Building plan (Local Planning Authority)Sanctioned 3 Jan 2024No. DPA/TP/LAO/01/2023-24
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted, 2 of 2 parcelsDates and authorities below
Permits
Approval letters
Building plan (Local Planning Authority)
Sanctioned 3 Jan 2024 · No. DPA/TP/LAO/01/2023-24
Power NOC
Filed with the registration
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
Locked
Forfeiture, agreement•• %
Forfeiture, allotment letterNot verified yet
Transfer feeNot verified yet
Maintenance includedNot verified yet
Cancellation
Forfeiture
•• %
•• %
•• %
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
The area
Comparable projects
Nearest 5 with filed prices
Location & risks
What is the location like?
Groundwater, taluk average11.4 m below groundYelahanka taluk, July 2023
Water supply, as filedBorewellDeclared by the promoter
Metro, operationalabout 17 kmNagasandra
Construction & progress
How is it being built, and when will it be ready?
CompletionNo return filed
Possession, agreement30 Jun 2026Agreement for sale, p. 8
Progress
Completion, architect
Completed: no quarterly return is on this phase's K-RERA filing
Work left
By component
Completed: no quarterly return is on this phase's K-RERA filing
Quarterly return
Completed: no quarterly return is on this phase's K-RERA filing
Developer
Can the developer deliver?
SoldNo return filed
Sold in the latest quarterNo return filed
Funding
Estimated cost
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan
Sanctioned 3 Jan 2024
Escrow bank
ICICI Bank · Wilson Garden
Stage
Certified progress
Completed: no quarterly return is on this phase's K-RERA filing
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Locked
164 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Contract & costs, Title & ownership, Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Worst builder experience ever. We purchased a flat at Raja Foursquares, and the level of negligence is unbelievable. Owners have to inform the builder more than 100 times about the same issue, and still, they simply ignore messages. We are…
AArsha F9 Jun 2025★★★★★
Raja Ira offers an impressive blend of modern design and natural surroundings. The villa layout, thoughtful amenities, and calm location near Yelahanka make it a standout choice for those seeking refined living.
BBinha Kameshe28 May 2025★★★★★
I recently booked a villa at Raja Ira, and the entire experience was seamless and reassuring. From the initial site visit to the final booking process, the team was extremely professional and supportive. I’m genuinely happy with my decision…
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Raja Ira in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
Not verified yet
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Fire department
Filed with the registration
SEIAA
Filed with the registration
AAI
Filed with the registration
Pollution board (CFE)
Filed with the registration
Water supply NOC
Filed with the registration
RERA
K-RERA
RERA extensions
None on the filing
RERA completion date
30 Jun 2026
Registration certificates
PRM/KA/RERA/1251/472/PR/180225/007513
Land use
Conversion order
Land conversion
2 of 2 parcels converted
Sy 66
Converted 9 Apr 2007 · The Special Deputy Commisioner, Bangalore District
Sy 68
Converted 25 Nov 2009 · The Special Deputy Commissioner, Bangalore District
Survey numbers
66 · 68
Not verified yet: Validity.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
•• %
•• %
Agreement and allotment letter
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Payments
Payment plan
Not verified yet
Agreement for sale
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Fees
Agreement for sale
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Not verified yet: Recent price, plot area; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, plot area; Form 4 certified totals; Agreements in the Form 4 sold list; Plot area vs rest, by type; Unit mix filed; Unit types; Transactions in this project; North Bengaluru, past year; Bengaluru, past year; North Bengaluru since 2022; This project vs North Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Plot price, plotted layouts within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
The site
Zoning & hazards
Power lines and drains around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400 and 66 kV
Its corridor, to scale
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Yelahanka taluk average, July 2023: 11.4 m below ground
What it means
10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class
Through the year
January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several)
Water supply, as filed
Borewell
Distances
Within 3 km of the filed pin
Connectivity
Road distance from the site
Nuisances
Distance from the filed pin
Not verified yet: Zoning, RMP 2015; Nearest high-tension line; Specification and Form 5; Nearest city water main; Ground level.
Dates
Dates
Filed dates
Possession, agreement
30 Jun 2026
RERA completion date
30 Jun 2026
Grace period for possession
6 months
Work began, as filed
1 May 2024
Specified structure
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Not verified yet: Structure; Structural safety certificate; Schedule end; What the promoter specified · not an inspection; Specification sheet · brands "or equivalent"; Structural engineer, quarterly; Design consultants (Form 6); Fire safety; Environmental clearance.
Land · ₹7.24 Cr 29.6%
Development · ₹17.20 Cr 70.4%
Form 4
Estimated cost, at registration
₹24.45 Cr
Estimated cost, architect's certificate
₹13.26 Cr
Estimated cost, engineer's certificate
₹10.12 Cr
Sales
Sold vs unsold
Completed: no quarterly return is on this phase's K-RERA filing
Sold per quarter
Completed: no quarterly return is on this phase's K-RERA filing
K-RERA inventory
Completed: no quarterly return is on this phase's K-RERA filing
Compliance
Escrow
Completed: no quarterly return is on this phase's K-RERA filing
Escrow and filings
Escrow bank
ICICI Bank · Wilson Garden
Track record
Average schedule slip
DOSL builder track
K-RERA registrations under this promoter
7
Marked completed
3
Past promised date, not completed
2
Other phases under this promoter name
6
With a filed extension or completion
4 (2 completed, 2 extended)
Average schedule slip
33 months
Not verified yet: Receivable, sold plots; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot