Overview
Lake Botanica
Overview
Lake Botanica
Overview
Lake Botanica
Overview

Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Survey | Land converted | Sale deed | Khata | Extent |
|---|---|---|---|---|
| Survey 31 | ||||
| 31/4 | 28 Jun 2024 | |||
Approvals
| Building plan (BIAPPA) | Sanctioned 25 Feb 2025 · No. BIAAPA/TP/LAO/29/2024-25/3108 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Records searched to | 10 Sep 2025 | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 25 Feb 2025 | |
| Escrow bank | HDFC · Richmond Road |
Data room
169 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 10 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 10 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Lake Botanica in the interactive atlas
| 10 Oct 2023in favour of Lake Botanica Private Limited |
| 25 Feb 20251 Acre 6.5 Guntas · Panchayathi |
| 1 Acre 6.5 Guntas |
| 31/5 | 26 Jul 2024District Commissioner | 30 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20251 Acre 6.5 Guntas · Panchayathi | 1 Acres 6.5 Guntas |
|---|
| 32 | 3 Jul 2024District Commissioner | 21 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20252 Acres 10 Guntas · Panchayathi | 2 Acre 10 Guntas |
|---|
| Survey 34 | ||||
|---|---|---|---|---|
| 34/1 | 14 Nov 2024District Commissioner | 30 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20250 Acres 16 Guntas · Panchayathi | 0 Acres 16 Guntas |
| 34/2 | 12 Apr 2005Asst Commissioner Bangalore North | 30 Jun 2025in favour of Lake Botanica Private Limited | 26 Jun 20250 Acres 29 Guntas · Panchayathi | 0 Acres 29 Guntas |
| 34/3 | 13 Apr 2005Asst Commissioner, Bangalore North | 30 Jun 2025in favour of Lake Botanica Private Limited | 26 Jun 20250 Acres 31 Guntas · Panchayathi | 0 Acres 31 Guntas |
| Survey 35 | ||||
|---|---|---|---|---|
| 35/1 | 1 Feb 2005Asst. Commissioner, Bangalore North | 30 Jun 2025in favour of Lake Botanica Private Limited | 26 Jun 20250 Acres 35 Guntas · Panchayathi | 0 Acres 35 Guntas |
| 35/2 | 29 Jun 2024District Commissioner | 30 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20251 Acres 2 Guntas · Panchayathi | 1 Acres 2 Guntas |
| 40/4 | 23 Dec 2024District Commissioner | 30 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20253 Acres 11 Guntas · Panchayathi | 3 Acres 11 Guntas |
|---|
| 49/3 | 19 Jun 2024District Commissioner | 30 Jun 2025in favour of Lake Botanica Private Limited | 25 Feb 20251 Acres 10 Guntas · Panchayathi | 1 Acre 10 Guntas |
|---|
K-RERA filing, land schedule
Deeds read, and the whole project
Transfer of the land
Title deed executed
Consideration ₹3.49 Cr · Sy 31/4
Title deed filed with K-RERA, pp. 1, 5, 11 · See it in Documents
Approval or registration
Building plan sanctioned
BIAPPA · plan BIAAPA/TP/LAO/29/2024-25/3108
K-RERA filing, approvals
Transfer of the land
Title deed executed
Consideration ₹6.75 Cr · Sy 32, Jala hobli, Yelahanka taluk
Title deed filed with K-RERA, pp. 1, 9, 13 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹3.15 Cr · Sy 35/2, Kuduregere village, Jala hobli, Yelahanka taluk
Title deed filed with K-RERA, pp. 1, 5, 10 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹3.79 Cr · Sy 49/2
Title deed filed with K-RERA, pp. 1, 7, 12 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹2.17 Cr · Sy 34/2, Kuduregere village, Jala hobli, Yelahanka taluk
Title deed filed with K-RERA, pp. 1, 7, 11 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹1.20 Cr · Sy 34/1, Kuduregere village, Jala hobli, Yelahanka taluk
Title deed filed with K-RERA, pp. 1, 7, 12 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹2.33 Cr · Sy 34/3, Kuduregere village, Jala hobli, Yelahanka taluk · 31 Guntas
Title deed filed with K-RERA, pp. 1, 7, 11 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹2.63 Cr · Sy 35/1, Yelahanka taluk
Title deed filed with K-RERA, pp. 1, 7, 11 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹9.82 Cr · Sy 40/4
Title deed filed with K-RERA, pp. 1, 12, 13 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹3.75 Cr · Sy 49/3; 49, Kuduregere village, Jala hobli, Yelahanka taluk · 1 Acre 10 Guntas
Title deed filed with K-RERA, pp. 1, 7, 12 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹4.65 Cr
Title deed filed with K-RERA, pp. 1, 7 · See it in Documents
Approval or registration
RERA registration
PRM/KA/RERA/1251/472/PR/250725/007954
K-RERA registration ·
Approval or registrationTransfer of the landTitle check
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 10 Sep 2025 |
|---|
Page 1
Page 1 of 3 of the encumbrance certificate. Filed with K-RERA: EC for Sy. No. 49/2, 3 pages.
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: 2 - ADLR Sketch, 1 page, not in English.
| Filed survey numbers matched to the KGIS map | 10 of 10 | |
|---|---|---|
| Whole survey numbers on the KGIS map | 1,10,053 sq m | |
| Extent the filed land schedule names for these survey numbers | 52,304 sq m | |
| Plot area against the filed extent | 2.1 times | |
| Village, hobli and taluk on the KGIS map | Kuduragere, JALA2 hobli, YALAHANKA taluk | |
| Sy. 32: filed extent, KGIS plot | 9,105 sq m, 9,657 sq m | |
| Sy. 40/4: filed extent, KGIS plot | 13,253 sq m, 19,224 sq m | |
| Sy. 49/3: filed extent, KGIS plot | 5,059 sq m, 15,351 sq m |
Satellite map with the 10 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 10 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Survey numbers | 31/4, 31/5, 32, 34/1, 34/2, 34/3 and 4 more | |
|---|---|---|
| Whole survey numbers on the KGIS map | 1,10,053 sq m (the project holds a share) | |
| Khata | 1 Acre 6.5 Guntas · Panchayathi · 25 Feb 2025; 2 Acres 10 Guntas · Panchayathi · 25 Feb 2025; 0 Acres 16 Guntas · Panchayathi · 25 Feb 2025; and 6 more | |
| Sale deed | Dated 10 Oct 2023, 21 Jun 2025, 30 Jun 2025 | |
| Sale deed in favour of | Lake Botanica Private Limited |
| Sy. No. 31/4 | 1 | 1 acre 7 guntas | Not read yet | |||||
| Sy. No. 31/5 | 1 | 1 acre 7 guntas | Not read yet | |||||
| Sy. No. 32 |
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2026 |
| Land conversion | 10 of 10 parcels converted | |
|---|---|---|
| Sy 31/4 | Converted 28 Jun 2024 · District Commissioner | |
| Sy 31/5 | Converted 26 Jul 2024 · District Commissioner | |
| Sy 32 | Converted 3 Jul 2024 · District Commissioner | |
| Sy 34/1 | Converted 14 Nov 2024 · District Commissioner | |
| Sy 34/2 | Converted 12 Apr 2005 · Asst Commissioner Bangalore North | |
| Sy 34/3 | Converted 13 Apr 2005 · Asst Commissioner, Bangalore North | |
| Other parcels | 4 more groups on the filing | |
| Survey numbers | 31/4 · 31/5 · 32 · 34/1 · 34/2 · 34/3 · 35/1 · 35/2 · 40/4 · 49/3 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| about 3 km |
| Locked |
| Fortius Good Earth | about 3 km | Locked |
|---|
| Earth Aroma Phase-2 | about 4 km | Locked |
|---|
| Earth Aroma | about 4 km | Locked |
|---|
| Ekta Elements | about 5.5 km | Locked |
|---|
| Lake Botanica This project | This project is the point the others are measured from | 31 Dec 2026 | – | Not verified yet |
|---|---|---|---|---|
| Vaishnavi At-One Life IV | about 3 km | 18 Dec 2027 | – | Locked |
| Fortius Good Earth | about 3 km | 31 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | about 4 km | 31 Dec 2025 | – | Locked |
| Earth Aroma | about 4 km | 31 Dec 2024 | – | Locked |
| Ekta Elements | about 5.5 km | 31 Dec 2027 | – | Locked |
| Projects within 4 km, counted | 24 (24 with an approximate location) | |
|---|---|---|
| Plots in them | 12,202 | |
| Booked | 7,455 of 12,202 (61%) | |
| Unsold | 4,747 | |
| Booked a month, pooled | 272 plots | |
| Months to sell, pooled | 15 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | 89% Agriculture, 11% Other, over the filed survey numbers | Review |
|---|---|---|
| Nearest government-flagged flood location | about 9.5 km, Kondappa layout | |
| Government land in the filed surveys | Sy 34: 32% of the parent survey, 0.69 of 2.17 acres | Review |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
As the promoter reported it

| Internal roads | 70% | |
|---|---|---|
| Completion | 65% | |
| Completion, accountant | 79.1% of the estimated cost spent |
| RERA completion date | 31 Dec 2026 | |
|---|---|---|
| Work began, as filed | 30 Jun 2025 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Feb 2026, Apr 2026 (2 filed) | Clear |
|---|---|---|
| Engineer's certificate, registration | Dated 4 Feb 2026 |
Land · ₹52.90 Cr 57.7%Development · ₹38.71 Cr 42.3%
| Estimated cost, at registration | ₹91.61 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹9.48 Cr | |
| Estimated cost, Form 4 Q4 2025-26 | ₹99.29 Cr | |
| Cost incurred | ₹78.53 Cr (79.1% of the Form 4 Q4 2025-26 estimate) | |
| Cost left | ₹20.76 Cr | |
| Receivable, sold plots | ₹14.56 Cr |
| Plots booked, Form 4 Q4 2025-26 | 26 |
|---|
| Escrow bank | HDFC · Richmond Road | |
|---|---|---|
| Designated account, collected | ₹3.34 Cr in Q4 2025-26 | |
| Designated account, withdrawn | ₹3.34 Cr in Q4 2025-26 (100% of that quarter's deposits) | |
| Amount withdrawable, Form 4 | ₹56,59,64,663 | |
| Net amount withdrawable, Form 4 | ₹51,62,09,718 | |
| Withdrawn from the escrow account to date | ₹4,97,54,945 | |
| Share of collections deposited in escrow | 100% |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 1 |
| 2 acres 10 guntas |
| 2 acres 10 guntas |
| 2 acres 15 guntas |
| The map differs by 5 guntas |
| Not read yet |
| Sy. No. 34/1 | 1 | 16 guntas | Not read yet |
| Sy. No. 34/2 | 1 | 0 guntas | Not read yet |
| Sy. No. 34/3 | 1 | 0 guntas | Not read yet |
| Sy. No. 35/1 | 1 | 35 guntas | Not read yet |
| Sy. No. 35/2 | 1 | 1 acre 2 guntas | Not read yet |
| Sy. No. 40/4 | 1 | 3 acres 11 guntas | 3 acres 11 guntas | 4 acres 30 guntas | The map differs by 1 acre 19 guntas | Not read yet |
| Sy. No. 49/3 | 1 | 1 acre 10 guntas | 1 acre 10 guntas | 3 acres 32 guntas | The map differs by 2 acres 22 guntas | Not read yet |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 19.5 km, Peenya | |
| Metro, under construction | about 3.5 km, Doddajala |
| Kempegowda Airport | 16.5 | 10 |
| MG Road (CBD) | 30.5 | 24 |
| Manyata Tech Park | 26 | 16.5 |
| ITPL, Whitefield | 41.5 | 26.5 |
| Ecospace, Bellandur ORR | 46 | 30.5 |
| Electronic City Ph 1 | 50.5 | 40 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 2 km to the west | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 2.5 km to the east |