Overview
Akasha By Essem18
Overview
Akasha By Essem18
Overview
Akasha By Essem18
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 2 | Clear |
| Disputes & cases | – | – | 1 | Clear |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | ||||
| Aadya SereneExtended to 24-03-2028 | M/s. JUST NATURAL | Apartment | – | Mar 2028 |
| Amigo AmparoExtended to 30-12-2026 | AMIGO PROPERTIES INDIA LLP | Apartment | 906–1,062 sqft carpet (as filed) | Dec 2026 |
| Antaliea HomesLapsed · completion date passed | VNG Developers | Apartment | 2,217 sqft carpet (as filed) | Jul 2019 |
| Aparna MapleCompleted · OC 21-04-2022 | Aparna Constructions And Estates Pvt Ltd | Apartment | 721 sqft carpet (as filed) | Completed |
| Assetz Zen & SatoActive · 60% built | APG TOWNSHIPS PRIVATE LIMITED | Apartment | 267–1,962 sqft carpet (as filed) | May 2030 |
| Baldota SummitActive · 18% built | BALDOTA BUILDERS AND DEVELOPERS | Apartment | 976–986 sqft carpet (as filed) | Mar 2030 |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BBMP) | Sanctioned 19 Mar 2025 · No. BBMP/Addl.Dir/JDNORTH/0115/23-24 | |
|---|---|---|
| Power NOC | Filed with the registration |
Disputes & cases
Builder: Essem18 Developers Private Limited
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None found. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None found. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
Contract & costs
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Interest the builder pays on late possession | SBI MCLR + 2% (Karnataka RERA Rules, r.16) |
|---|
| Defect liability | 5 years |
|---|
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | Bajaj Housing Finance Limited · ₹25.00 Cr disbursed | |
|---|---|---|
| Records searched to | 28 Aug 2025 | |
| Building plan (BBMP) | Sanctioned 19 Mar 2025 | |
| Escrow bank | ICICI Bank · BASAVANAGUDI,BENGALURU |
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 62 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| – |
| 1 |
| – |
| Review |
| Construction & progress | – | – | 1 | Clear |
|---|
| Developer & finance |
|---|
| Developer | – | 1 | – | Review |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Bhartiya City Nikoo Homes 1Completed (regulator flag) | Bhartiya City | Apartment | 620–2,800 sqft | Completed |
| Bhartiya City Nikoo Homes 4Lapsed · completion date passed | Bhartiya City | Apartment | 450–2,500 sqft | – |
8 of 80 other projects in Thanisandra, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Akasha By Essem18 in the interactive atlas
Approval or registration
Land use converted
DC Office Bengaluru · Survey 34/2
K-RERA filing, land schedule
Approval or registration
Land use converted
DC Office Banglore · Survey 34/9
K-RERA filing, land schedule
Approval or registration
Land use converted
DC Office Bengaluru · Survey 34/10
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BBMP · plan BBMP/Addl.Dir/JDNORTH/0115/23-24
K-RERA filing, approvals
Approval or registration
Khata issued
E Khatha · BBMP · Survey 34/2, 34/9, 34/10
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · BBMP · Survey 34/2, 34/9, 34/10
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · BBMP · Survey 34/2, 34/9, 34/10
K-RERA filing, land schedule
Transfer of the land
Title deed executed
Sy 34/2, Geddalahalli village; Sy 34/9, Geddalahalli village; and 2 more items
Title deed filed with K-RERA, pp. 1, 33, 34 · See it in Documents
Approval or registration
RERA registration
PRM/KA/RERA/1251/446/PR/101125/008235
K-RERA registration ·
Approval or registrationTransfer of the landTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 28 Aug 2025 |
|---|
| Developer's project loan | Bajaj Housing Finance Limited · ₹25.00 Cr disbursed |
|---|
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: ADLR Sketch Essem18 Developers Pvt Ltd, 1 page, not in English.
