I got villa mr subramanyam reddy help me and he had guide me well
Overview
Nyra Sunterra
Overview
Nyra Sunterra
Overview
Nyra Sunterra
Overview
Photo: Nyra SunterraTitle & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
5BHK · 198 m² 51.7%5BHK · 196 m² 48.3%
Location & risks
Construction & progress
Developer
Land · ₹10.31 Cr 11.7%
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BMRDA) | Sanctioned 20 Oct 2023 | |
| Escrow bank | Axis Bank · Sarjapur road, BAN KT Branch |
Data room
141 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
I got villa mr subramanyam reddy help me and he had guide me well
Sales team are very good I got villa from them
Nyra Sunterra offers a rare blend of expansive villa-living with modern sustainability in Bangalore’s growing south corridor. With a limited set of 58 premium villas and features such as rooftop solar power and smart home-ready…
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| “the Sanctuary”Completed (regulator flag) | Classic Ventures LLP | Plot | – | Completed |
| 42 Queens SquareCompleted (regulator flag) | GRS INFRA | Plot | – | Completed |
| 77 EastLapsed · completion date passed | MODERN SPAACES | Apartment | – | Jan 2023 |
| 77 East Phase 2 By Modern Spaaces VenturesLapsed · completion date passed | MODERN SPAACES | Apartment | 1,010 sqft carpet (as filed) | Dec 2022 |
| 302 WestCompleted · OC 30-08-2023 | MODERN SPAACES VENTURES | Apartment | 735–1,398 sqft carpet (as filed) | Completed |
| 312 WestLapsed · completion date passed | MODERN SPAACES CONSTRUCTIONS | Apartment | 604 sqft carpet (as filed) | Apr 2022 |
| Aban DazzleRegistered · no quarterly update yet | ABAN DEVELOPERS PRIVATE LIMITED | Rowhouse | 2,040 sqft carpet (as filed) | Dec 2028 |
| Abhee Kings CourtCompleted · OC 26-05-2026 | ABHEE VENTURES PVT LTD | Apartment | 836–1,124 sqft carpet (as filed) | Completed |
8 of 191 other projects in Sarjapur, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Nyra Sunterra in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (BMRDA) | Sanctioned 20 Oct 2023 · No. STRRPA/TC/CC/42/2023-24 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| AAI | Filed with the registration | |
| Pollution board (CFE) | consent order CTE-123739 · issued 8 Jun 2023 · valid until 1 Jun 2028 | Clear |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 1 Jul 2027 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 83/10 | Converted 15 Nov 2022 · District commissioner | |
| Sy 83/11, 83/12 | Converted 5 Nov 2022 · District Commissioner | |
| Survey numbers | 83/10 · 83/11 · 83/12 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Type | Villas | Carpet per villa (sq ft) |
|---|---|---|
| 5BHK | 28 | 2,110 |
| 5BHK | 30 | 2,131 |
| Mitta Orrin | about 2.5 km | Locked | |
|---|---|---|---|
| Suyug's Saffron | about 4.5 km | Locked | |
| Mahidhara Harmony | about 4.5 km | Locked | |
| Engrace Vista | about 5 km | Locked | |
| Sowparnika Olivia Nest | about 5 km | Locked | |
| Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 | about 5 km | Locked | |
| Sobha Manhattan Towers-Town Park Phase 2 W 1 & 2 | about 5 km | Locked | |
| Engrace 4 | about 5 km | Locked | |
| Engrace 3 | about 5 km | Locked | |
| Sobha Hamptons -Townpark Phase 1 W4 To 6 | about 5 km | Locked | |
| Sobha Madison Heights-Townpark Phase 1 W5 To 7 | about 5 km | Locked | |
| Sobha Madison Heights-Townpark Phase 2 W1 To 4 | about 5 km | Locked |
| Nyra Sunterra This project | This project is the point the others are measured from | 1 Jul 2027 | – | Not verified yet |
|---|---|---|---|---|
| Mitta Orrin | about 2.5 km | 31 Dec 2027 | 46% (36 of 79) | Locked |
| Suyug's Saffron | about 4.5 km | 31 Dec 2028 | 8% (9 of 110) | Locked |
| Mahidhara Harmony | about 4.5 km | 10 Sep 2026 |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 12 km, Gunjur |
|---|
| Nearest storm drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed pond |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Indoor Sports facility · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Covered parking per unit | 1.00 (58 covered spaces for 58 units) | |
| Power backup | Declared by the promoter |
| Schedule end | 31 Dec 2026 | |
|---|---|---|
| RERA completion date | 1 Jul 2027 | |
| Work began, as filed | 1 Nov 2023 |
| Building heights, fire NOC | 9.6 m filed, 57 towers |
|---|
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Power backup | Provided, 15 sq m |
|---|
| Architect's certificate, registration | Dated 29 Dec 2023 · site inspected 29 Dec 2023 | |
|---|---|---|
| Engineer's certificate, registration | Dated 29 Dec 2023 | |
| Chartered accountant's certificate, registration | Dated 20 Dec 2023 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹87.80 Cr | |
|---|---|---|
| Estimated cost, architect's and chartered accountant's certificates | ₹87.80 Cr, same as the filing | |
| Estimated cost, engineer's certificate | ₹72.18 Cr |
| Escrow bank | Axis Bank · Sarjapur road, BAN KT Branch |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 62% (91 of 146) |
| Locked |
| Engrace Vista | about 5 km | 30 Dec 2028 | 46% (181 of 392) | Locked |
|---|
| Sowparnika Olivia Nest | about 5 km | 30 Sep 2027 | 100% (211 of 211) | Locked |
|---|
| Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 | about 5 km | 31 Dec 2026 | 100% (280 of 280) | Locked |
|---|
| Projects within 4 km, counted | 16 (16 with an approximate location) | |
|---|---|---|
| Villas in them | 3,657 | |
| Booked | 1,457 of 3,657 (40%) | |
| Unsold | 2,200 | |
| Booked a month, pooled | 73 villas | |
| Months to sell, pooled | 29 months |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 28.7 m
Taluk average; not a reading at the site.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class | |
| Through the year | January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several) | |
| Water supply, as filed | Borewell |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 9.5 km, Bommasandra | |
| Metro, under construction | about 15.5 km, Kadubeesanahalli |
| Kempegowda Airport | 58.5 | 42.5 |
| MG Road (CBD) | 37.5 | 25.5 |
| Manyata Tech Park | 39.5 | 30 |
| ITPL, Whitefield | 25 | 18.5 |
| Ecospace, Bellandur ORR | 21 | 15.5 |
| Electronic City Ph 1 | 19.5 | 11 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 2 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 3 km to the north-east |