Overview
Surya Valencia Phase I
Part ofSurya Valencia2 phases, 122 flats
Overview
Surya Valencia Phase I
Part ofSurya Valencia2 phases, 122 flats
Overview
Surya Valencia Phase I
Part ofSurya Valencia2 phases, 122 flats
Overview
Part ofSurya Valencia2 phases, 122 flats
Title & ownership
Approvals
| Building plan (Local Planning Authority) | Sanctioned 8 Nov 2024 · No. DPA/TP/CC/197/24-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
Disputes & cases
Contract & costs
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Defect liability | 5 years |
|---|
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
4 BHK and 5 BHK 100%
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan | Sanctioned 8 Nov 2024 | |
| Escrow bank | ICICI Bank · Yelahanka New Town |
Data room
257 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 2 | 1 | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | – | – | – |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Surya Valencia Phase I in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Fire department |
|---|
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| Pollution board (CFE) | consent order CTE-344434 · issued 18 Jul 2024 |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2028 |
| Land conversion | 10 of 10 parcels converted | |
|---|---|---|
| Sy 200/7, 200/9, 200/10 | Converted 6 Mar 2023 · Deputy Commissioner Office, Bangalore | |
| Sy 201/2 | Converted 20 Mar 2023 · Deputy Commissioner Office, Bangalore | |
| Sy 200/11, 201/10 | Converted 29 May 2024 · Deputy Commissioner Office Bangalore | |
| Sy 201/1 | Converted 29 May 2024 · Deputy Cmmissioner Bangalore | |
| Sy 201/9, 201/8, 201/7 | Converted 6 Mar 2023 · Deputy Commissioner Office Bangalore | |
| Survey numbers | 200/7 · 200/9 · 200/10 · 201/2 · 200/11 · 201/1 · 201/9 · 201/10 · 201/8 · 201/7 |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Houses | Carpet, as filed (sq ft) |
|---|---|---|
| 4 BHK and 5 BHK | 44 | – |
| Sold, Q2 2026-27 | 33 / 44 | |
|---|---|---|
| Unsold, Q2 2026-27 | 11 | |
| Months to sell, derived from filed bookings | 8 months |
| Assetz Miru & Miyo | about 5 km | Locked | |
|---|---|---|---|
| Riviera Glade | about 7.5 km | Locked | |
| Century Kindle Phase 1 | 10.0 km | Locked | |
| Sattva City | 10.4 km | Locked | |
| Shriram Solitaire | about 10.5 km | Locked | |
| Godrej Aveline | 11.4 km | Locked | |
| Godrej MSR City | 11.6 km | Locked | |
| Tnm Lakeview | about 11.5 km | Locked | |
| Barca II At Godrej Msr City | about 12 km | Locked | |
| Sattva Vasanta Skye | 12.0 km | Locked |
| Surya Valencia Phase I This project | This project is the point the others are measured from | 31 Dec 2028 | 75% (33 of 44) | Not verified yet |
|---|---|---|---|---|
| Assetz Miru & Miyo | about 5 km | 31 Mar 2031 | 6% (20 of 350) | Locked |
| Riviera Glade | about 7.5 km | 31 Dec 2030 | 28% (31 of 112) | Locked |
| Century Kindle Phase 1 |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Agriculture, at the filed pin | Review |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 400 kV, 540 m from the filed location | Clear |
| Nearest government-flagged flood location | 10.4 km, Attur, Near Dairy Circle |
| Nearest storm drain | 1.7 km to the north-east, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 640 m to the south-west, an unnamed pond |
| Amenities declared | Electricity | |
|---|---|---|
| Electricity, built | 0% | |
| Parks, built | 0% | |
| Covered parking per unit | 2.00 (88 covered spaces for 44 units) | |
| Power backup | Not declared |
As the promoter reported it
| Main structure | 78% · planned by 20 Nov 2028 | |
|---|---|---|
| Electrical and plumbing finishing | 29% · planned by 1 Jul 2025 | |
| Completion | 68% | |
| Completion, accountant | 68.2% of the estimated cost spent |
| Schedule end | 31 Dec 2028 | |
|---|---|---|
| RERA completion date | 31 Dec 2028 | |
| Completion date, agreement | 31 Dec 2028 | |
| Work began, as filed | 8 Nov 2024 |
| Building heights, fire NOC | filed: Block 1 14 m, Block 2 Part A 14 m, Block 2 Part B 10.75 m, Block 3 10.75 m, Block 4 14 m |
|---|
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Not provided |
|---|
| Structural engineer, quarterly | Form 6 · Feb 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Architect, quarterly | Form 5 · Feb 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Engineer's certificate, registration | Dated 16 Nov 2024 | |
| Chartered accountant's certificate, registration | Dated 16 Nov 2024 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹65.83 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹64.45 Cr | |
| Estimated cost, Form 4 Q2 2026-27 | ₹65.83 Cr | |
| Cost incurred | ₹44.88 Cr (68.2% of the Form 4 Q2 2026-27 estimate) | |
| Cost left | ₹20.95 Cr | |
| Receivable, sold houses | ₹60.36 Cr |
Sold (33) 75%Unsold (11) 25%
| Sold, Q3 2025-26 | 21 / 44 · 23 available | |
|---|---|---|
| Sold, Q4 2025-26 | 24 / 44 · 20 available | |
| Sold, Q1 2026-27 | 28 / 44 · 16 available | |
| Sold, Q2 2026-27 | 33 / 44 · 11 available | |
| Unsold, Q2 2026-27 | 11 | |
| Sold in Q4 2025-26 | 3 | |
| Sold in Q1 2026-27 | 4 | |
| Sold in Q2 2026-27 | 5 | |
| 5 BHK, sold | 25 / 32 | |
| 4 BHK, sold | 8 / 12 | |
| Houses booked, Form 4 Q4 2025-26 | 24 |
| Escrow bank | ICICI Bank · Yelahanka New Town | |
|---|---|---|
| Designated account, collected | ₹34.32 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹29.32 Cr in Q2 2026-27 (85% of that quarter's deposits) | |
| Net amount withdrawable, Form 4 | ₹5,41,00,000 | |
| Escrow account, Q2 2026-27 | ₹3.26 Cr withdrawn | |
| Escrow account, Q1 2026-27 | Opened at ₹46.0 L | |
| Escrow account to date, Q4 2025-26 | ₹24.98 Cr deposited from sales, ₹24.52 Cr withdrawn | |
| Escrow account to date, Q3 2025-26 | Balance ₹68.0 L |
| K-RERA registrations under this promoter | 5 | |
|---|---|---|
| Marked completed | 1 | |
| Past promised date, not completed | 2 |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| 10.0 km |
| 14 Mar 2031 |
| 73% (336 of 458) |
| Locked |
| Sattva City | 10.4 km | 28 Feb 2032 | 17% (425 of 2,491) | Locked |
|---|
| Shriram Solitaire | about 10.5 km | 15 May 2026 | 100% (269 of 269) | Locked |
|---|
| Godrej Aveline | 11.4 km | 31 Mar 2031 | 91% (769 of 849) | Locked |
|---|
| Projects within 4 km, counted | 11 (11 with an approximate location) | |
|---|---|---|
| Houses in them | 2,138 | |
| Booked | 766 of 2,138 (36%) | |
| Unsold | 1,372 | |
| Booked a month, pooled | 24 houses | |
| Months to sell, pooled | 47 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Borewell | |
| Nearest city water main | 8.0 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 1.7 km to the north-east, tertiary drain | |
|---|---|---|
| Ground level | 891 m above sea level, plus or minus 4 m | |
| Metro, operational | 17.4 km, Manjunatha Nagar | |
| Metro, under construction | 9.4 km, Bettahalasuru |
| Kempegowda Airport | 24.9 | 32 | 17.2 |
| MG Road (CBD) | 30.2 | 34 | 25.5 |
| Manyata Tech Park | 23.1 | 29 | 18.8 |
| ITPL, Whitefield | 40.1 | 49 | 31.3 |
| Ecospace, Bellandur ORR | 45.7 | 55 | 33.6 |
| Electronic City Ph 1 | 50.0 | 59 | 42.4 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 2.5 km to the south |