| Filed survey numbers matched to the KGIS map | 3 of 3 | |
|---|---|---|
| Whole survey numbers on the KGIS map | 36,314 sq m | |
| Extent the filed land schedule names for these survey numbers | 4,815 sq m | |
| Plot area against the filed extent | 7.54 times | |
| Land area filed with K-RERA | 4,750 sq m | |
| Village, hobli and taluk on the KGIS map | Gedhlahalli, K R PURA2 hobli, BANGALORE-EAST taluk | |
| Mutation entry | None open on 3 of 3 filed surveys |
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Survey numbers | 34/2, 34/9, 34/10 | |
|---|---|---|
| Land extent, Sy 34/2 | 30 Guntas | |
| Land extent, Sy 34/9 | 7.8 Guntas | |
| Land extent, Sy 34/10 | 9.8 Guntas | |
| Whole survey numbers on the KGIS map | 36,314 sq m (the project holds a share) | |
| Land area of this registration | 4,750 sq m | |
| Khata | E Khatha · BBMP · 4 Jun 2025 |
| Survey | Owners on the RTC | RTC extent | Filed extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|
| Sy. No. 34/2 | Not read yet | 0 | ||||
| Sy. No. 34/9 | Not read yet | 0 | ||||
| Sy. No. 34/10 | Not read yet | 0 |
| Fire NOC | KSFES/NOC/018/2024 · issued 31 May 2024 | Clear |
|---|
| Environmental clearance | SEIAA 52 CON 2024 · EC identification no. EC24C3801KA5665182N · issued 12 Mar 2025 | Clear |
|---|
| Airport height NOC | Filed with the registration |
|---|
| Pollution board (CFE) | consent order CTE-126387 · issued 17 Feb 2024 |
|---|
| Water and sewerage NOC (BWSSB) | issued 31 Aug 2024 |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 May 2029 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 34/2 | Converted 23 Dec 2002 · DC Office Bengaluru | |
| Sy 34/9 | Converted 19 May 2023 · DC Office Banglore | |
| Sy 34/10 | Converted 19 May 2023 · DC Office Bengaluru | |
| Survey numbers | 34/2 · 34/9 · 34/10 |
3BHK · avg 107 m² 94%3BHK - duplex 4.8%1BHK · 55 m² 1.2%
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| 1BHK | 1 | 592 |
| 3BHK | 78 | 89,653 |
| 3BHK - duplex | 4 | 4,919 |
| Sold, Q2 2026-27 | 7 / 85 | |
|---|---|---|
| Unsold, Q2 2026-27 | 78 | |
| Months to sell, derived from filed bookings | Too few bookings to project (4 flats booked in 9 months) |
| Vkk Grand | about 1 km | Locked | |
|---|---|---|---|
| Brr North Excellency Phase I | about 1.5 km | Locked | |
| SOBHA Victoria Park Phase 1 | about 1.5 km | Locked | |
| Nava Skanda Bellavita | about 2 km | Locked | |
| Lodha Mirabelle | about 2.5 km | Locked | |
| Mirabelle Phase 2 | about 2.5 km | Locked | |
| Sumadhura Solea | about 2.5 km | Locked | |
| The Pearl Paradise | about 2.5 km | Locked | |
| Sumadhura Epitome | about 2.5 km | Locked | |
| Sattva La Vita | about 3 km | Locked | |
| Sobha City Athena | about 3 km | Locked | |
| Legacy Saviero | about 3.5 km | Locked |
| Akasha By Essem18 This project | This project is the point the others are measured from | 31 May 2029 | 8% (7 of 85) | Not verified yet |
|---|---|---|---|---|
| Vkk Grand | about 1 km | 30 Jun 2027 | 49% (59 of 120) | Locked |
| Brr North Excellency Phase I | about 1.5 km | 31 Dec 2029 | 33% (34 of 104) | Locked |
| SOBHA Victoria Park Phase 1 |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | 93% Residential (main), 7% Valley / drain buffer, over the filed survey numbers | Review |
|---|---|---|
| Nearest government-flagged flood location | about 1 km, Vaddera Palya (Railway track) | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Swimming Pool, built | 0% | |
| Power Backup, built | 0% | |
| Covered parking per unit | 1.76 (150 covered spaces for 85 units) | |
| Power backup | Declared by the promoter |
