Photo: M.Lakshminarayana KPCCTitle & ownership
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 14 Aug 2019 |
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹40.0 L |
|---|
Loan & collateral
| Escrow bank | ICICI Bank · Sanjaynagar |
|---|
Data room
42 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sln Dreams Phase 4 in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Fortius Good Earth | about 4.5 km | Locked |
|---|
| Vaishnavi At-One Life IV | about 4.5 km | Locked |
|---|
| Ekta Elements | about 5 km | Locked |
|---|
| Earth Aroma Phase-2 | about 5.5 km | Locked |
|---|
| Earth Aroma | about 6 km | Locked |
|---|
| Sln Dreams Phase 4 This project | This project is the point the others are measured from | 14 Aug 2019 | – | Not verified yet |
|---|---|---|---|---|
| Fortius Good Earth | about 4.5 km | 31 Dec 2027 | – | Locked |
| Vaishnavi At-One Life IV | about 4.5 km | 18 Dec 2027 | – | Locked |
| Ekta Elements | about 5 km | 31 Dec 2027 | – | Locked |
| Earth Aroma Phase-2 | about 5.5 km | 31 Dec 2025 | – | Locked |
| Earth Aroma | about 6 km | 31 Dec 2024 | – | Locked |
| Projects within 4 km, counted | 25 (25 with an approximate location) | |
|---|---|---|
| Plots in them | 12,258 | |
| Booked | 7,494 of 12,258 (61%) | |
| Unsold | 4,764 | |
| Booked a month, pooled | 274 plots | |
| Months to sell, pooled | 15 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 8 km, Kondappa layout |
|---|
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Local authority |
| RERA completion date | 14 Aug 2019 | |
|---|---|---|
| Work began, as filed | 15 Aug 2018 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Escrow bank | ICICI Bank · Sanjaynagar |
|---|
| K-RERA registrations under this promoter | 6 | |
|---|---|---|
| Marked completed | 3 | |
| Past promised date, not completed | 2 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 19 km, Peenya | |
| Metro, under construction | about 2.5 km, Doddajala |
| Kempegowda Airport | 12.5 | 9.5 |
| MG Road (CBD) | 27 | 22.5 |
| Manyata Tech Park | 22 | 15 |
| ITPL, Whitefield | 35.5 | 25 |
| Ecospace, Bellandur ORR | 42.5 | 29 |
| Electronic City Ph 1 | 46.5 | 38.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 2.5 km to the north-east | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 2 km |