Ambegaon
Haveli taluka · Pune
26 residential projects registered with MahaRERA name Ambegaon as their locality. Across the 5 of them with a carpet rate on file, the median works out at ₹7,058 per sqft of RERA carpet : carpet area, not super-built-up, as filed with the regulator rather than asked.
10 are still filed as ongoing, and 9 of those are already past the completion date the promoter themselves declared. 518 units remain unsold against 24 sold.
| AMITs BLOOMFIELD PHASE III - J AND K BUILDINGP52100005644 | Amit Enterprises Housing Limited | Ongoing | Jan 2027 | 6 / 246 | ₹8,352filed |
| Ankur ResidencyP52100078740 | Ankur Developers | New | Feb 2027 | 2 / 18 | ₹7,009filed |
| GV7 INSIGNIA BUILDING B AND CP52100080265 | M/S Chirag Developers | New | Apr 2030 | 2 / 116 | ₹10,361filed |
| NAKSHATRA APARTMENTP52100079588 | Ajinkya Namdeo Kate | New | May 2027 | 0 / 22 | ₹7,058filed |
| WISTERIAP52100051103 | Jnd Construction | New | Apr 2028 | 14 / 116 | ₹6,083filed |
| ASTON PLAZA PHASE IP52100013383 | SKP Corp Private Limited | New | Mar 2019 | – | – |
| Atmosphere - C WingP52100000821 | JRS Associates | Ongoingpast its promised date | Dec 2021 | – | – |
| Bhakti ParkP52100024924 | Pravin Haibatrao Shinde | New | Aug 2024 | – | – |
| CAPELLAP52100051877 | D K Realties | New | Dec 2026 | – | – |
| EXCELLAA PLAZZOP52100021440 | The Excellaa | New | Dec 2025 | – | – |
| EXCELLAA RESIDENCYP52100021432 | The Excellaa | New | Dec 2025 | – | – |
| JIDNYASA WING BP52100020072 | Jidnyasa Pramoters & Developers | New | May 2022 | – | – |
| KOOL HOMES PANCHAMRUTP52100001452 | Sanket Properties Private Limited | Ongoingpast its promised date | Dec 2020 | – | – |
| Kool Homes Panchamrut Phase IIP52100030080 | Sanket Properties Private Limited | New | Dec 2023 | – | – |
| KRUSHNAGANDHAP52100016803 | Devidas Bachchu Dangat | New | Jul 2022 | – | – |
| MSR OLIVEP52100008615 | Mind Space Realty Pvt. Ltd. | Ongoingpast its promised date | Mar 2025 | – | – |
| PARIJAT BUILDING AP52100005323 | Shri Venkatesh Sharada Infracon | Ongoingpast its promised date | Dec 2017 | – | – |
| PRIMEROSEP52100008282 | Gurukrupa Developers | Ongoingpast its promised date | Nov 2018 | – | – |
| ROYAL CITY BUILDING A1 AND B ROW HOUSES PHASE IP52100023365 | Ms Momin Infra Through Shafi Hazi Nazir Momin | New | Apr 2024 | – | – |
| Sai sparshP52100021019 | Sai Rachana Lifespaces | New | Dec 2025 | – | – |
| VENKATESH LAKE LIFE PHASE 1P52100001126 | Shree Venkatesh Realties | Ongoingpast its promised date | Jun 2018 | – | – |
| WESTBROOKP52100003178 | Tara Constructions | Ongoingpast its promised date | May 2024 | – | – |
| WESTBROOK AVENUEP52100046193 | Tara Constructions | New | Jun 2024 | – | – |
| ZIGGURAT G BuildingP52100003097 | M/S Built Up | Ongoingpast its promised date | Dec 2019 | – | – |
| ZIGGURAT H BuildingP52100002178 | M/S Built Up | Ongoingpast its promised date | Mar 2019 | – | – |
| P52100017615P52100017615 | – | Registered | – | – | – |
Every rate is RERA carpet area. Source: MahaRERA public register and each promoter's own quarterly filings. See these on the map →