Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Transfer of the land
Title deed executed
Consideration ₹18.60 Cr · Sy 45/5, Nagamangala village, Kundana hobli, Devanahalli taluk; Sy 45/9, Nagamangala village, Kundana hobli, Devanahalli taluk
Approvals
| Building plan (BIAPPA) | Sanctioned 16 Sep 2025 · No. BIAAPA/TP/LAO/22/2025-26 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹22.41 Cr 80.9%Development · ₹5.29 Cr 19.1%
Loan & collateral
| Building plan (BIAPPA) | Sanctioned 16 Sep 2025 |
|---|
Data room
84 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. 1 of 2 filed survey numbers matched, 1 found no plot. The village name is shared by several villages; the one nearest the filed coordinate was used.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | – | Review |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Serene Gardens Phase 3 in the interactive atlas
Title deed filed with K-RERA, pp. 1, 11, 16, 17 · See it in Documents
Transfer of the land
Title deed executed
Sy 45/5, Nagamangala village, Kundana hobli, Devanahalli taluk; Sy 45/9, Nagamangala village, Kundana hobli, Devanahalli taluk
Title deed filed with K-RERA, pp. 1, 7 · See it in Documents
Transfer of the land
Title deed registered
No. DBP-1-01891-2025-26 · Book 1 · executed 13 May 2025 · Consideration ₹21.00 Cr · Sy 45/5, Nagamangala village, Devanahalli taluk; Sy 45/9, Nagamangala village, Devanahalli taluk
Title deed filed with K-RERA, pp. 1, 4, 9, 11 · See it in Documents
Transfer of the land
Sale deed
in favour of M/s. Colaco Buildtech Pvt Ltd · Survey 45/5, 45/9
K-RERA filing, land schedule
Approval or registration
Khata issued
1 Acre 38.8 Guntas · Jalige Gram Panchayat · Survey 45/5, 45/9
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BIAPPA · plan BIAAPA/TP/LAO/22/2025-26
K-RERA filing, approvals
Approval or registration
Land use converted
DC Office, Bangalore Rural · Survey 45/5, 45/9
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1250/303/PR/170326/008535
K-RERA registration
Transfer of the landApproval or registrationThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Title opinion | Positive title opinion given |
|---|
Page 1
Page 1 of 1 of the survey sketch. Filed with K-RERA: Survey Sketch from ADLR - Nagamangala Sy 45-5 and 45-9, 1 page, not in English.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. 1 of 2 filed survey numbers matched, 1 found no plot. The village name is shared by several villages; the one nearest the filed coordinate was used.
| Survey numbers | 45/5, 45/9 | |
|---|---|---|
| Land extent, Sy 45/5 | 1 Acre 38.8 Guntas | |
| Land extent, Sy 45/9 | 1 Acre 38.8 Guntas | |
| Khata | 1 Acre 38.8 Guntas · Jalige Gram Panchayat · 17 Jun 2025 | |
| Sale deed | Dated 13 May 2025 | |
| Sale deed in favour of | M/s. Colaco Buildtech Pvt Ltd |
| Survey | Owners as on the RTC, read date / relation / share | Owners on the RTC | RTC extent | Filed extent | Map extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|---|---|
| Sy. No. 45/5 | 1 | 1 acre 38 guntas | 1 acre 39 guntas | 3 acres 35 guntas | The map differs by 1 acre 37 guntas | Not read yet | ||
| Sy. No. 45/9 | 1 | 1 acre 38 guntas | Not read yet |
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 5 Mar 2026 |
| Land conversion | Converted 18 Nov 2025 · DC Office, Bangalore Rural | |
|---|---|---|
| Survey numbers | 45/5 · 45/9 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Map of 2 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Earth Aroma Phase-2, price locked; Earth Aroma, price locked.
| Fortius Good Earth | about 2 km | Locked | |
|---|---|---|---|
| Earth Aroma Phase-2 | 2.8 km | Locked | |
| Vaishnavi At-One Life IV | about 3 km | Locked | |
| Earth Aroma | 3.2 km | Locked | |
| Ekta Elements | 5.1 km | Locked |
| Serene Gardens Phase 3 This project | This project is the point the others are measured from | 5 Mar 2026 | – | Not verified yet |
|---|---|---|---|---|
| Fortius Good Earth | about 2 km | 31 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | 2.8 km | 31 Dec 2025 | – | Locked |
| Vaishnavi At-One Life IV | about 3 km | 18 Dec 2027 | – | Locked |
| Earth Aroma | 3.2 km | 31 Dec 2024 | – | Locked |
| Ekta Elements | 5.1 km | 31 Dec 2027 | – | Locked |
| Projects within 4 km, counted | 20 (12 with an approximate location) | |
|---|---|---|
| Plots in them | 13,858 | |
| Booked | 9,070 of 13,858 (65%) | |
| Unsold | 4,788 | |
| Booked a month, pooled | 256 plots | |
| Months to sell, pooled | 18 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture | Review |
|---|---|---|
| Nearest government-flagged flood location | 11.9 km, Kondappa layout | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | 2.4 km to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 330 m to the north, an unnamed water body |
| RERA completion date | 5 Mar 2026 | |
|---|---|---|
| Work began, as filed | 16 Sep 2025 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Estimated cost, at registration | ₹27.71 Cr |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell, Local authority (Jalige Grama Panchayath) | |
| Nearest city water main | 7.9 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 2.4 km to the south, tertiary drain | |
|---|---|---|
| Ground level | 921 m above sea level, plus or minus 4 m | |
| Metro, operational | 22.3 km, Peenya | |
| Metro, under construction | 3.6 km, Doddajala |
| Kempegowda Airport | 13.8 | 18 | 9.1 |
| MG Road (CBD) | 31.9 | 36 | 26.6 |
| Manyata Tech Park | 27.1 | 31 | 18.8 |
| ITPL, Whitefield | 43.8 | 48 | 28.2 |
| Ecospace, Bellandur ORR | 47.4 | 56 | 32.6 |
| Electronic City Ph 1 | 51.7 | 60 | 42.1 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | 1.8 km to the east, named Sadahalli Quarry on OpenStreetMap | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.8 km to the south-east |