Very good Amenities and configurations in this vicinity. Chandan has been helpful by providing all necessary information about the project. thank you
Overview
Bren Avaana
Overview
Bren Avaana
Overview
Bren Avaana
Overview
Photo: Bren AvaanaTitle & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
3BHK · avg 92 m² 98.8%2BHK
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 29 Jul 2024 | |
| Escrow bank | HDFC · KASTURBA GANDHI MARG |
Data room
263 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Very good Amenities and configurations in this vicinity. Chandan has been helpful by providing all necessary information about the project. thank you
Premium 3bhk project, Good connectivity just 10mins from nice road, project has all the amenities and Good open area with lush greenery.
Quite horrible people. They partner with people who in our case was Champions on Sarjapur Road and the kind of issues they have created by leasing out the building in front of the apartment to first Belanus and now to Apollo is just…
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 3 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | – | – | – |
| 1410 The ResidencesCompleted (regulator flag) | Hitin Property Developments | Apartment | 1,550 sqft carpet (as filed) | Completed |
| A.N. ComfortsCompleted · OC 30-12-2019 | D. Anand Naidu | Apartment | – | Completed |
| Aarohana AlterraActive · 2% built | AAROHANA PROJECTS | Apartment | 1,133–1,936 sqft carpet (as filed) | Aug 2033 |
| AayodhyaLapsed · completion date passed | UTOCORP | Apartment | 285 sqft carpet (as filed) | Jun 2024 |
| AiekyaCompleted · OC 18-08-2025 | Avaneesh Ventures | Apartment | 1,129 sqft carpet (as filed) | Completed |
| Aikyam Emerald GroveCompleted (regulator flag) | AIKYAM VENTURES | Plot | – | Completed |
| Amberstone ElanzaActive · 63% built | SRIVARI VENTURES | Apartment | 804–1,161 sqft carpet (as filed) | Dec 2028 |
| Amberstone IlluminaActive · 54% built | SRIVARI DWELLINGS | Apartment | 793–1,071 sqft carpet (as filed) | Dec 2028 |
8 of 170 other projects in Kanakapura Road, A to Z. Status is taken from each project's own filing.
All 180 projects in Kanakapura Road → · Bren Corporation Private Limited's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Bren Avaana in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (Local Planning Authority) | Sanctioned 29 Jul 2024 · No. Ka.Yo.Pra/Pra.Pra.Patra/62/2023-24/843 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | KSFES/NOC/232/2023 · issued 27 Nov 2023 | Clear |
| Environmental clearance | SEIAA 191 CON 2023 · EC identification no. EC24B038KA183961 · issued 8 May 2024 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | consent order CTE-344126 · issued 5 Jul 2024 · valid until 4 Jul 2029 | Clear |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 29 Feb 2028 |
| Land conversion | 18 of 18 parcels converted | |
|---|---|---|
| Sy 188/1, 188/2, 188/3, 189/2, 190/2 | Converted 11 Jul 2023 · The Deputy Commissioner, Bangalore Urban District | |
| Sy 189/3, 189/4, 189/5, 189/6 | Converted 31 Dec 2020 · The Deputy Commissioner, Bangalore Urban District | |
| Sy 190/3, 190/4, 190/5, 190/6, 191/2… | Converted 7 Mar 2020 · The Deputy Commissioner, Bangalore Urban District | |
| Sy 190/7, 191/3 | Converted 19 Dec 2020 · The Deputy Commissioner, Bangalore Urban District | |
| Sy 193 | Converted 4 Dec 2019 · The Deputy Commissioner, Bangalore Urban District | |
| Survey numbers | 188/1 · 188/2 · 188/3 · 189/2 · 189/3 · 189/4 · 189/5 · 189/6 · 190/2 · 190/3 · 190/4 · 190/5 · 190/6 · 190/7 · 191/2 · 191/3 · 191/4 · 193 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| 2BHK | 4 | 3,132 |
| 3BHK | 323 | 3,18,633 |
| Sold, Q2 2026-27 | 67 / 327 | |
|---|---|---|
| Unsold, Q2 2026-27 | 260 | |
| Months to sell, derived from filed bookings | 73 months |
| Sattva Springs | about 0.5 km | Locked | |
|---|---|---|---|
| Harivishram | about 0.5 km | Locked | |
| Axis Amarissa | about 1.5 km | Locked | |
| Jhanavi Trishul Alaska | about 5.5 km | Locked | |
| Mahindra Eden Phase-2 | about 7 km | Locked | |
| Sattva Forest Ridge | about 7 km | Locked | |
| Srivara Vasudha | about 7.5 km | Locked | |
| Platinum Landmark | about 8 km | Locked | |
| Good Earth Cadence | about 9 km | Locked | |
| Good Earth Ochre | about 9.5 km | Locked | |
| Garden Square | about 10 km | Locked | |
| Samaya Sunshine | about 10 km | Locked |
| Bren Avaana This project | This project is the point the others are measured from | 29 Feb 2028 | 20% (67 of 327) | Not verified yet |
|---|---|---|---|---|
| Sattva Springs | about 0.5 km | 18 Sep 2027 | 38% (25 of 66) | Locked |
| Harivishram | about 0.5 km | 31 Mar 2027 | 100% (152 of 152) | Locked |
| Axis Amarissa | about 1.5 km | 31 Dec 2029 |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | 94% Residential (main), 6% Commercial (business), over the filed survey numbers | |
|---|---|---|
| Nearest government-flagged flood location | about 6 km, Mantri Lake view Appartment Next to Talagattapura Lake | |
| Government land in the filed surveys | Sy 191: 6% of the parent survey, 0.07 of 1.31 acres | Review |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Outdoor Sports facility, built | 0% | |
| Swimming Pool, built | 0% | |
| Parks, built | 0% | |
| Water and Sanitation, built | 0% | |
| Covered parking per unit | 1.00 (327 covered spaces for 327 units) | |
| Power backup | Declared by the promoter |
As the promoter reported it
| Main structure | 50% · planned by 11 Mar 2026 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 15 May 2027 | |
| Club house | Not started | |
| Completion | 20% |
| Schedule end | 14 Jul 2027 | |
|---|---|---|
| RERA completion date | 29 Feb 2028 | |
| Completion date, agreement | 29 Feb 2028 | |
| Work began, as filed | 29 Jul 2024 |
| Structure | RCC structure, Mivan aluminium formwork | |
|---|---|---|
| Building heights, fire NOC | 75.33 m filed, 3 towers |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Wiring | Fire-resistant wiring | |
|---|---|---|
| Sanctioned load per flat | Per flat: 5 kW | |
| Power backup | Provided, 201 sq m |
| Structural engineer, quarterly | Form 6 · Feb 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | KSFES/NOC/232/2023 · issued 27 Nov 2023 | |
| Environmental clearance | SEIAA 191 CON 2023 · EC identification no. EC24B038KA183961 · issued 8 May 2024 | |
| Architect, quarterly | Form 5 · Feb 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 31 Jul 2024 · site inspected 31 Jul 2024 | |
| Engineer's certificate, registration | Dated 29 Aug 2024 | |
| Chartered accountant, Form 4 | Dated 13 Oct 2026 | |
| Architect's quarterly progress certificate dated | 30 Sep 2026 | |
| Architect's site inspection for the quarterly progress certificate | 30 Sep 2026 |
Land · ₹32.96 Cr 12.7%Development · ₹226.28 Cr 87.3%
| Estimated cost, at registration | ₹261.07 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹228.10 Cr | |
| Estimated cost, engineer's certificate | ₹261.07 Cr, same as the filing | |
| Estimated cost, Form 4 Q2 2026-27 | ₹228.10 Cr |
Sold (67) 20.5%Unsold (260) 79.5%
| Sold, Q3 2025-26 | 35 / 327 · 292 available | |
|---|---|---|
| Sold, Q4 2025-26 | 44 / 327 · 283 available | |
| Sold, Q1 2026-27 | 54 / 327 · 273 available | |
| Sold, Q2 2026-27 | 67 / 327 · 260 available | |
| Unsold, Q2 2026-27 | 260 | |
| Sold in Q4 2025-26 | 9 | |
| Sold in Q1 2026-27 | 10 | |
| Sold in Q2 2026-27 | 13 |
| Escrow bank | HDFC · KASTURBA GANDHI MARG | |
|---|---|---|
| Designated account, collected | ₹6.54 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹6.54 Cr in Q2 2026-27 (100% of that quarter's deposits) | |
| Net amount withdrawable, Form 4 | ₹15,63,73,023 | |
| Withdrawn from the escrow account to date | ₹29,77,36,163 | |
| Share of collections deposited in escrow | 100% |
| K-RERA registrations under this promoter | 13 | |
|---|---|---|
| Marked completed | 6 | |
| Past promised date, not completed | 1 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 30% (24 of 81) |
| Locked |
| Jhanavi Trishul Alaska | about 5.5 km | 30 Sep 2028 | 32% (47 of 148) | Locked |
|---|
| Mahindra Eden Phase-2 | about 7 km | 30 Jul 2027 | 100% (250 of 250) | Locked |
|---|
| Sattva Forest Ridge | about 7 km | 31 Dec 2029 | 75% (304 of 407) | Locked |
|---|
| Projects within 4 km, counted | 10 (10 with an approximate location) | |
|---|---|---|
| Flats in them | 1,819 | |
| Booked | 550 of 1,819 (30%) | |
| Unsold | 1,269 | |
| Booked a month, pooled | 11 flats | |
| Months to sell, pooled | 56 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 23.2 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 10 CGWB wells in Bengaluru South taluk read in this class | |
| Through the year | January 2025: 2.2 m (5 wells), Pre-monsoon 2025: 1.9 m (10 wells), August 2025: 1.5 m (11 wells), depth below ground of CGWB's monitoring wells in Bengaluru South taluk (the median where there are several) | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 5.5 km, Silk Institute | |
| Metro, under construction | about 11 km, Kalena Agrahara |
| Kempegowda Airport | 56.5 | 47.5 |
| MG Road (CBD) | 23.5 | 20.5 |
| Manyata Tech Park | 32 | 28 |
| ITPL, Whitefield | 40.5 | 31 |
| Ecospace, Bellandur ORR | 28.5 | 22 |
| Electronic City Ph 1 | 25 | 18 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 0.5 km |