.22 times | |
| Village, hobli and taluk on the KGIS map | Kadathanamale, Hesarughatta-2 hobli, Yelahanka taluk | |
| Mutation entry | None open on 2 of 2 filed surveys |
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
| Survey numbers | 37/1, 37/3 | |
|---|---|---|
| Land extent, Sy 37/1 | 3 Acres 9 Gunats | |
| Land extent, Sy 37/3 | 7 Acres 39 Gunats | |
| Area on the KGIS map | 55,842 sq m, 1 of 1 filed survey numbers | |
| Khata | A Khatha · Revenue Inspector Hesaragatta Hobli · 15 Mar 2023; A Khatha · Revenue Inspector Hesaragatta Hobli · 22 Aug 2023 | |
| Sale deed | Dated 22 Feb 2023, 28 Jul 2023 | |
| Sale deed in favour of | Billore Royal Ventures Rep by its Partner Jagadish kumar Patel and Sanjay Suresh |
| Survey | Owners as on the RTC, read date / relation / share | Owners on the RTC | RTC extent | Filed extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|---|
| Sy. No. 37/1 | 2 | 3 acres 9 guntas | 0 | ||||
| Sy. No. 37/3 | 2 | 7 acres 39 guntas | 0 |
| SEIAA | Filed with the registration |
|---|
| Airport height NOC | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 27 May 2026 |
| Land conversion | 2 of 2 parcels converted | |
|---|---|---|
| Sy 37/1 | Converted 6 Feb 2024 · Deputy Comissioner, Bengaluru Urban District | |
| Sy 37/3 | Converted 14 Feb 2024 · Deputy Comissioner, Bengaluru Urban District. | |
| Survey numbers | 37/1 · 37/3 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| Earth Aroma | about 5.5 km | Locked |
|---|
| Vaishnavi At-One Life IV | about 6 km | Locked |
|---|
| Earth Aroma Phase-2 | about 6 km | Locked |
|---|
| Fortius Good Earth | about 6.5 km | Locked |
|---|
| Kns Billore This project | This project is the point the others are measured from | 27 May 2026 | – | Not verified yet |
|---|---|---|---|---|
| Earth Aroma | about 5.5 km | 31 Dec 2024 | – | Locked |
| Vaishnavi At-One Life IV | about 6 km | 18 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | about 6 km | 31 Dec 2025 | – | Locked |
| Fortius Good Earth | about 6.5 km | 31 Dec 2027 | – | Locked |
| Projects within 4 km, counted | 8 (8 with an approximate location) | |
|---|---|---|
| Plots in them | 1,752 | |
| Booked | 555 of 1,752 (32%) | |
| Unsold | 1,197 | |
| Booked a month, pooled | 30 plots | |
| Months to sell, pooled | 40 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Agriculture, over the filed survey numbers | Review |
|---|---|---|
| Nearest government-flagged flood location | about 14 km, Attur, Near Dairy Circle | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
| RERA completion date | 27 May 2026 | Review |
|---|---|---|
| Work began, as filed | 4 Jun 2024 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Architect's certificate, registration | Dated 22 May 2024 · site inspected 15 Apr 2024 | |
|---|---|---|
| Engineer's certificate, registration | Dated 22 May 2024 | |
| Chartered accountant's certificate, registration | Dated 24 May 2024 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹31.17 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹31.17 Cr, same as the filing | |
| Estimated cost, engineer's certificate | ₹11.68 Cr |
| Escrow bank | RATNAKAR BANK · Prestige Towers ,Bangalore |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Doddaballapura grama panchayathi) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 21 km, Chikkabidarakallu | |
| Metro, under construction | about 11.5 km, Doddajala |
| Kempegowda Airport | 32 | 18 |
| MG Road (CBD) | 37.5 | 29 |
| Manyata Tech Park | 30.5 | 22 |
| ITPL, Whitefield | 47.5 | 34.5 |
| Ecospace, Bellandur ORR | 53 | 37 |
| Electronic City Ph 1 | 57.5 | 46 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km, named Substation on OpenStreetMap |