Has anyone got plot allotted and registered in this layout??? After meeting the executives i felt these are frauds trying to do some cheap marketing ..i was told it takes 6yrs for allotment
Overview
Sahakara North City
Overview
Sahakara North City
Overview
Sahakara North City
Overview
Photo: harinatha reddy reddyTitle & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BIAPPA) | Sanctioned 9 Aug 2021 · No. 63/2019-20 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹26.62 Cr 75.3%Development · ₹8.74 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 9 Jul 2024 | Review |
| Building plan (BIAPPA) | Sanctioned 9 Aug 2021 | |
| Escrow bank | BANK OF INDIA · Sahakaranagar (B’lore) Branch |
Data room
152 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 2 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 2 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
Has anyone got plot allotted and registered in this layout??? After meeting the executives i felt these are frauds trying to do some cheap marketing ..i was told it takes 6yrs for allotment
Can anyone tell is the society layouts are genuine and recieve the allotment. I am an young guy with all my little savings for my future of children sacrificing many things trying to invest in society layout. But looks there is greater risk
I don't know what happened. The project is now renamed to ARTH city and took over by dck builders whereas the original documents are under sai panchami developers. So what's their deal is not known. Not transparent. The launch of phase 2 in…
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | – | Review |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | 1 | – | Review |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sahakara North City in the interactive atlas
Approval or registration
Khata issued
A Khatha · Devanahalli · Survey 19
K-RERA filing, land schedule
Approval or registration
Land use converted
DC Office, Bangalore Rural · Survey 19, 20/6
K-RERA filing, land schedule
Covers 20/6 only
Approval or registration
Land use converted
DC Office, Bangalore Rural · Survey 19, 20/6
K-RERA filing, land schedule
Covers 20/1 only
Approval or registration
Land use converted
DC office, Bangalore Rural · Survey 20/1
K-RERA filing, land schedule
Covers 20/6 only
Approval or registration
Khata issued
A Khatha · Devanahalli · Survey 20/6
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BIAPPA · plan 63/2019-20
K-RERA filing, approvals
Covers 20/1 only
Transfer of the land
Sale deed
in favour of Sai Panchami Developers private Limited · Survey 20/1
K-RERA filing, land schedule
Covers 20/1 only
Approval or registration
Khata issued
A Khatha · Devanahalli · Survey 20/1
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1250/303/PR/200824/006976
K-RERA registration
Approval or registrationTransfer of the landTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 9 Jul 2024 |
|---|
| Developer's project loan | None declared |
|---|
Page 1
Page 1 of 4 of the encumbrance certificate. Filed with K-RERA: old EC SY NO 20-1, 4 pages, not in English.
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: sy no 20-6 sketch, 1 page.
| Filed survey numbers matched to the KGIS map | 2 of 2 | |
|---|---|---|
| Whole survey numbers on the KGIS map | 39,735 sq m | |
| Extent the filed land schedule names for these survey numbers | 27,417 sq m | |
| Plot area against the filed extent | 1.45 times | |
| Village, hobli and taluk on the KGIS map | K.G. Dyavarahalli, Kundana hobli, Devanahalli taluk | |
| Sy. 19: filed extent, KGIS plot | 14,265 sq m, 13,738 sq m | |
| Mutation entry | None open on 3 of 3 filed surveys |
Satellite map with the 2 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 2 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. Some drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Survey numbers | 19, 20/1, 20/6 | |
|---|---|---|
| Land extent, Sy 19 | 3 Acre 21 Guntas | |
| Land extent, Sy 20/1 | 1 Acre | |
| Land extent, Sy 20/6 | 2 Acre 10 Guntas | |
| Whole survey numbers on the KGIS map | 39,735 sq m (the project holds a share) | |
| Khata | A Khatha · Devanahalli · 10 Nov 2017; A Khatha · Devanahalli · 1 Dec 2023; A Khatha · Devanahalli · 10 Nov 2020 | |
| Sale deed | Dated 1 Dec 2023 | |
| Sale deed in favour of | Sai Panchami Developers private Limited |
| Survey | Owners as on the RTC, read date / relation / share | Owners on the RTC | RTC extent | Filed extent | Map extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|---|---|
| Sy. No. 19 | 1 | 3 acres 21 guntas | 3 acres 21 guntas | 3 acres 16 guntas | Yes | 0 | ||
| Sy. No. 20/1 | 1 | 1 acre | 0 | |||||
| Sy. No. 20/6 | 1 | 2 acres 10 guntas |
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 19 Apr 2024 |
| Land conversion | Converted 7 Feb 2020 · DC Office, Bangalore Rural | |
|---|---|---|
| Survey numbers | 19 · 20/1 · 20/6 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Map of 2 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Earth Aroma, price locked; Earth Aroma Phase-2, price locked.
| Earth Aroma | 1.9 km | Locked | |
|---|---|---|---|
| Earth Aroma Phase-2 | 2.0 km | Locked | |
| Fortius Good Earth | about 2.5 km | Locked | |
| Vaishnavi At-One Life IV | about 3 km | Locked | |
| Ekta Elements | 8.7 km | Locked |
| Sahakara North City This project | This project is the point the others are measured from | 19 Apr 2024 | – | Not verified yet |
|---|---|---|---|---|
| Earth Aroma | 1.9 km | 31 Dec 2024 | – | Locked |
| Earth Aroma Phase-2 | 2.0 km | 31 Dec 2025 | – | Locked |
| Fortius Good Earth | about 2.5 km | 31 Dec 2027 | – | Locked |
| Vaishnavi At-One Life IV | about 3 km | 18 Dec 2027 | – | Locked |
| Ekta Elements | 8.7 km | 31 Dec 2027 | – | Locked |
| Projects within 4 km, counted | 1 | |
|---|---|---|
| Plots in them | 95 | |
| Booked | 37 of 95 (39%) | |
| Unsold | 58 | |
| Booked a month, pooled | 3 plots | |
| Months to sell, pooled | 17 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture, at the filed pin | Review |
|---|---|---|
| Nearest government-flagged flood location | 14.7 km, Kondappa layout | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 50 m to the south, an unnamed water body |
| Possession, agreement | 19 Apr 2024 | |
|---|---|---|
| RERA completion date | 19 Apr 2024 | |
| Work began, as filed | 5 Jan 2022 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Architect's certificate, registration | Dated 12 Jun 2024 · site inspected 10 Jun 2024 | |
|---|---|---|
| Engineer's certificate, registration | Dated 12 Jun 2024 |
| Estimated cost, at registration | ₹35.37 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹7.92 Cr |
| Escrow bank | BANK OF INDIA · Sahakaranagar (B’lore) Branch |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell, BWSSB | |
| Nearest city water main | 11.3 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | None within 3 km | |
|---|---|---|
| Ground level | 924 m above sea level, plus or minus 4 m | |
| Metro, operational | 24.2 km, Dasarahalli | |
| Metro, under construction | 7.4 km, Doddajala |
| Kempegowda Airport | 19.3 | 25 | 12.1 |
| MG Road (CBD) | 35.1 | 39 | 29.7 |
| Manyata Tech Park | 30.2 | 34 | 22.0 |
| ITPL, Whitefield | 45.8 | 52 | 32.0 |
| Ecospace, Bellandur ORR | 50.6 | 59 | 36.2 |
| Electronic City Ph 1 | 54.9 | 63 | 45.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.3 km to the north-east |