Overview
Century Trails (Phase 1 + 2)
Overview
Century Trails (Phase 1 + 2)
Overview
Century Trails (Phase 1 + 2)
Overview
Title & ownership
Approvals
| Building plan (Local Planning Authority) | Sanctioned 3 Nov 2023 · No. STRRPA/TP/LAO/27/2022-23 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department |
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 3 Nov 2023 | |
| Escrow bank | Axis Bank · Yeshwanthpur Branch |
Data room
178 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 5 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 5 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | 1 | Review |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
Other sites that list or cover this project. DOSL does not vouch for them, and they can be older than the filing above.
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
All 308 projects in Devanahalli → · Century Real Estate's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Century Trails (Phase 1 + 2) in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| Airport height NOC | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Mar 2027 |
| Land conversion | 9 of 9 parcels converted | |
|---|---|---|
| Sy 113/1, 113/2, 115/1, 115/2, 117/2 | Converted 4 Mar 2005 · Assistant Commissioner, Doddaballapura | |
| Sy 114, 126 | Converted 27 Jun 2005 · Assistant Commissioner, Doddaballapura | |
| Sy 117/1 | Converted 12 Aug 1997 · Deputy Commissioner, Bangalore Rural | |
| Sy 117/3 | Converted 4 Mar 2005 · Deputy Commissioner, Bangalore Rural | |
| Survey numbers | 113/1 · 113/2 · 114 · 115/1 · 115/2 · 117/1 · 117/2 · 117/3 · 126 |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Ekta Elements | 9.9 km | Locked |
|---|
| Fortius Good Earth | about 10.5 km | Locked |
|---|
| Earth Aroma Phase-2 | 10.4 km | Locked |
|---|
| Earth Aroma | 10.6 km | Locked |
|---|
| Vaishnavi At-One Life IV | about 11.5 km | Locked |
|---|
| Century Trails (Phase 1 + 2) This project | This project is the point the others are measured from | 31 Mar 2027 | – | Not verified yet |
|---|---|---|---|---|
| Ekta Elements | 9.9 km | 31 Dec 2027 | – | Locked |
| Fortius Good Earth | about 10.5 km | 31 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | 10.4 km | 31 Dec 2025 | – | Locked |
| Earth Aroma | 10.6 km | 31 Dec 2024 | – | Locked |
| Vaishnavi At-One Life IV | about 11.5 km | 18 Dec 2027 | – | Locked |
Map of the ground within about 450 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture | Review |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 66 kV, 500 m from the site | Clear |
| Nearest government-flagged flood location | 20.8 km, Kondappa layout |
| Nearest storm drain | 1.9 km to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 190 m to the north-east, an unnamed water body |
| RERA completion date | 31 Mar 2027 | |
|---|---|---|
| Work began, as filed | 1 Dec 2023 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Chartered accountant's certificate, registration | Dated 6 Nov 2023 |
|---|
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹86.26 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹46.13 Cr | |
| Estimated cost, chartered accountant's certificate | ₹86.26 Cr, same as the filing |
| Escrow bank | Axis Bank · Yeshwanthpur Branch |
|---|
| K-RERA registrations under this promoter | 21 | |
|---|---|---|
| Marked completed | 2 | |
| Past promised date, not completed | 7 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 450 m of the site.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Bidaluru Grama Panchayat) | |
| Nearest city water main | 16.3 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 1.9 km to the south, tertiary drain | |
|---|---|---|
| Ground level | 929 m above sea level, plus or minus 4 m | |
| Metro, operational | 30.9 km, K.R. Puram | |
| Metro, under construction | 9.0 km, Airport City |
| Kempegowda Airport | 17.7 | 23 | 9.4 |
| MG Road (CBD) | 43.2 | 46 | 34.8 |
| Manyata Tech Park | 38.4 | 42 | 26.8 |
| ITPL, Whitefield | 47.9 | 45 | 33.2 |
| Ecospace, Bellandur ORR | 58.5 | 58 | 39.3 |
| Electronic City Ph 1 | 63.0 | 71 | 48.9 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | 1.6 km to the north-west | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |