Are there court cases or buyer complaints on this project?
Clear1 clear
Builder: M/s Orion Projects
Court cases on the project's land
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
None found.
Buyer complaints filed with K-RERA on this project
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
Buyer complaints on other projects by this builder
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
Contract & costs
What does a buyer commit to?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Forfeiture, agreement10% of the sale considerationAgreement for sale, p. 6
Cancellation
Forfeiture
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
The area
Comparable projects
Nearest 12 with filed prices
Location & risks
What is the location like?
Groundwater, taluk average27.3 m below groundBengaluru East taluk, July 2023
Water supply, as filedSelf developmentDeclared by the promoter
Completed: no quarterly return is on this phase's K-RERA filing
Work left
By component
Completed: no quarterly return is on this phase's K-RERA filing
Quarterly return
Completion
Completed, occupancy certificate 3 Jul 2024
Developer
Can the developer deliver?
Sold11 / 34At the completion filing, 29 Apr 2025
Sold in the latest quarterNo return filed
Funding
Estimated cost
Land · ₹15.78 Cr 45.1%Development · ₹19.20 Cr
Loan & collateral
Can it be financed?
Review1 to review
Conditions
Collateral checks
Records searched to
10 Nov 2019
!Review
Escrow bank
South Indian Bank Ltd. · M S Nagar
Stage
Certified progress
Completed: no quarterly return is on this phase's K-RERA filing
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Documents filed108On K-RERA
Available108100% of filed
K-RERA only0
Approvals with a validity dateNone read
Approvals & NOCs
1 pageAvailable
1 pageAvailable
27 pagesAvailable
12 pagesAvailable
2 pagesAvailable
36 pagesAvailable
1 pageAvailable
1 pageAvailable
Available
Available
1 pageAvailable
1 pageAvailable
1 pageAvailable
3 pagesAvailable
12 pagesAvailable
2 pagesAvailable
Source: K-RERA project page and the documents filed there, as read by us. 12 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Orion Palm Dew is not plotted on the interactive atlas: its filing gives no coordinate precise enough to place a single building, only the surrounding locality.
Page 1
Page 1 of the encumbrance certificate. Filed with K-RERA: Latest Encumbrance Certificate.
No survey sketch is listed on this phase's K-RERA filing
Land record
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around the locality centre named in the filing, on satellite imagery. The outlines are the land of each survey number, not buildings. The filing names only the locality, so the marker is the locality centre, not the site. The survey plots around it are shown for orientation only; this project's survey numbers are not matched to them yet.
Not verified yet: Title opinion; Charges on the land; Landowner share of sales; How the land reached this project; Court-case search; High Court order; Charges; Schedule in the EC vs KGIS neighbours; Sketch, sanction and mutation vs KGIS map; Area on the KGIS map; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
RERA
K-RERA
RERA extensions
Granted · Approved 18 Mar 2025
RERA completion date
30 Apr 2025
Registration certificates
PRM/KA/RERA/1251/446/PR/200113/003152
EX/PRM/KA/RERA/1251/446/PR/250318/003152
Not verified yet: Building plan, Land conversion, Validity, Environmental clearance, Conversion order.
Agreement and allotment letter
Forfeiture, agreement
10% of the sale consideration
Fees
Agreement for sale
Defect liability
5 years
Not verified yet: Forfeiture, allotment letter; Transfer fee; Maintenance included; Payment plan; Agreement for sale; Holding charge.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Unit mix filed; Unit types; Transactions in this project; North Bengaluru, past year; Bengaluru, past year; North Bengaluru since 2022; This project vs North Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields; Months to sell unsold stock; K-RERA inventory.
Nearest storm drain
about 0.5 km from the locality centre, tertiary drain
Nearest lake, tank or pond
about 0.5 km from the locality centre, an unnamed water body
Around it
Water
Groundwater, Bengaluru East taluk average
Ten-year July mean for this taluk: 30.5 m
Taluk average; not a reading at the site.
Water at a glance
Groundwater
Bengaluru East taluk average, July 2023: 27.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes
Through the year
Not found
Water supply, as filed
Self development
Distances
Approximate: locality level
Nuisances
Distance from the site
Locality only filed: no distance from the site to show
DOSL nuisance layer
Landfill or waste transfer station
None within 3 km of the locality centre
Sewage treatment plant
about 2.5 km from the locality centre, named Sewage Treatment Plant on OpenStreetMap
Quarry
about 1 km from the locality centre
Crematorium
None within 3 km of the locality centre
Prison
None within 3 km of the locality centre
Electrical substation
about 1 km from the locality centre
Not verified yet: Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Drains and lakes; Specification and Form 5; Nearest city water main; Ground level; Metro, under construction; Road distance from the site; Six city anchors · OSRM, no traffic.
Dates
Dates
Filed dates
Schedule end
30 Sep 2023
RERA completion date
30 Apr 2025
Work began, as filed
1 Jan 2020
Specified structure
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Main structure; Electrical and plumbing finishing; Internal roads; Club house; Completion, accountant; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Engineer, architect and fire certificates.
54.9%
Form 4
Estimated cost, at registration
₹34.98 Cr
Sales
Sold vs unsold, at completion
Sold (11) 32.4%Unsold (23) 67.6%
Sold per quarter
Completed: no quarterly return is on this phase's K-RERA filing
K-RERA inventory
Flats sold, at completion
11
Flats unsold, at completion
23
Flats in the phase
34
Compliance
Escrow
Completed: no quarterly return is on this phase's K-RERA filing
Escrow and filings
Escrow bank
South Indian Bank Ltd. · M S Nagar
Share of collections the promoter declared for escrow
70%
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Basemap: Esri, OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.