Overview
Embassy Verde (Embassy Springs)
Overview
Embassy Verde (Embassy Springs)
Overview
Embassy Verde (Embassy Springs)
Overview

Title & ownership
Approvals
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 30 Oct 2024 | |
| Escrow bank | KOTAK MAHINDRA BANK · MG Road |
Data room
418 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 2 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 3 | – | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | 1 | 1 | Review |
| Loan & collateral | – | – | – | – |
Other sites that list or cover this project. DOSL does not vouch for them, and they can be older than the filing above.
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| AamayaActive · 7% built | SRK INFRA PROJECTS PRIVATE LIMITED | Plot | ~7,780–16,060 sqft (estimate: filed carpet plus 25%) | Jan 2029 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Abhi HomesExtended to 30-12-2026 | ABHI DEVELOPERS | Apartment | – | Dec 2026 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE | Plot | ~1,200–1,530 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
8 of 293 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
All 308 projects in Devanahalli → · Embassy Group's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Embassy Verde (Embassy Springs) in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (BIAPPA) | Sanctioned 30 Oct 2024 · No. 228/2023-24 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire NOC | KSFES/NOC/1021/2018 · building height 57.45 m | Clear |
| Environmental clearance | Filed with the registration | |
| Airport height NOC (1 of 2) | NOC ID BIAL/SOUTH/B/031121/533736 · issued 19 Mar 2021 · valid until 18 Mar 2029 | Clear |
| Airport height NOC (2 of 2) | issued 7 Apr 2021 · valid until 6 Apr 2029 | |
| Pollution board (CFE) | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2030 |
| Land conversion | 23 of 23 parcels converted | |
|---|---|---|
| Sy 57/3, 57/4 | Converted 8 Aug 2012 · DC office, Bangalore Rural | |
| Sy 58/1, 99, 100, 112, 122 | Converted 16 Jul 2012 · DC office, Bangalore Rural | |
| Sy 59/2, 109, 116 | Converted 10 Aug 2012 · DC office, Bangalore Rural | |
| Sy 59/3, 59/4, 59/5, 59/6, 59/7, 59/… | Converted 23 Aug 2012 · DC office, Bangalore Rural | |
| Sy 94, 96 | Converted 24 Aug 2012 · DC office, Bangalore Rural | |
| Sy 119 | Converted 30 Nov 2016 · DC office, Bangalore Rural | |
| Survey numbers | 57/3 · 57/4 · 58/1 · 59/2 · 59/3 · 59/4 · 59/5 · 59/6 · 59/7 · 59/8 · 94 · 95 · 96 · 97 · 99 · 100 · 103 · 106 · 109 · 112 · 116 · 119 · 122 |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
2BHK+2t · avg 60 m² 24.1%2.5BHK+2ts · avg 65 m² 20.7%1BHK+1t · avg 38 m² 20.7%3BHK+3t · avg 80 m² 17.2%2 other types 17.2%
| 1BHK+1t | 216 | 409 |
| 2.5BHK+2ts | 216 | 703 |
| 2BHK+2t | 252 | 648 |
| 2BHK+2ts | 72 | 700 |
| 3BHK+2t | 108 | 813 |
| 3BHK+3t | 180 | 863 |
| Sold, Q2 2026-27 | 1,043 / 1,044 | |
|---|---|---|
| Unsold, Q2 2026-27 | 1 | |
| Months to sell, derived from filed bookings | 0 months |
Map of 1 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Sattva City, price locked.
| Sattva City | 4.0 km | Locked | |
|---|---|---|---|
| Godrej MSR City | 4.6 km | Locked | |
| Sattva Vasanta Skye | 4.7 km | Locked | |
| Barca II At Godrej Msr City | about 5 km | Locked |
| Embassy Verde (Embassy Springs) This project | This project is the point the others are measured from | 31 Dec 2030 | 100% (1,043 of 1,044) | Not verified yet |
|---|---|---|---|---|
| Sattva City | 4.0 km | 28 Feb 2032 | 17% (425 of 2,491) | Locked |
| Godrej MSR City | 4.6 km | 31 Mar 2030 | 100% (1,957 of 1,961) | Locked |
| Sattva Vasanta Skye | 4.7 km | 6 May 2031 |
Map of the ground within about 450 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | 93% Agriculture, 5% Transport & communication | Review |
|---|---|---|
| Nearest high-tension line | A 220 kV line's corridor covers about 20% of the site (about 14,620 m²), with 2 transmission towers standing inside the outline | Review |
| Nearest government-flagged flood location | 11.0 km, Kondappa layout |
| Nearest storm drain | 1.7 km to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 650 m to the north, an unnamed tank |
| Amenities declared | Electricity · CCTV Surveillance · Power Backup · Water and Sanitation | |
|---|---|---|
| Club House, built | 0% | |
| Electricity, built | 0% | |
| Water and Sanitation, built | 0% | |
