Building plan (BDA)Sanctioned 4 Sep 2024No. 276/2024-25
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted, 2 of 2 parcelsDates and authorities below
Permits
Approval letters
Building plan (BDA)
Sanctioned 4 Sep 2024 · No. 276/2024-25
Power NOC
Filed with the registration
Fire NOC (1 of 2)
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
Locked
Forfeiture, agreement•• %
Forfeiture, allotment letterNot verified yet
Transfer feeNot verified yet
Maintenance includedNot verified yet
Cancellation
Forfeiture
Not verified yet
Agreement and allotment letter
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Unit mix filed
Location & risks
What is the location like?
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedBorewell, BWSSBDeclared by the promoter
Metro, operationalabout 10 kmBommasandra
Construction & progress
How is it being built, and when will it be ready?
CompletionFirst return due
Possession, agreement31 Mar 2028Agreement for sale, p. 17
Progress
Completion, architect
Registered: its first quarterly return is still to come
Work left
By component
Registered: its first quarterly return is still to come
Quarterly return
Registered: its first quarterly return is still to come
Dates
Developer
Can the developer deliver?
SoldFirst return due
Sold in the latest quarterFirst return due
Funding
Estimated cost
Land · ₹25.73 Cr 20.7%Development · ₹98.38 Cr 79.3%
Loan & collateral
Can it be financed?
Conditions
Collateral checks
Building plan (BDA)
Sanctioned 4 Sep 2024
Escrow bank
HDFC · Sompura Branch
Stage
Certified progress
Registered: its first quarterly return is still to come
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Locked
146 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Contract & costs, Title & ownership, Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Had a really good experience with Suyug The 1 so far. The layouts, planning, and amenities look impressive. Special thanks to Sirisha for her patience and clear guidance throughout the buying process, especially in explaining the IGBC…
AArun Belgavi15 Jul 2026★★★★★
Had A Great Experience @ THE1 By Suyug. Visited model 3BHK Apartment. It's premium living experience! ♥️ I have been welcomed by the Receptionist Sangeetha. Mr. Manjunath has explained very well about this project with professionalism. The…
BBala naresh9 May 2026★★★★★
I recently purchased a flat at Suyug The 1 and my overall experience with the project has been very positive. The apartment layout, project planning, and modern amenities are quite impressive. The walkthrough provided gave us a very clear…
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Suyug The 1 in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
Not verified yet
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Survey sketch
Survey sketch filed with K-RERA
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
Not verified yet
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
KSFES/NOC/153/2024 · issued 30 May 2024
✓Clear
Fire NOC (2 of 2)
KSFES/NOC/011/2025 · issued 19 Feb 2025
✓Clear
Environmental clearance
SEIAA 55 CON 2025 · issued 21 Apr 2025
✓Clear
Airport height NOC
Filed with the registration
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
31 Mar 2028
Registration certificates
PRM/KA/RERA/1251/310/PR/051224/007268
Land use
Conversion order
Land conversion
2 of 2 parcels converted
Sy 27/1
Converted 3 Jan 2013 · Deputy Comissioner
Sy 27/2
Converted 12 Apr 2012 · DEPUTY COMMISSIONER
Survey numbers
27/1 · 27/2
Not verified yet: Validity.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Payments
Payment plan
Not verified yet
Agreement for sale
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Fees
Agreement for sale
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
3BHK · avg 105 m² 93.7%4BHK 3.2%1BHK 1.6%Other - studio 1.6%
Unit types
1BHK
2
1,238
3BHK
118
1,33,117
4BHK
4
8,267
Other - studio
2
398
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Registered: its first quarterly return is still to come
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; East Bengaluru, past year; Bengaluru, past year; East Bengaluru since 2022; This project vs East Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot
Not verified yet: Structure; Structural safety certificate; Schedule end; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Structural engineer, quarterly; Design consultants (Form 6).
Form 4
Estimated cost, at registration
₹124.12 Cr
Estimated cost, engineer's certificate
₹98.38 Cr
Sales
Sold vs unsold
Registered: its first quarterly return is still to come
Sold per quarter
Registered: its first quarterly return is still to come
K-RERA inventory
Registered: its first quarterly return is still to come
Compliance
Escrow
Registered: its first quarterly return is still to come
Escrow and filings
Escrow bank
HDFC · Sompura Branch
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220, 110 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Approximate location: the filed pin, good to the neighbourhood, not the plot
Anekal taluk average, July 2023: 21.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class
Through the year
January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several)
Water supply, as filed
Borewell, BWSSB
Distances
Within 3 km of the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220, 110 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot