Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Parkwest - Oak - Tower 10 is not plotted on the interactive atlas: its filing gives no coordinate precise enough to place a single building, only the surrounding locality.
•• ••• ••••
•••••
₹ •.•• Cr
Charges
Not verified yet
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Filed with the registration
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
Granted · Approved 4 Jul 2025
RERA completion date
30 Jun 2026
Registration certificates
PRM/KA/RERA/1251/310/PR/210216/003900
EX/PRM/KA/RERA/1251/310/PR/250704/003900
Not verified yet: Building plan, Land conversion, Validity, Conversion order.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Defect liability
5 years
Not verified yet: Forfeiture, allotment letter; Transfer fee; Maintenance included; Payment plan; Agreement for sale; Holding charge.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Unit mix filed; Unit types; Transactions in this project; Central Bengaluru, past year; Bengaluru, past year; Central Bengaluru since 2022; This project vs Central Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields; Months to sell unsold stock; K-RERA inventory.
Nearest storm drain
about 0.5 km from the locality centre, tertiary drain
Nearest lake, tank or pond
about 0.5 km from the locality centre, an unnamed water body
Amenities
Specification and Form 5
Electricity, built
30%
Gas, built
0%
Around it
Water
Groundwater, Bengaluru North taluk average
Ten-year July mean for this taluk: 26.8 m
Taluk average; not a reading at the site.
Water at a glance
Groundwater
Bengaluru North taluk average, July 2023: 22.7 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 7 CGWB wells in Bengaluru North taluk read in this class
Through the year
January 2025: 2.6 m (5 wells), Pre-monsoon 2025: 2.9 m (7 wells), August 2025: 3.2 m (7 wells), depth below ground of CGWB's monitoring wells in Bengaluru North taluk (the median where there are several)
Water supply, as filed
Self development
Distances
Approximate: locality level
Nuisances
Distance from the site
Locality only filed: no distance from the site to show
DOSL nuisance layer
Landfill or waste transfer station
about 2.5 km from the locality centre
Sewage treatment plant
about 1.5 km from the locality centre, named Kempabudhi Sewage Treatment Planet on OpenStreetMap
Quarry
None within 3 km of the locality centre
Crematorium
about 1.5 km from the locality centre, named Chamrajapet Crematorium on OpenStreetMap
Prison
None within 3 km of the locality centre
Electrical substation
about 1 km from the locality centre, named Telecom Layout Substation on OpenStreetMap
Not verified yet: Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Drains and lakes; Kitchen handover; Sewage plant; Power backup; Nearest city water main; Ground level; Metro, under construction; Road distance from the site; Six city anchors · OSRM, no traffic.
As the promoter reported it
Site photos filed with K-RERA, Q1 2026-27
Work left
By component, Q1 2026-27
Quarterly return, Q1 2026-27
Main structure
100% · planned by 21 Sep 2023
Electrical and plumbing finishing
40% · planned by 24 Aug 2024
Completion
74%
Completion, accountant
77.8% of the estimated cost spent
Dates
Dates
Filed dates
Schedule end
18 Jun 2025
RERA completion date
30 Jun 2026
!Review
Work began, as filed
1 Feb 2021
Specified structure
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Internal roads; Club house; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Design consultants (Form 6).
Land · ₹80.16 Cr 34%Development · ₹155.42 Cr 66%
Form 4
Estimated cost, at registration
₹235.58 Cr
Estimated cost, Form 4 Q1 2026-27
₹296.12 Cr
Cost incurred
₹230.39 Cr (77.8% of the Form 4 Q1 2026-27 estimate)
Cost left
₹65.72 Cr
Sales
Sold vs unsold, Q1 2026-27
Sold (222) 100%
Sold per quarter
K-RERA inventory
Sold, Q3 2025-26
222 / 222 · 0 available
Sold, Q4 2025-26
222 / 222 · 0 available
Sold, Q1 2026-27
222 / 222 · 0 available
Unsold, Q1 2026-27
0
Sold in Q4 2025-26
0
Sold in Q1 2026-27
0
Compliance
Escrow, Q1 2026-27
Escrow and filings
Escrow bank
HDFC · Rajajinagar, [name withheld] road
Designated account, collected
₹3.41 Cr in Q1 2026-27
Designated account, withdrawn
₹3.60 Cr in Q1 2026-27
Track record
Average schedule slip
DOSL builder track
K-RERA registrations under this promoter
11
Marked completed
5
Past promised date, not completed
4
Other phases under this promoter name
10
With a filed extension or completion
7 (5 completed, 2 extended)
Average schedule slip
20 months
Not verified yet: Receivable, sold flats; Cost left vs buyer dues; Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid.
Site photos, Q1 2026-27
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Records searched to; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.