As the promoter reported itPossession date in the agreement
| Main structure | 14% · planned by 30 Sep 2027 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 30 Apr 2029 | |
| Club house | Not started | |
| Completion | 32% | |
| Completion, accountant | 31.6% of the estimated cost spent |
| Possession, agreement | 27 May 2029 | |
|---|---|---|
| Schedule end | 31 May 2029 | |
| RERA completion date | 31 May 2029 | |
| Work began, as filed | 5 Aug 2025 |
| Building heights, fire NOC | 34.95 m filed |
|---|
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Provided, 65.36 sq m |
|---|
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | KSFES/NOC/018/2024 · issued 31 May 2024 | |
| Environmental clearance | SEIAA 52 CON 2024 · EC identification no. EC24C3801KA5665182N · issued 12 Mar 2025 | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Chartered accountant's certificate, registration | Dated 3 Sep 2025 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹14.74 Cr 16.1%Development · ₹77.06 Cr 83.9%
| Estimated cost, at registration | ₹91.80 Cr | |
|---|---|---|
| Estimated cost, Form 4 Q2 2026-27 | ₹91.80 Cr | |
| Cost incurred | ₹29.05 Cr (31.6% of the Form 4 Q2 2026-27 estimate) |
Sold (7) 8.2%Unsold (78) 91.8%
| Sold, Q3 2025-26 | 3 / 85 · 82 available | |
|---|---|---|
| Sold, Q4 2025-26 | 6 / 85 · 79 available | |
| Sold, Q1 2026-27 | 7 / 85 · 78 available | |
| Sold, Q2 2026-27 | 7 / 85 · 78 available | |
| Unsold, Q2 2026-27 | 78 | |
| Sold in Q4 2025-26 | 3 | |
| Sold in Q1 2026-27 | 1 | |
| Sold in Q2 2026-27 | 0 |
| Escrow bank | ICICI Bank · BASAVANAGUDI,BENGALURU | |
|---|---|---|
| Designated account, collected | ₹25.0 L in Q2 2026-27 | |
| Designated account, withdrawn | ₹3.5 L in Q2 2026-27 (14% of that quarter's deposits) | |
| Net amount withdrawable, Form 4 | ₹27,46,49,811 | |
| Escrow account, Q2 2026-27 | ₹3.5 L withdrawn | |
| Escrow account to date, Q4 2025-26 | ₹1.04 Cr deposited from sales, ₹60.2 L withdrawn | |
| Withdrawn from the escrow account to date | ₹1,58,90,000 |
| K-RERA registrations under this promoter | 7 | |
|---|---|---|
| Marked completed | 3 | |
| Past promised date, not completed | 0 | |
| Other phases under this promoter name | 5 | |
| With a filed extension or completion | 3 (3 completed, 0 extended) | |
| Average schedule slip | 3 months |
| about 1.5 km |
| 31 Dec 2027 |
| 93% (280 of 300) |
| Locked |
| Nava Skanda Bellavita | about 2 km | 31 Dec 2029 | 18% (63 of 360) | Locked |
|---|
| Lodha Mirabelle | about 2.5 km | 30 Jun 2028 | 96% (418 of 437) | Locked |
|---|
| Mirabelle Phase 2 | about 2.5 km | 31 May 2030 | 61% (173 of 284) | Locked |
|---|
| Projects within 4 km, counted | 61 (61 with an approximate location) | |
|---|---|---|
| Flats in them | 12,670 | |
| Booked | 7,645 of 12,670 (60%) | |
| Unsold | 5,025 | |
| Booked a month, pooled | 192 flats | |
| Months to sell, pooled | 25 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 30.5 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru East taluk average, July 2023: 27.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | BWSSB |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 6.5 km, Benniganahalli | |
| Metro, under construction | about 2.5 km, Nagawara |
| Kempegowda Airport | 23.5 | 17.5 |
| MG Road (CBD) | 11.5 | 9.5 |
| Manyata Tech Park | 5.5 | 3 |
| ITPL, Whitefield | 18.5 | 12 |
| Ecospace, Bellandur ORR | 23.5 | 14.5 |
| Electronic City Ph 1 | 31.5 | 24 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 0.5 km, named Sewage Treatment Plant on OpenStreetMap | |
| Quarry | about 3 km to the north | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |