Parkland View
Overview
Parkland View
Overview
Parkland View
Overview
Title & ownership
Approvals
| Building plan (BIAPPA) | Sanctioned 4 Feb 2025 · No. BIAAPA/TP/LAO/95/2024-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹16.46 Cr 74.5%Development · ₹5.64 Cr 25.5%
Loan & collateral
| Building plan (BIAPPA) | Sanctioned 4 Feb 2025 |
|---|
Data room
84 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 1 Lakh Multi Storey Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| Ab GardeniaApplied for completion 06/12/2023 | S & S Properties | Plot | – | Apr 2021 |
| Belvedere By Ukn Airport District -Phase 1Completed · OC 18-10-2023 | U.K.N. PROPERTIES PRIVATE LIMITED | Apartment | 425–1,013 sqft carpet (as filed) | Completed |
| Belvedere By Ukn Airport District -Phase 2Active · 51% built | U.K.N. PROPERTIES PRIVATE LIMITED | Apartment | 471–1,124 sqft carpet (as filed) | Feb 2031 |
| Bhartiya Garden Estate (Nikoo Homes 7)Active · 42% built | Bhartiya City | Apartment | 1,126–2,504 sqft | 2030 |
| Bhartiya Garden Estate Phase-2Active · 43% built | Bhartiya Urban Pvt Ltd | Apartment | 1,089 sqft carpet (as filed) | Feb 2031 |
| Bhartiya Garden Estate Phase-3Active · 43% built | Bhartiya Urban Pvt Ltd | Apartment | 959 sqft carpet (as filed) | Aug 2031 |
| Cornerstone MayberryRegistered · no quarterly update yet | AKR PROPERTY DEVELOPERS PRIVATE LIMITED | Plot | ~2,860–4,000 sqft (estimate: filed carpet plus 25%) | Apr 2025 |
8 of 14 other projects in Sadahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Parkland View in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 17 Sep 2025 |
| Land conversion | 2 of 2 parcels converted | |
|---|---|---|
| Sy 102/1 | Converted 27 Dec 2006 · DC | |
| Sy 104/1 | Converted 22 Jul 1998 · DC | |
| Survey numbers | 102/1 · 104/1 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Fortius Good Earth | about 3.5 km | Locked |
|---|
| Ekta Elements | about 4 km | Locked |
|---|
| Earth Aroma Phase-2 | about 4.5 km | Locked |
|---|
| Vaishnavi At-One Life IV | about 4.5 km | Locked |
|---|
| Earth Aroma | about 4.5 km | Locked |
|---|
| Parkland View This project | This project is the point the others are measured from | 17 Sep 2025 | – | Not verified yet |
|---|---|---|---|---|
| Fortius Good Earth | about 3.5 km | 31 Dec 2027 | – | Locked |
| Ekta Elements | about 4 km | 31 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | about 4.5 km | 31 Dec 2025 | – | Locked |
| Vaishnavi At-One Life IV | about 4.5 km | 18 Dec 2027 | – | Locked |
| Earth Aroma | about 4.5 km | 31 Dec 2024 | – | Locked |
| Projects within 4 km, counted | 31 (31 with an approximate location) | |
|---|---|---|
| Plots in them | 17,990 | |
| Booked | 12,165 of 17,990 (68%) | |
| Unsold | 5,825 | |
| Booked a month, pooled | 290 plots | |
| Months to sell, pooled | 20 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 12 km, Kondappa layout |
|---|
| Nearest storm drain | about 2.5 km to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body |
| RERA completion date | 17 Sep 2025 | |
|---|---|---|
| Work began, as filed | 4 Feb 2025 |
| Estimated cost, at registration | ₹22.09 Cr |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell, Local authority (Kannamangala Village) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 2.5 km to the south, tertiary drain | |
|---|---|---|
| Metro, operational | about 23 km, Peenya | |
| Metro, under construction | about 2.5 km, Doddajala |
| Kempegowda Airport | 11.5 | 7.5 |
| MG Road (CBD) | 30 | 26.5 |
| Manyata Tech Park | 25 | 18.5 |
| ITPL, Whitefield | 41.5 | 27.5 |
| Ecospace, Bellandur ORR | 45.5 | 32 |
| Electronic City Ph 1 | 49.5 | 41.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 0.5 km, named Sadahalli Quarry on OpenStreetMap | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 2 km |