Building plan (Anekal Planning Authority)Sanctioned 2 Mar 2026No. APC/CC/1160/2025-26
RERA extensionsNone on the filingFiling read 20 Oct 2026
Land conversionConverted 18 Sep 2024Deputy Commissioner
Permits
Approval letters
Building plan (Anekal Planning Authority)
Sanctioned 2 Mar 2026 · No. APC/CC/1160/2025-26
Power NOC
Filed with the registration
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
Locked
Forfeiture, agreement•• %
Forfeiture, allotment letterNot verified yet
Transfer feeNot verified yet
Maintenance includedNot verified yet
Cancellation
Forfeiture
Not verified yet
Agreement and allotment letter
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Unit mix filed
3BHK · avg 92 m² 66.5%2BHK · avg 72 m²
Location & risks
What is the location like?
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedBorewell, Local authority (Neriga Grama Panchayati)Declared by the promoter
Metro, operationalabout 9.5 kmChannasandra
Construction & progress
How is it being built, and when will it be ready?
Clear1 clear
Completion9%As of Q2 2026-27, promoter's return
Possession, agreement31 Dec 2029Agreement for sale, p. 14
Progress
Completion, as the promoter reported it
Developer
Can the developer deliver?
Clear1 clear
Sold54 / 167As of Q2 2026-27
Sold in Q2 2026-2748✓ClearClear
Funding
Estimated cost
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan
Sanctioned 2 Mar 2026
Escrow bank
Bank of Baroda · MID CORPORATE BENGALURU
Stage
Progress as reported, by quarter
Data room
Documents filed for this project
Locked
83 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Contract & costs, Title & ownership, Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Satellite map with the 2 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 2 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
Fantastic project and a seamless booking experience! Vrushabadri Winter Park offers brilliant floor plans, top-notch amenities, and a peaceful green environment right off Sarjapur Road. The generous open spaces and well-ventilated…
UUpendra Chhipa4 Oct 2026★★★★★
A Smooth and Trustworthy Home Buying Experience Buying a home is a big decision, but the team at Vrushabadri Winter Park made it smooth and stress-free. The flat layout is very well planned, and the overall construction quality along with…
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Vrushabadri Winter Park in the interactive atlas
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Not verified yet
Survey sketch
Survey sketch filed with K-RERA
Sketch, sanction and mutation vs KGIS map
₹ ••,•••
•• %
•• ••• ••••
•••••
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
Not verified yet
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Fire NOC
KSFES/NOC/489/2025 · issued 14 Jan 2026
✓Clear
Environmental clearance
SEIAA 299 CON 2025 · issued 9 Feb 2026
✓Clear
Airport height NOC
NOC ID HOSU/SOUTH/B/120325/2251538
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
31 Dec 2029
Registration certificates
PRM/KA/RERA/1251/308/PR/070526/008631
Land use
Conversion order
Land conversion
Converted 18 Sep 2024 · Deputy Commissioner
Survey numbers
110/4 · 110/5
Not verified yet: Validity.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Payments
Payment plan
Not verified yet
Agreement for sale
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Fees
Agreement for sale
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; East Bengaluru, past year; Bengaluru, past year; East Bengaluru since 2022; This project vs East Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
Power lines, drains and flood locations around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400 and 220 kV
Its corridor, to scale
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Land · ₹9.63 Cr 8.2%Development · ₹108.47 Cr 91.8%
Form 4
Estimated cost, at registration
₹118.10 Cr
Estimated cost, architect's and engineer's certificates
₹108.47 Cr
Estimated cost, Form 4 Q2 2026-27
₹127.73 Cr
Cost incurred
₹38.81 Cr (30.4% of the Form 4 Q2 2026-27 estimate)
Sales
Sold vs unsold, Q2 2026-27
Sold (54) 32.3%Unsold (113) 67.7%
Sold per quarter
K-RERA inventory
Sold, Q1 2026-27
6 / 167 · 161 available
Sold, Q2 2026-27
54 / 167 · 113 available
Unsold, Q2 2026-27
113
Sold in Q2 2026-27
48
Flats booked, Form 4 Q2 2026-27
54
Compliance
Escrow, Q2 2026-27
Escrow and filings
Escrow bank
Bank of Baroda · MID CORPORATE BENGALURU
Designated account, collected
₹2.48 Cr in Q2 2026-27
Designated account, withdrawn
₹1.04 Cr in Q2 2026-27 (42% of that quarter's deposits)
Escrow account to date, Q2 2026-27
₹3.68 Cr deposited from sales, ₹2.23 Cr withdrawn
Share of collections deposited in escrow
70%
Sale proceeds realised, Q1 2026-27
₹12,18,000
Not verified yet: Receivable, sold flats; Cost left; Cost left vs buyer dues; Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Site photos, Q2 2026-27
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Anekal taluk average, July 2023: 21.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class
Through the year
January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several)
Water supply, as filed
Borewell, Local authority (Neriga Grama Panchayati)
Distances
Within 3 km of the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot