As of 18 Nov 2026
New projects in Raipur, page 2
Chhattisgarh
939 projects are registered with the real estate regulator in Raipur, Chhattisgarh. 891 of them have enough filed detail for a full report here: who is building it, when it is due, and any court cases or complaints filed against it.
490 of the 891 are still filed as under construction, and 438 are already past the completion date their promoter filed. 412 have at least one complaint or court case filed against them.
Projects 101 to 200 of 891
| GOKUL TOWERPCGRERA050618000043 | Chhagan Lal Patel | – | Apartments | Under constructionpast its filed completion date | Jun 2018 | 84 |
| GOKULDHAM RESIDENCYPCGRERA130618000121 | Vijay Patel | – | Apartments | Under constructionpast its filed completion date | Dec 2018 | 132 |
| GOLDEN SANDSPCGRERA291218000884 | Nexus Devcon Private Limited | – | Apartments | Under construction | Dec 2026 | 49 |
| GOLDEN SKYPCGRERA060818000659 | K R Creations | – | Apartments | Under constructionpast its filed completion date | Dec 2018 | 192 |
| GOLDEN SKY IIPCGRERA090718000505 | K R Creations | – | Apartments | Under constructionpast its filed completion date | Mar 2019 | 72 |
| GOLDEN TOWERPCGRERA230718000624 | K R Creations | – | Apartments | Under constructionpast its filed completion date | Jun 2025 | 392 |
| GOLDEN TRADE CENTERPCGRERA160718000546 | Navkar Associates | – | Commercial | Under constructionpast its filed completion date | Dec 2018 | 324 |
| GOLF GREENPCGRERA140818000687 | A S Housing Company | – | Plots | Under constructionpast its filed completion date | Jan 2025 | 839 |
| GOLF GREEN PHASE-IIPCGRERA070323001617 | A S Housing Company | – | Plots | Registered | Mar 2027 | 367 |
| GOOD LUCK RESIDENCYPCGRERA180718000607 | Goodluck Global Private Limited | – | Plots | Under constructionpast its filed completion date | Mar 2025 | 302 |
| GORE PARISARPCGRERA160721001229 | Gore Parisar | – | Mixed | Registered | Jun 2024 | 110 |
| GOVINDA GREENPCGRERA210921001268 | Singhania Buildcon Private Limited | – | Plots | Registered | Sep 2024 | 41 |
| GREEN GLORYPCGRERA220618000283 | M. Ahuja Project India Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | May 2019 | 120 |
| GREEN VILLEY CITY BORIYAKALAPCGRERA040718000439 | Executive Engineer Chhattisgarh Housing Board Division 02 Raipur | – | Mixed | Under constructionpast its filed completion date | Nov 2021 | 840 |
| GT LIFE SPACESPCGRERA270418000009 | G T Homes | – | Apartments | Under constructionpast its filed completion date | Jul 2025 | 316 |
| GT UNI HOMESPCGRERA070219000912 | G T Homes | – | Plots | Registered | Sep 2022 | 56 |
| GULMOHAR PARKPCGRERA151018000804 | Ansons Buildcon | – | Plots | Under constructionpast its filed completion date | Jan 2022 | 53 |
| GULMOHAR PARKPCGRERA231018000823 | Shahid Bhagat Singh Nagar Grih Nirman Sahkari Samiti Mydt | – | Plots | Under constructionpast its filed completion date | Jan 2025 | 273 |
| GULSHAN VATIKA PHASE-IIPCGRERA090818000670 | Gulshan Vatika | – | Plots | Under constructionpast its filed completion date | Dec 2019 | 346 |
| GULZAR HOMESPCGRERA011218000863 | Aviva Constructions | – | Plots | Under constructionpast its filed completion date | Sep 2022 | 23 |
| HAMAR ANGNAPCGRERA111023001687 | Unitech Inferastructure | – | Plots | Registered | Dec 2028 | 101 |
| HAPPY HOMESPCGRERA221018000822 | Damodar Park | – | Plots | Under constructionpast its filed completion date | Jun 2019 | 140 |
| HARSH BHOOMIPCGRERA070718000488 | Singhania Goel Buildcon | – | Plots | Under construction | Jun 2029 | 961 |
| HARSH HORIZONPCGRERA160718000565 | Abhishek Buildcon | – | Apartments | Under constructionpast its filed completion date | Mar 2019 | 96 |
| HARSHIT HARMONYPCGRERA200618000241 | Singhania Buildcon Private Limited | – | Plots | Under constructionpast its filed completion date | Feb 2023 | 553 |
| HARSHIT HARMONY PHASE -IIP3CGRERA161118000013 | Singhania Buildcon Pvt. Ltd. | – | Apartments | Registered | Feb 2023 | 22 |
| HARSHIT LANDMARK (PHASE-I, BLOCK -A&B)PCGRERA160718000539 | Singhania Buildcon Private Limited | – | Mixed | Under constructionpast its filed completion date | Aug 2021 | 160 |
| HARSHIT LANDMARK (PHASE-II, BLOCK- C & D)PCGRERA270618000349 | Singhania Buildcon Private Limited | – | Mixed | Under constructionpast its filed completion date | Aug 2023 | 260 |
| HARSHIT LANDMARK (PHASE-III, BLOCK -E & F)PCGRERA270618000352 | Singhania Buildcon Private Limited | – | Mixed | Under construction | May 2028 | 112 |
| HARSHIT LANDMARK (PHASE-IV, BLOCK-G)PCGRERA270618000348 | Singhania Buildcon Private Limited | – | Mixed | Under construction | May 2028 | 119 |
| HIGH PARK PHASE - 2PCGRERA180619000989 | H.R.Developers | – | Apartments | Registered | Sep 2025 | 20 |
| HIGH PARK PHASE-IIIPCGRERA040322001352 | H.R.Developers | – | Apartments | Registered | Jan 2027 | 36 |
| HOUSING PROJECTS, VIP CITYPCGRERA130718000523 | Rcp Infratech Pvt Ltd | – | Apartments | Under constructionpast its filed completion date | Dec 2023 | 171 |
| ISHAAN HEIGHTSPCGRERA190221001199 | S R Construction | – | Mixed | Registered | May 2025 | 52 |
| JEEVAN PARISARPCGRERA051018000792 | Bharat Grih Nirman Sahkari Samiti Maryadit | – | Commercial | Under construction | May 2027 | 26 |
| KALPVRIKSHPCGRERA170718000584 | Geekay Colonizers And Builders Limited | – | Plots | Under constructionpast its filed completion date | Sep 2022 | 709 |
| KANCHAN VIHAR PHASE - IPCGRERA260618000340 | Kanchan Complexes Pvt Ltd | – | Apartments | Under constructionpast its filed completion date | Jul 2025 | 78 |
| KAVISH ENCLAVEPCGRERA060122001312 | Harivallabh Agrawal | – | Plots | Registered | Sep 2026 | 11 |
| KRISHNA GREENS (PHASE-1)PCGRERA030421001220 | Shree Krishna Colonisers | – | Apartments | Registered | Apr 2026 | 30 |
| KRISHNA LIFESTYLE COLONY PHASE-IPCGRERA110122001322 | Shree Krishna Developers | – | Apartments | Registered | Feb 2026 | 82 |
| KRISHNA VIHARPCGRERA180718000601 | Rajendra Kumar Pillai | – | Plots | Under construction | Dec 2026 | 68 |
| LALGANGA MIDASPCGRERA220618000290 | Lalganga Builders Pvt. Ltd. | – | Commercial | Under constructionpast its filed completion date | May 2025 | 159 |
| LAS VISTA, PHASE - IIPCGRERA280918000787 | Amrit Homes Private Limited | – | Plots | Under constructionpast its filed completion date | Dec 2018 | 8 |
| LOTUS TOWER PHASE IPCGRERA280618000378 | A. Dhebar Buildcon | – | Apartments | Under constructionpast its filed completion date | Nov 2021 | 256 |
| LOTUS TOWER PHASE IIPCGRERA280618000377 | A. Dhebar Buildcon | – | Apartments | Under constructionpast its filed completion date | Dec 2025 | 1,032 |
| LUXORA & EDGEPCGRERA130618000132 | Shri Balaji Developers | – | Mixed | Under constructionpast its filed completion date | Dec 2019 | 197 |
| M/S SHIVNATH APARTMENTSPCGRERA070322001353 | Shivnath Apartments | – | Apartments | Registered | Nov 2025 | 22 |
| MANGALAMPCGRERA200319000943 | Manglam Developers | – | Plots | Registered | Jul 2023 | 129 |
| MANJEET SMART HOMESPCGRERA150219000924 | Manjeet Buildcon | – | Apartments | Registered | Apr 2022 | 32 |
| MAPPLE TREEPCGRERA200618000256 | Aarambh Infraventures | – | Apartments | Under constructionpast its filed completion date | Jul 2023 | 67 |
| MARUTI LIFE STYLE TOWERPCGRERA131120001163 | Avinash Developers Pvt. Ltd. | – | Apartments | Registered | May 2027 | 252 |
| MARUTI LIFESTYLEPCGRERA290618000395 | Avinash Developers Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Dec 2018 | 21 |
| MAY FAIRPCGRERA180718000591 | Hariom Infratech | – | Apartments | Under constructionpast its filed completion date | Sep 2020 | 48 |
| MERLIN JAYSHREE VIHAR (PHASE-II)PCGRERA220618000287 | M/S Jayshree Builders | – | Apartments | Under construction | Apr 2028 | 24 |
| METRO GREENSPCGRERA130718000532 | Metro Infrastructures | – | Apartments | Under constructionpast its filed completion date | Mar 2024 | 52 |
| METRO HEXAPCGRERA160418000007 | M/S Shivay Infra | – | Apartments | Registered | Dec 2023 | 49 |
| METROPOLISPCGRERA201119001071 | Kanker Roadways | – | Commercial | Under constructionpast its filed completion date | Sep 2021 | 19 |
| MM SILVER PLAZAPCGRERA270618000342 | Mm Real Estate | – | Commercial | Under constructionpast its filed completion date | Dec 2018 | 60 |
| MOSAIC BUSINESS & COMMUNITY CENTREPCGRERA050718000473 | Mosaic Infraventures Pvt. Ltd. | – | Commercial | Under constructionpast its filed completion date | Dec 2024 | 443 |
| MOTI MAHAL PALLADIUMPCGRERA170718000583 | Moti Lal Agrawal | – | Commercial | Under constructionpast its filed completion date | Dec 2018 | 64 |
| NAKODAJEE ASSOCIATESPCGRERA200818000703 | Nakodajee Associates | – | Commercial | Under constructionpast its filed completion date | Dec 2018 | 80 |
| NAMO ENCLAVEPCGRERA281118000853 | Shree Vishwabharti Buildcon | – | Apartments | Under constructionpast its filed completion date | Dec 2019 | 71 |
| NARAYANIPCGRERA170718000576 | Ravi Prakash Gupta | – | Plots | Under construction | May 2028 | 255 |
| NAYA RAIPUR MUKHYAMANTRI AWAS YOJNA PMAY SECTOR-16PCGRERA070718000487 | Chhattisgarh Housing Board Cpd-1 | – | Apartments | Under constructionpast its filed completion date | Jan 2024 | 2,712 |
| NAYA RAIPUR MUKHYAMANTRI AWAS YOJNA PMAY SECTOR-30PCGRERA070718000493 | Chhattisgarh Housing Board Cpd-1 | – | Apartments | Under constructionpast its filed completion date | May 2025 | 1,376 |
| NAYA RAIPUR MUKHYAMANTRI AWAS YOJNA PMAY SECTOR-34PCGRERA050718000464 | Chhattisgarh Housing Board Cpd-1 | – | Apartments | Under constructionpast its filed completion date | Jan 2024 | 2,208 |
| NILAYAPCGRERA200618000259 | Arya Business Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Dec 2018 | 35 |
| NIRVANA GARDEN PHASE - 2PCGRERA250518000019 | Ashok Kumar Sharma | – | Plots | Under constructionpast its filed completion date | Jan 2024 | 124 |
| NIRVANA GARDEN PHASE- IPCGRERA250518000018 | Jsr Builder & Developers | – | Plots | Under constructionpast its filed completion date | Mar 2020 | 142 |
| NIRVANA GARDEN PHASE-3PCGRERA190719001011 | Ashok Kumar Sharma | – | Plots | Registered | Oct 2026 | 61 |
| OFFICER PARKPCGRERA161018000817 | Officers Park | – | Plots | Under constructionpast its filed completion date | Jun 2024 | 176 |
| OM EXOTICA VILLAP3CGRERA311225000043 | Om Real Estate | – | Apartments | Registered | Jul 2030 | 15 |
| OM RAJ ENCLAVEPCGRERA050718000462 | Arvind Bansal | – | Apartments | Under constructionpast its filed completion date | Sep 2023 | 37 |
| ORIENTAL BANK EMPLEYEES HOUSING COP.SOCIETY MYDT -PCGRERA080519000970 | Chandra Pratap Patel | – | Plots | Registered | Sep 2027 | 193 |
| ORIONPCGRERA121218000868 | Manakshya Builders & Developers | – | Apartments | Under constructionpast its filed completion date | Jun 2023 | 48 |
