New projects in Murshidabad
West Bengal
19 projects are registered with the real estate regulator in Murshidabad, West Bengal. 15 of them have enough filed detail for a full report here: who is building it, when it is due, and any court cases or complaints filed against it.
10 of the 15 are still filed as under construction, and 6 are already past the completion date their promoter filed.
All 15 projects
| "Saanvi"WBRERA/P/MUR/2024/002182 | Suvdeep Construction | – | Mixed | Registered | Jul 2027 | 16 |
| Arihant Heights IIIHIRA/P/MUR/2019/000623 | Arihant Neerman | – | Mixed | Under constructionpast its filed completion date | Oct 2021 | 35 |
| BISHNUPUR ENCLAVEWBRERA/P/MUR/2023/000401 | M.L. Jain Developers | – | Mixed | Under constructionpast its filed completion date | Dec 2025 | 29 |
| Classic ApartmentHIRA/P/MUR/2020/000796 | Taracon | – | Mixed | Under constructionpast its filed completion date | May 2022 | 27 |
| FIJAX MANSIONWBRERA/P/MUR/2023/000342 | Fijax Construction Private Limited | – | Apartments | Registered | Dec 2028 | 30 |
| FIJAX SPACEWBRERA/P/MUR/2024/000999 | Fijax Construction Private Limited | – | Apartments | Registered | Dec 2028 | 54 |
| FORTUNAWBRERA/P/MUR/2024/001018 | Swarnapradeep Infrastructural Solutions | – | Mixed | Registered | May 2027 | 54 |
| LIM MANSIONWBRERA/P/MUR/2024/002185 | Lim Renovation | – | Mixed | Under construction | Aug 2029 | 145 |
| PALASH KOLIWBRERA/P/MUR/2023/000613 | Bharat Shelter Development Limited | – | Apartments | Under construction | Dec 2030 | 72 |
| PRANTIKHIRA/P/MUR/2019/000616 | Prantik Construction Private Limited | – | Apartments | Under constructionpast its filed completion date | Sep 2021 | 15 |
| SHEFALI APARTMENTWBRERA/P/MUR/2026/003865 | Shib Sankar Construction | – | Mixed | Under construction | Oct 2027 | 23 |
| SIGNATURE TOWERWBRERA/P/MUR/2024/001860 | Ahmed Trade Corp. Private. Limited | – | Mixed | Registered | Mar 2027 | 140 |
| Swapnabhumi VWBRERA/P/MUR/2024/001097 | Swapnabhumi V | – | Mixed | Under constructionpast its filed completion date | Jun 2025 | 40 |
| TARACON ENCLAVEHIRA/P/MUR/2020/000797 | Taracon | – | Mixed | Under constructionpast its filed completion date | Sep 2022 | 43 |
| TARACON ENCLAVE BUILDING BWBRERA/P/MUR/2025/002468 | Taracon | – | Mixed | Under construction | Dec 2026 | 46 |
Listed in order of how much each report can say, then by name. Status and completion dates are as each promoter filed them. Every project in West Bengal