Title & ownership
Approvals
| Power NOC | Filed with the registration | |
|---|---|---|
| Fire NOC | Filed with the registration | |
| Environmental clearance | Filed with the registration | |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified this for this project yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹5.00 Cr |
|---|
Loan & collateral
| Escrow bank | HDFC · K R Road |
|---|
Data room
63 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around the locality centre named in the filing, on satellite imagery. The outlines are the land of each survey number, not buildings. The filing names only the locality, so the marker is the locality centre, not the site. The survey plots around it are shown for orientation only; this project's survey numbers are not matched to them yet.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | 1 | – | – | Red flag |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| “the Sanctuary”Completed (regulator flag) | Classic Ventures LLP | Plot | – | Completed |
| 42 Queens SquareCompleted (regulator flag) | GRS INFRA | Plot | – | Completed |
| 77 EastLapsed · completion date passed | MODERN SPAACES | Apartment | – | Jan 2023 |
| 77 East Phase 2 By Modern Spaaces VenturesLapsed · completion date passed | MODERN SPAACES | Apartment | 1,010 sqft carpet (as filed) | Dec 2022 |
| 302 WestCompleted · OC 30-08-2023 | MODERN SPAACES VENTURES | Apartment | 735–1,398 sqft carpet (as filed) | Completed |
| 312 WestLapsed · completion date passed | MODERN SPAACES CONSTRUCTIONS | Apartment | 604 sqft carpet (as filed) | Apr 2022 |
| Aban DazzleRegistered · no quarterly update yet | ABAN DEVELOPERS PRIVATE LIMITED | Rowhouse | 2,040 sqft carpet (as filed) | Dec 2028 |
| Abhee Kings CourtCompleted · OC 26-05-2026 | ABHEE VENTURES PVT LTD | Apartment | 836–1,124 sqft carpet (as filed) | Completed |
8 of 191 other projects in Sarjapur, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Unicon Hamlet is not plotted on the interactive atlas: its filing gives no coordinate precise enough to place a single building, only the surrounding locality.
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2020 |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Nearest storm drain | about 0.5 km from the locality centre, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km from the locality centre, an unnamed tank |
Ten-year July mean for this taluk: 28.7 m
Taluk average; not a reading at the site.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class | |
| Through the year | January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several) | |
| Water supply, as filed | Self development |
| Landfill or waste transfer station | None within 3 km of the locality centre | |
|---|---|---|
| Sewage treatment plant | about 2 km from the locality centre | |
| Quarry | None within 3 km of the locality centre | |
| Crematorium | None within 3 km of the locality centre | |
| Prison | None within 3 km of the locality centre | |
| Electrical substation | None within 3 km of the locality centre |
| RERA completion date | 31 Dec 2020 | Red flag |
|---|---|---|
| Work began, as filed | 15 Nov 2017 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Fire safety | Filed with the registration | |
|---|---|---|
| Environmental clearance | Filed with the registration |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Escrow bank | HDFC · K R Road |
|---|
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Centre of the filed locality; basemap © OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Centre of the filed locality; basemap © OpenStreetMap contributors
| Nearest drain | about 0.5 km from the locality centre, tertiary drain |
|---|