| ORRANGE ATMOSPHEREPCGRERA220722001474 | Orrange Infracon | – | Apartments | Registered | Jul 2027 | 60 |
| ORRANGE COUNTYPCGRERA170718000579 | Sankalp Associates | – | Apartments | Under constructionpast its filed completion date | Jul 2026 | 100 |
| ORRANGE HIVEPCGRERA260718000633 | Sankalp Associates | – | Commercial | Under constructionpast its filed completion date | Jul 2026 | 150 |
| OVERSEAS PALM RESORTSPCGRERA240218000002 | M/S Agrawal Construction And Contractors | – | Apartments | Under constructionpast its filed completion date | Sep 2022 | 156 |
| OXYGENPCGRERA210819001026 | Satpal Singh Gandhi | – | Commercial | Registered | Nov 2025 | 76 |
| PALM BELLAGIOPCGRERA200618000237 | Purandar Promoters & Developers Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Sep 2021 | 544 |
| PALM RESORTSPCGRERA290420001106 | M/S Agrawal Construction And Contractors | – | Apartments | Registered | May 2025 | 76 |
| PARAMPARAPCGRERA090126002025 | C.G. Buildcon Pvt. Ltd. | – | Plots | Registered | Nov 2030 | 86 |
| PARK GREENPCGRERA231119001073 | Geekay Construction Company | – | Plots | Under constructionpast its filed completion date | Jun 2024 | 771 |
| PARK SERENEPCGRERA130618000131 | Ashiyana Builders & Colonizers | – | Plots | Under constructionpast its filed completion date | Feb 2026 | 127 |
| PARTHIVI PACIFIC-ROYAL WOODSPCGRERA291018000830 | Parthivi Constructions Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Jun 2025 | 28 |
| PARTHIVI PROVINCE SARONAPCGRERA190618000233 | Parthivi Constructions Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Mar 2025 | 591 |
| PRAGATI PEARLPCGRERA280618000367 | Pragati Builders & Developers | – | Apartments | Under construction | Jul 2027 | 224 |
| QASBAPCGRERA200618000249 | Arya Business Pvt. Ltd. | – | Apartments | Under constructionpast its filed completion date | Dec 2018 | 8 |
| RADHA FLORENCE EMPIREPCGRERA250918000782 | Srs Fortune Estate And Developers Pvt. Ltd. | – | Plots | Under construction | May 2027 | 85 |
| RAHEJA RESIDENCYPCGRERA280618000375 | S P Buildcon Private Limited | – | Mixed | Under constructionpast its filed completion date | Jul 2018 | 472 |
| RAHEJA RIVIERAPCGRERA300326002076 | S P Buildcon Private Limited | – | Plots | Registered | Apr 2031 | 327 |
| RAHEJA WATERFRONT VILLASPCGRERA130326002055 | S P Buildcon Private Limited | – | Apartments | Registered | Apr 2031 | 27 |
| RAHEJA'S SKY SCAPESPCGRERA180718000592 | Deepak Raheja | – | Apartments | Under constructionpast its filed completion date | Jun 2021 | 94 |
| RAIS INFINITYPCGRERA230226002046 | M/S Rais Realty | – | Commercial | Registered | Mar 2027 | 44 |
| RAJDHANI VIHAR COLONYPCGRERA180718000593 | Surya Land Developers | – | Plots | Under constructionpast its filed completion date | Apr 2025 | 546 |
| RALAS ENCLAVEPCGRERA160718000556 | Ralas Infraventures | – | Mixed | Under constructionpast its filed completion date | Dec 2018 | 140 |
| RAM KUNJ (SECTOR - 1 & 2)PCGRERA080219000919 | Prachi Agriculture And Properties P Ltd | – | Plots | Registered | Jan 2027 | 365 |
| RAM RAMA RESIDENCYPCGRERA051018000795 | Vijaya Lakshmi Sharma | – | Plots | Under constructionpast its filed completion date | Mar 2019 | 95 |
| RAMKUTIRPCGRERA050618000033 | Mosh Varaya Inifrastructure Limited | – | Apartments | Under constructionpast its filed completion date | Jun 2022 | 199 |
Listed in order of how much each report can say, then by name. Status and completion dates are as each promoter filed them. Every project in Chhattisgarh