| Covered parking per unit | 0.69 (717 covered spaces for 1,044 units) | |
| Power backup | Declared by the promoter |
As the promoter reported it

| Main structure | Not started · planned by 8 Jul 2029 | |
|---|---|---|
| Electrical and plumbing finishing | Not started · planned by 28 May 2029 | |
| Club house | Not started | |
| Completion | 26% | |
| Completion, accountant | 40% of the estimated cost spent |
| Schedule end | 31 Dec 2030 | |
|---|---|---|
| RERA completion date | 31 Dec 2030 | |
| Work began, as filed | 1 Jan 2025 |
| Building heights, fire NOC | 57.45 m on the fire NOC · 60 m filed, 3 towers |
|---|
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Provided, 351 sq m |
|---|
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | KSFES/NOC/1021/2018 · building height 57.45 m | |
| Environmental clearance | Filed with the registration | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 30 Oct 2024 | |
| Engineer's certificate, registration | Dated 30 Oct 2024 | |
| Chartered accountant's certificate, registration | Dated 29 Oct 2024 | |
| Architect's quarterly progress certificate dated | 25 Jun 2026 | |
| Architect's site inspection for the quarterly progress certificate | 25 Jun 2026 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹74.00 Cr 13.7%Development · ₹466.39 Cr 86.3%
| Estimated cost, at registration | ₹540.39 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹435.68 Cr | |
| Estimated cost, Form 4 Q2 2026-27 | ₹679.33 Cr | |
| Cost incurred | ₹272.02 Cr (40% of the Form 4 Q2 2026-27 estimate) |
Sold (1,043) 99.9%Unsold (1) 0.1%
| Sold, Q3 2025-26 | 947 / 1,044 · 97 available | |
|---|---|---|
| Sold, Q4 2025-26 | 943 / 1,044 · 101 available | |
| Sold, Q1 2026-27 | 1,034 / 1,044 · 10 available | |
| Sold, Q2 2026-27 | 1,043 / 1,044 · 1 available | |
| Unsold, Q2 2026-27 | 1 | |
| Sold in Q4 2025-26 | 4 bookings cancelled or corrected (947 → 943 sold) | |
| Sold in Q1 2026-27 | 91 | |
| Sold in Q2 2026-27 | 9 | |
| Flats booked, Form 4 Q2 2026-27 | 1,036 |
| Escrow bank | KOTAK MAHINDRA BANK · MG Road | |
|---|---|---|
| Designated account, collected | ₹87.51 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹47.20 Cr in Q2 2026-27 (54% of that quarter's deposits) |
| K-RERA registrations under this promoter | 10 | |
|---|---|---|
| Marked completed | 3 | |
| Past promised date, not completed | 2 |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Sattva Vasanta Cove | 5.0 km | Locked |
|---|
| Riviera Glade | about 5.5 km | Locked |
|---|
| Birla Trimaya Phase-3 | 6.1 km | Locked |
|---|
| Varnam Phase 1c | about 6 km | Locked |
|---|
| Birla Trimaya Phase-2 | about 6 km | Locked |
|---|
| Aeropolis, A Project Of Sattva Group | about 6.5 km | Locked |
|---|
| Birla Trimaya | about 6.5 km | Locked |
|---|
| Sobha Oakshire Phase 1 Wing 1,2,7 And 8 | about 7.5 km | Locked |
|---|
| 28% (301 of 1,077) |
| Locked |
| Barca II At Godrej Msr City | about 5 km | 31 Dec 2030 | 99% (593 of 602) | Locked |
|---|
| Sattva Vasanta Cove | 5.0 km | 27 Dec 2030 | 14% (28 of 200) | Locked |
|---|
| Riviera Glade | about 5.5 km | 31 Dec 2030 | 28% (31 of 112) | Locked |
|---|
| Projects within 4 km, counted | 18 (13 with an approximate location) | |
|---|---|---|
| Flats in them | 10,704 | |
| Booked | 6,198 of 10,704 (58%) | |
| Unsold | 4,506 | |
| Booked a month, pooled | 235 flats | |
| Months to sell, pooled | 16 months |
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 1 of 5 CGWB wells in Devanahalli taluk read in this class | |
| Through the year | January 2024: 6.9 m (5 wells), Pre-monsoon 2024: 7.1 m (5 wells), August 2024: 6.8 m (5 wells), depth below ground of CGWB's monitoring wells in Devanahalli taluk (the median where there are several) | |
| Water supply, as filed | Borewell | |
| Nearest city water main | 7.3 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 1.7 km to the south, tertiary drain | |
|---|---|---|
| Ground level | 927 m above sea level, plus or minus 4 m | |
| Metro, operational | 21.2 km, Peenya | |
| Metro, under construction | 3.9 km, Doddajala |
| Kempegowda Airport | 14.2 | 19 | 10.1 |
| MG Road (CBD) | 31.4 | 35 | 25.8 |
| Manyata Tech Park | 26.6 | 31 | 18.1 |
| ITPL, Whitefield | 44.2 | 49 | 28.0 |
| Ecospace, Bellandur ORR | 46.9 | 56 | 32.1 |
| Electronic City Ph 1 | 51.2 | 60 | 41.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | 2.2 km to the south-east | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |